Detail Letting Schedule for Marion County (FY 2014)
Marion County (FY 2014) |
CCSJ: 0919-22-019 | |||
District: | Atlanta | Let Date: | SEP 2013 |
Highway: | CR | Let Status: | Actual |
Project ID: | BR 2002(373) | CSJ: | 0919-22-019 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | ON CR 113CC AT BLACK CYPRESS CREEK | Fund Cat: | 6 |
Limits To: | . | Estimate: | $265,518 |
Length: | 0.0 Miles | Actual: | $304,787 |
Back... |
Totals for 0919-22-019 | ||
---|---|---|---|
Length: | 0.0 Miles | ||
Estimate: | $265,518 | ||
Actual: | $304,787 | ||
CCSJ: 0919-22-031 | |||
District: | Atlanta | Let Date: | JAN 2014 |
Highway: | CR | Let Status: | Actual |
Project ID: | BR 1102(243) | CSJ: | 0919-22-031 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | ON CR 3306 AT HUNTS CREEK | Fund Cat: | 6 |
Limits To: | . | Estimate: | $213,106 |
Length: | 0.1 Miles | Actual: | $231,033 |
Back... |
Totals for 0919-22-031 | ||
Length: | 0.1 Miles | ||
Estimate: | $213,106 | ||
Actual: | $231,033 |
|