Detail Letting Schedule for Hudspeth County (FY 2014)
Hudspeth County (FY 2014) |
CCSJ: 0002-06-051 | |||
District: | El Paso | Let Date: | SEP 2013 |
Highway: | IH 10 | Let Status: | Actual |
Project ID: | IM 0101(266) | CSJ: | 0002-06-051 |
Description: | INSTALL MEDIAN BARRIER | Handling Code: |
|
Limits From: | 0.23 MI E OF FM 34 | Fund Cat: | 1 |
Limits To: | 8.38 MI W OF FM 1111 | Estimate: | $1,294,610 |
Length: | 10.8 Miles | Actual: | $1,024,270 |
District: | El Paso | Let Date: | SEP 2013 |
Highway: | IH 10 | Let Status: | Actual |
Project ID: | IM 0101(266) | CSJ: | 0002-07-044 |
Description: | INSTALL MEDIAN BARRIER | Handling Code: |
|
Limits From: | 8.38 MI W OF FM 1111 | Fund Cat: | 1 |
Limits To: | 5.18 MI W OF FM 1111 | Estimate: | $344,390 |
Length: | 3.2 Miles | Actual: | $251,475 |
District: | El Paso | Let Date: | SEP 2013 |
Highway: | IH 10 | Let Status: | Actual |
Project ID: | IM 0101(266) | CSJ: | 0002-08-051 |
Description: | INSTALL MEDIAN BARRIER | Handling Code: |
|
Limits From: | 0.18 MI W OF FM 1111 | Fund Cat: | 1 |
Limits To: | 8.82 MI E OF FM 1111 | Estimate: | $1,002,253 |
Length: | 9.8 Miles | Actual: | $727,525 |
District: | El Paso | Let Date: | SEP 2013 |
Highway: | IH 10 | Let Status: | Actual |
Project ID: | IM 0101(266) | CSJ: | 0002-09-038 |
Description: | INSTALL MEDIAN BARRIER | Handling Code: |
|
Limits From: | 8.82 MI E OF FM 1111 | Fund Cat: | 1 |
Limits To: | 9.43 M W OF HUDSPETH/CULBERSON CL | Estimate: | $928,440 |
Length: | 9.1 Miles | Actual: | $674,995 |
District: | El Paso | Let Date: | SEP 2013 |
Highway: | IH 10 | Let Status: | Actual |
Project ID: | IM 0101(266) | CSJ: | 0002-10-036 |
Description: | INSTALL MEDIAN BARRIER | Handling Code: |
|
Limits From: | 9.43 MI W OF HUDSPETH/CULBERSON CL | Fund Cat: | 1 |
Limits To: | 0.30 MI W OF HUDSPETH/CULBERSON CL | Estimate: | $839,240 |
Length: | 9.1 Miles | Actual: | $619,090 |
District: | El Paso | Let Date: | SEP 2013 |
Highway: | IH 10 | Let Status: | Actual |
Project ID: | IM 0101(266) | CSJ: | 0002-11-057 |
Description: | INSTALL MEDIAN BARRIER | Handling Code: |
|
Limits From: | 0.30 MI W OF HUDSPETH/CULBERSON CL | Fund Cat: | 1 |
Limits To: | 2.68 MI E OF HUDSPETH/CULBERSON CL | Estimate: | $228,510 |
Length: | 3.0 Miles | Actual: | $166,800 |
District: | El Paso | Let Date: | SEP 2013 |
Highway: | IH 10 | Let Status: | Actual |
Project ID: | IM 0101(266) | CSJ: | 2121-04-099 |
Description: | INSTALL MEDIAN BARRIER | Handling Code: |
|
Limits From: | 0.87 MI W OF FM 1281 | Fund Cat: | 1 |
Limits To: | 0.90 MI E OF FM 793 | Estimate: | $525,205 |
Length: | 13.4 Miles | Actual: | $399,465 |
District: | El Paso | Let Date: | SEP 2013 |
Highway: | IH 10 | Let Status: | Actual |
Project ID: | IM 0101(266) | CSJ: | 2121-05-045 |
Description: | INSTALL MEDIAN BARRIER | Handling Code: |
|
Limits From: | 0.90 MI E OF FM 793 | Fund Cat: | 1 |
Limits To: | 0.56 MI W OF FM 3380 | Estimate: | $238,400 |
Length: | 5.0 Miles | Actual: | $179,390 |
District: | El Paso | Let Date: | SEP 2013 |
Highway: | IH 10 | Let Status: | Actual |
Project ID: | IM 0101(266) | CSJ: | 2121-06-040 |
Description: | INSTALL MEDIAN BARRIER | Handling Code: |
|
Limits From: | 0.55 MI W OF SH 198 | Fund Cat: | 1 |
Limits To: | 0.31 MI W OF SH 20 | Estimate: | $312,160 |
Length: | 6.0 Miles | Actual: | $234,150 |
Back... |
Totals for 0002-06-051 | ||
---|---|---|---|
Length: | 69.4 Miles | ||
Estimate: | $5,713,208 | ||
Actual: | $4,277,160 |
|