Letting Schedule for Paris District (FY 2012)

 
 
Last Update: Monday, September 24, 2012
Paris District (FY 2012)
Fannin | Franklin | Grayson | Hopkins | Hunt | Lamar | Red River

Fannin County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0202-03-036 US 69 Actual SEP 2011 $2,572,631 1 HOT MIX OVERLAY
0202-03-037 US 69 Actual DEC 2011 $109,200 10 UPGRADE RR CROSSING PLANKING
0279-03-034 SH 78 Actual MAR 2012 $3,660,235 1 REHABILITATION OF EXISTING ROAD
0549-01-029 SH 121 Actual AUG 2012 $6,855,007 1 UPGRADE TO 5 LANE ROADWAY WITH SHOULDERS

Franklin County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0901-21-016 CR Actual OCT 2011 $340,261 6 REPLACE BRIDGE AND APPROACHES

Grayson County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0045-02-031 SH 56 Actual OCT 2011 $7,539,780 1 SEAL COAT
0045-03-045 SH 56 Actual JUL 2012 $610,186 3 SIDEWALK RECONSTRUCTION WITH LANDSCAPE PLANTING
0045-19-047 US 82 Actual AUG 2012 $26,059,262 3 WIDEN FROM 2 - LANE TO 4 - LANE DIVIDED
0047-02-132 SH 91 Actual APR 2012 $2,685,392 1 OVERLAY EXISTING PAVEMENT
0047-12-021 SH 91 Actual MAY 2012 $38,400 10 UPGRADE RXR CROSSING PLANKING TO CONCRETE
0091-01-046 SH 289 Actual MAY 2012 $4,252,949 8 ADD SHOULDERS
0202-08-051 FM 131 Actual APR 2012 $890,559 11 CONSTRUCT TURN LANES
0728-01-044 FM 120 Actual NOV 2011 $3,371,213 1 OVERLAY
0901-19-134 CR Actual JUN 2012 $546,773 6 REPLACE BRIDGE AND APPROACHES
0901-19-154 CR Actual FEB 2012 $405,435 6 REPLACE BRIDGE AND APPROACHES
0901-19-172 PW Actual MAY 2012 $1,172,197 10 REPAIR PAVEMENT AND OVERLAY; CONSTRUCT SECONDARY ENTRANCE
0901-19-175 CS Actual AUG 2012 $4,500 8 INSTALL STOP SIGNS AND STOP LINE AT RAILROAD CROSSINGS
1855-02-007 FM 922 Actual OCT 2011 $746,251 1 REHABILITATION OF EXISTING ROAD
2454-01-009 FM 131 Actual MAY 2012 $1,658,502 1 REHABILITATE EXISTING ROADWAY
2459-02-010 FM 902 Actual DEC 2011 $883,742 8 WIDEN ROADWAY
2640-02-007 FM 406 Actual OCT 2011 $2,569,783 1 REHABILITATION OF EXISTING ROAD

Hopkins County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0009-09-097 IH 30 Actual APR 2012 $2,799,967 1 MILL, OVERLAY AND PFC OVERLAY
0010-02-090 IH 30 Actual MAR 2012 $1,478,967 6 REPLACE BRIDGE AND APPROACHES
0083-02-049 SH 11 Actual APR 2012 $2,433,158 11 REHAB WITH SHOULDERS
0901-28-084 CR Actual AUG 2012 $179,000 8 INSTALL RAILROAD LIGHTS AND GATES

Hunt County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0009-06-049 SH 66 Actual DEC 2011 $51,200 10 RAILROAD REPLANKING
0009-07-042 SP 302 Actual MAY 2012 $44,800 10 UPGRADE RXR CROSSING PLANKING TO CONCRETE
0641-01-033 SH 276 Actual JUL 2012 $47,845,879 3 REPLACE BRIDGE AND APPROACHES
0642-03-019 FM 36 Actual AUG 2012 $1,731,836 1 REHAB EXIST ROAD
0726-01-028 FM 118 Actual MAY 2012 $52,800 10 UPGRADE RXR CROSSING PLANKING TO CONCRETE
0901-22-083 CR Actual JUN 2012 $611,116 6 REPLACE BRIDGE AND APPROACHES

Lamar County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0136-07-048 US 271 Actual AUG 2012 $3,275,793 1 REHABILITATION OF EXISTING ROAD
0901-00-051 VA Actual FEB 2012 $1,629,779 10 CONSTRUCT CURB RAMPS FOR ADA COMPLIANCE
1690-01-111 LP 286 Actual DEC 2011 $89,600 10 RAILROAD CROSSING REPLANKING

Red River County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0189-01-007 SH 37 Actual AUG 2012 $14,580,057 3 REPLACE BRIDGE
0901-27-042 CR Actual DEC 2011 $866,123 6 REPLACE BRIDGE AND APPROACHES


Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract