Detail Letting Schedule for Galveston County (FY 2012)
Detail Letting Schedule for Galveston County (FY 2012) | ||||
Last Update: Monday, September 24, 2012 |
Galveston County (FY 2012) |
CCSJ: 0051-09-025 | |||
District: | Houston | Let Date: | SEP 2011 |
Highway: | FM 3005 | Let Status: | Actual |
Project ID: | STP 2012(018) | CSJ: | 0051-09-025 |
Description: | PLANE, ACP OVERLAY AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | WEST END OF GALVESTON SEAWALL | Fund Cat: | 1 |
Limits To: | SPUR 342 (61ST STREET) | Estimate: | $1,557,562 |
Length: | 2.9 Miles | Actual: | $1,274,439 |
Back... |
Totals for 0051-09-025 | ||
---|---|---|---|
Length: | 2.9 Miles | ||
Estimate: | $1,557,562 | ||
Actual: | $1,274,439 | ||
CCSJ: 0192-04-102 | |||
District: | Houston | Let Date: | MAY 2012 |
Highway: | SH 6 | Let Status: | Actual |
Project ID: | NH 2012(508) | CSJ: | 0192-04-102 |
Description: | BASE REPAIR, SEAL COAT & ACP OVERLAY | Handling Code: |
|
Limits From: | FM 1764 | Fund Cat: | 1 |
Limits To: | BRAZORIA COUNTY LINE | Estimate: | $3,361,046 |
Length: | 5.4 Miles | Actual: | $3,221,796 |
Back... |
Totals for 0192-04-102 | ||
Length: | 5.4 Miles | ||
Estimate: | $3,361,046 | ||
Actual: | $3,221,796 | ||
CCSJ: 0389-06-101 | |||
District: | Houston | Let Date: | MAY 2012 |
Highway: | SH 146 | Let Status: | Actual |
Project ID: | STP 2012(512)HES | CSJ: | 0389-06-101 |
Description: | ADD LEFT TURN LANE | Handling Code: |
|
Limits From: | AT FM 1764 | Fund Cat: | 8 |
Limits To: | . | Estimate: | $117,260 |
Length: | 0.1 Miles | Actual: | $98,935 |
Back... |
Totals for 0389-06-101 | ||
Length: | 0.1 Miles | ||
Estimate: | $117,260 | ||
Actual: | $98,935 | ||
CCSJ: 0500-01-140 | |||
District: | Houston | Let Date: | JUL 2012 |
Highway: | IH 45 | Let Status: | Actual |
Project ID: | IM 0451(343) | CSJ: | 0500-01-140 |
Description: | ASPHALT CONCRETE PAVEMENT OVERLAY | Handling Code: |
|
Limits From: | SOUTH END CAUSEWAY | Fund Cat: | 1 |
Limits To: | HARBOR SIDE DRIVE | Estimate: | $544,664 |
Length: | 0.4 Miles | Actual: | $626,034 |
Bid Tabulations Back... |
Totals for 0500-01-140 | ||
Length: | 0.4 Miles | ||
Estimate: | $544,664 | ||
Actual: | $626,034 | ||
CCSJ: 0500-04-125 | |||
District: | Houston | Let Date: | JUN 2012 |
Highway: | IH 45 | Let Status: | Actual |
Project ID: | CM 2012(600) | CSJ: | 0500-04-125 |
Description: | INSTALL LEFT TURN LANES | Handling Code: |
|
Limits From: | AT FM 646 NORTHBOUND AND SOUTHBOUND | Fund Cat: | 1 |
Limits To: | . | Estimate: | $459,206 |
Length: | 0.4 Miles | Actual: | $473,737 |
Back... |
Totals for 0500-04-125 | ||
Length: | 0.4 Miles | ||
Estimate: | $459,206 | ||
Actual: | $473,737 | ||
CCSJ: 0686-01-047 | |||
District: | Houston | Let Date: | APR 2012 |
Highway: | FM 1765 | Let Status: | Actual |
Project ID: | STP 2012(445)HES | CSJ: | 0686-01-047 |
Description: | IMPROVE TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | AT 34TH STREET S | Fund Cat: | 8 |
Limits To: | . | Estimate: | $144,774 |
Length: | 0.0 Miles | Actual: | $142,457 |
Back... |
Totals for 0686-01-047 | ||
Length: | 0.0 Miles | ||
Estimate: | $144,774 | ||
Actual: | $142,457 | ||
CCSJ: 0686-02-025 | |||
District: | Houston | Let Date: | APR 2012 |
Highway: | FM 1765 | Let Status: | Actual |
Project ID: | STP 2012(461) | CSJ: | 0686-02-025 |
Description: | BASE REPAIR, 1.5" ACP OVERLAY AND PAVEMENT MARKINGS | Handling Code: |
|
Limits From: | IH 45 | Fund Cat: | 1 |
Limits To: | FM 2004 | Estimate: | $539,045 |
Length: | 1.9 Miles | Actual: | $464,138 |
Back... |
Totals for 0686-02-025 | ||
Length: | 1.9 Miles | ||
Estimate: | $539,045 | ||
Actual: | $464,138 | ||
CCSJ: 0976-03-095 | |||
District: | Houston | Let Date: | DEC 2011 |
Highway: | FM 518 | Let Status: | Actual |
Project ID: | CRX 976-3-95 | CSJ: | 0976-03-095 |
Description: | FY 2008 RAILROAD GRADE CROSSING REPLANKING PROGRAM | Handling Code: |
XX |
Limits From: | UPRR RR IN LEAGUE CITY AT MAIN ST | Fund Cat: | 10 |
Limits To: | . | Estimate: | $120,320 |
Length: | 0.0 Miles | Actual: | $120,320 |
Back... |
Totals for 0976-03-095 | ||
Length: | 0.0 Miles | ||
Estimate: | $120,320 | ||
Actual: | $120,320 | ||
CCSJ: 0976-03-097 | |||
District: | Houston | Let Date: | APR 2012 |
Highway: | FM 518 | Let Status: | Actual |
Project ID: | NH 2012(465) | CSJ: | 0976-03-097 |
Description: | BASE REPAIR, MILLING & ACP OVERLAY | Handling Code: |
|
Limits From: | W OF FM 2351 | Fund Cat: | 1 |
Limits To: | CASTLEWOOD | Estimate: | $851,839 |
Length: | 1.2 Miles | Actual: | $824,471 |
Back... |
Totals for 0976-03-097 | ||
Length: | 1.2 Miles | ||
Estimate: | $851,839 | ||
Actual: | $824,471 | ||
CCSJ: 0976-07-011 | |||
District: | Houston | Let Date: | APR 2012 |
Highway: | SH 96 | Let Status: | Actual |
Project ID: | STP 2012(517) | CSJ: | 0976-07-011 |
Description: | MILL SEAL COAT, BASE REPAIR & ACP OVERLAY | Handling Code: |
|
Limits From: | SH 3 | Fund Cat: | 1 |
Limits To: | SH 146 | Estimate: | $4,202,252 |
Length: | 4.5 Miles | Actual: | $3,978,629 |
Back... |
Totals for 0976-07-011 | ||
Length: | 4.5 Miles | ||
Estimate: | $4,202,252 | ||
Actual: | $3,978,629 | ||
CCSJ: 1607-02-021 | |||
District: | Houston | Let Date: | FEB 2012 |
Highway: | FM 1764 | Let Status: | Actual |
Project ID: | STP 2012(303) | CSJ: | 1607-02-021 |
Description: | MILLING, OCST & ACP OVERLAY | Handling Code: |
|
Limits From: | WEST OF IH 45 | Fund Cat: | 1 |
Limits To: | CONCRETE SECTION | Estimate: | $390,420 |
Length: | 0.5 Miles | Actual: | $395,632 |
Back... |
Totals for 1607-02-021 | ||
Length: | 0.5 Miles | ||
Estimate: | $390,420 | ||
Actual: | $395,632 | ||
CCSJ: 3049-01-028 | |||
District: | Houston | Let Date: | SEP 2011 |
Highway: | FM 646 | Let Status: | Actual |
Project ID: | NH 2012(024) | CSJ: | 0978-02-066 |
Description: | BASE REPAIR, OCST AND OVERLAY | Handling Code: |
|
Limits From: | FM 3436 | Fund Cat: | 1 |
Limits To: | SH 146 | Estimate: | $527,589 |
Length: | 0.8 Miles | Actual: | $465,470 |
District: | Houston | Let Date: | SEP 2011 |
Highway: | FM 646 | Let Status: | Actual |
Project ID: | NH 2012(024) | CSJ: | 3049-01-028 |
Description: | BASE REPAIR, OCST AND OVERLAY | Handling Code: |
|
Limits From: | SH 3 | Fund Cat: | 1 |
Limits To: | FM 3436 | Estimate: | $2,152,923 |
Length: | 4.2 Miles | Actual: | $1,876,271 |
Back... |
Totals for 3049-01-028 | ||
Length: | 5.0 Miles | ||
Estimate: | $2,680,512 | ||
Actual: | $2,341,741 | ||
CCSJ: 3595-01-015 | |||
District: | Houston | Let Date: | DEC 2011 |
Highway: | SH 275 | Let Status: | Actual |
Project ID: | CRX 3595-1-15 | CSJ: | 3595-01-015 |
Description: | FY 2010 RAILROAD GRADE CROSSING REPLANKING PROGRAM | Handling Code: |
XX |
Limits From: | SH 275(HARBOUR SIDE DR) AT BNSF | Fund Cat: | 10 |
Limits To: | . | Estimate: | $112,000 |
Length: | 0.0 Miles | Actual: | $112,000 |
Back... |
Totals for 3595-01-015 | ||
Length: | 0.0 Miles | ||
Estimate: | $112,000 | ||
Actual: | $112,000 |
|
|