COUNTY: STARR HIGHWAY: US 83 LENGTH: 4.17MI CONTROL NUMBER: 0038-06-047 DBE GOAL: 0.0 % PROJECT NUMBER: F 2B24(195) TYPE: WIDEN NON-FREEWAY TIME FOR COMPLETION: 484 WORKING DAYSGUARANTY: 100,000.00 BIDS RECEIVED UNTIL: 1:00 PM JUNE 05, 2024*EST.COST: 38,517,487.52 BIDS WILL BE OPENED: 1:00 PM JUNE 05, 2024 MAIL OR DELIVER BIDS TO: FOR PS&E PACKAGE QUESTIONS CALL: TEXAS DEPARTMENT OF TRANSPORTATIONFRANCISCO CANTU ATTN: CONSTRUCTION DIVISION - RM M1C3.02 600 W US 83 EXPRESSWAY 6230 E. STASSNEY LANEPHARR, TX 78577 AUSTIN TX 78744-3147956/702-6155 FOR QUESTIONS REGARDING A PROPOSAL CALL 512/416-2498 TO REQUEST A PROPOSAL GO TO http://www.dot.state.tx.us/business/pr.htm FOR ELECTRONIC BIDDING VISIT THE WEBSITE BELOW: http://www.txdot.gov/business/letting-bids/ebs.html LIMITS FROM: 0.31 MI SOUTH OF MARGARITO RD. LIMITS TO: 0.09 MI NORTH OF LOMA BLANCA RD. ------------------------------------------------------------------------------------------------------------- ITEM DESAPPROXIMATE ALT NO. CD. ITEM DESCRIPTIONUNITQUANTITIESBID PRICEAMOUNTSEQ ------------------------------------------------------------------------------------------------------------- 100 6002PREPARING ROWSTA 220.3001 100 6006PREP ROW (TREE)(LESS THAN 24" DIA)EA 82.0002 100 6007PREP ROW (TREE)(GREATER THAN 24" DIA)EA 11.0003 104 6009REMOVING CONC (RIPRAP)SY 1,529.0004 104 6017REMOVING CONC (DRIVEWAYS)SY 748.0005 104 6037REMOVE CONC (RAIL)LF 253.0006 104 6054REMOVING CONCRETE(MOW STRIP)LF 2,242.0007 105 6026REMOVE STAB BASE & ASPH PAV (13"-18")SY 44,887.0008 110 6001EXCAVATION (ROADWAY)CY 73,852.0009 110 6002EXCAVATION (CHANNEL)CY 4,404.00010 132 6006EMBANKMENT (FINAL)(DENS CONT)(TY C)CY 125,052.00011 160 6003FURNISHING AND PLACING TOPSOIL (4")SY 196,001.00012 164 6021CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)SY 196,001.00013 164 6029CELL FBR MLCH SEED(TEMP)(WARM)SY 98,002.00014 168 6001VEGETATIVE WATERINGMG 3,142.00015 169 6002SOIL RETENTION BLANKETS (CL 1) (TY B)SY 13,048.00016 169 6008SOIL RETENTION BLANKETS (CL 2) (TY H)SY 6,641.00017 192 6002PLANT MATERIAL (1-GAL)EA 400.00018 192 6004PLANT MATERIAL (5-GAL)EA 154.00019 193 6001PLANT MAINTENANCEMO 9.00020 204 6003SPRINKLING (DUST CONTROL)MG 1,322.00021 216 6001PROOF ROLLINGHR 40.00022 247 6225FL BS (RDWY DEL)(TY E GR 4)(FNAL POS)CY 43,662.00023 260 6043LIME (HYD, COM OR QK)(SLURRY)TON 1,388.00024 260 6079LIME TRT (SUBGRADE)(6")SY 163,248.00025 275 6001CEMENTTON 2,222.00026 275 6031CEMENT TREAT (NEW BASE) (10")SY 157,184.00027 305 6004SALV, HAUL & STKPL RCL APH PV (4 TO 6")SY 66,192.00028 310 6009PRIME COAT (MC-30)GAL 30,955.00029 354 6045PLANE ASPH CONC PAV (2")SY 55,164.00030 400 6005CEM STABIL BKFLCY 1,120.60031 400 6010STRUCT EXCAV (SPECIAL)CY 252.00032 400 6011SAND BACKFILLCY 359.00033 402 6001TRENCH EXCAVATION PROTECTIONLF 43.00034 403 6001TEMPORARY SPL SHORINGSF 1,036.00035 416 6001DRILL SHAFT (18 IN)LF 454.00036 416 6004DRILL SHAFT (36 IN)LF 3,979.00037 420 6012CL B CONC (MISC)CY 359.00038 420 6013CL C CONC (ABUT)CY 234.80039 420 6029CL C CONC (CAP)CY 252.20040 420 6037CL C CONC (COLUMN)CY 125.20041 420 6066CL C CONC (RAIL FOUNDATION)CY 220.00042 422 6001REINF CONC SLABSF 41,250.00043 422 6015APPROACH SLABCY 597.20044 423 6001RETAINING WALL (MSE)SF 17,689.00045 425 6036PRESTR CONC GIRDER (TX34)LF 5,544.61046 432 6002RIPRAP (CONC)(5 IN)CY 2,253.00047 432 6023RIPRAP (STONE COMMON)(DRY)(8 IN)CY 91.00048 432 6032RIPRAP (STONE PROTECTION)(15 IN)CY 570.00049 432 6033RIPRAP (STONE PROTECTION)(18 IN)CY 1,629.00050 432 6044RIPRAP (CONC)(FLUME)CY 39.00051 432 6045RIPRAP (MOW STRIP)(4 IN)CY 337.00052 432 6047RIPRAP (MOW STRIP)(6 IN)CY 51.20053 450 6006RAIL (TY T223)LF 132.00054 450 6023RAIL (TY SSTR)LF 4,031.25055 450 6054RAIL (TY SSTR) (W/DRAIN SLOTS)LF 1,078.00056 454 6018SEALED EXPANSION JOINT (4 IN) (SEJ - M)LF 538.00057 462 6001CONC BOX CULV (3 FT X 2 FT)LF 554.00058 462 6005CONC BOX CULV (4 FT X 4 FT)LF 531.00059 462 6015CONC BOX CULV (7 FT X 4 FT)LF 252.00060 462 6034CONC BOX CULV (10 FT X 10 FT)LF 200.00061 462 6049CONC BOX CULV (4 FT X 4 FT)(EXTEND)LF 102.00062 464 6017RC PIPE (CL IV)(18 IN)LF 292.00063 464 6018RC PIPE (CL IV)(24 IN)LF 2,186.00064 464 6020RC PIPE (CL IV)(36 IN)LF 85.00065 465 6079INLET (COMPL)(PSL)(RG)(4FTX4FT)EA 1.00066 465 6126INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT)EA 8.00067 465 6128INLET (COMPL)(PSL)(FG)(4FTX4FT-4FTX4FT)EA 1.00068 465 6178INLET (COMPL)(TY MSE1)EA 4.00069 466 6097HEADWALL (CH - PW - 0) (DIA= 24 IN)EA 1.00070 466 6101HEADWALL (CH - PW - 0) (DIA= 36 IN)EA 1.00071 466 6152WINGWALL (FW - 0) (HW=5 FT)EA 1.00072 466 6153WINGWALL (FW - 0) (HW=6 FT)EA 1.00073 466 6160WINGWALL (FW - S) (HW=13 FT)EA 1.00074 466 6166WINGWALL (FW - S) (HW=5 FT)EA 2.00075 466 6174WINGWALL (PW - 1) (HW=13 FT)EA 1.00076 466 6180WINGWALL (PW - 1) (HW=5 FT)EA 1.00077 466 6181WINGWALL (PW - 1) (HW=6 FT)EA 2.00078 466 6182WINGWALL (PW - 1) (HW=7 FT)EA 2.00079 466 6183WINGWALL (PW - 1) (HW=8 FT)EA 1.00080 467 6107SET (TY I)(S=3 FT)(HW=3FT)(4:1)(P)EA 16.00081 467 6363SET (TY II) (18 IN) (RCP) (6: 1) (P)EA 9.00082 467 6388SET (TY II) (24 IN) (RCP) (3: 1) (C)EA 2.00083 467 6390SET (TY II) (24 IN) (RCP) (4: 1) (C)EA 4.00084 467 6391SET (TY II) (24 IN) (RCP) (4: 1) (P)EA 7.00085 467 6395SET (TY II) (24 IN) (RCP) (6: 1) (P)EA 48.00086 480 6001CLEAN EXIST CULVERTSEA 5.00087 496 6001REMOV STR (BOX CULVERT)EA 1.00088 496 6004REMOV STR (SET)EA 82.00089 496 6005REMOV STR (WINGWALL)EA 5.00090 496 6007REMOV STR (PIPE)LF 1,592.00091 496 6008REMOV STR (BOX CULVERT)LF 298.00092 496 6010REMOV STR (BRIDGE 100 - 499 FT LENGTH)EA 1.00093 500 6001MOBILIZATIONLS 1.00094 502 6001BARRICADES, SIGNS AND TRAFFIC HANDLINGMO 31.00095 506 6002ROCK FILTER DAMS (INSTALL) (TY 2)LF 3,877.00096 506 6004ROCK FILTER DAMS (INSTALL) (TY 4)LF 2,054.00097 506 6011ROCK FILTER DAMS (REMOVE)LF 5,931.00098 506 6020CONSTRUCTION EXITS (INSTALL) (TY 1)SY 1,456.00099 506 6024CONSTRUCTION EXITS (REMOVE)SY 1,456.000100 506 6030BACKHOE WORK (EROSION & SEDMT CONT)HR 40.000101 506 6034CONSTRUCTION PERIMETER FENCELF 275.000102 506 6038TEMP SEDMT CONT FENCE (INSTALL)LF 22,205.000103 506 6039TEMP SEDMT CONT FENCE (REMOVE)LF 22,205.000104 506 6041BIODEG EROSN CONT LOGS (INSTL) (12")LF 1,377.000105 506 6043BIODEG EROSN CONT LOGS (REMOVE)LF 1,377.000106 508 6001CONSTRUCTING DETOURSSY 1,446.000107 512 6005PORT CTB (FUR & INST)(F-SHAPE)(TY 1)LF 6,180.000108 512 6029PORT CTB (MOVE)(F-SHAPE)(TY 1)LF 14,160.000109 512 6053PORT CTB (REMOVE)(F-SHAPE)(TY 1)LF 6,180.000110 530 6004DRIVEWAYS (CONC)SY 1,246.000111 530 6005DRIVEWAYS (ACP)SY 6,783.000112 533 6001RUMBLE STRIPS (SHOULDER)LF 81,488.000113 540 6001MTL W-BEAM GD FEN (TIM POST)LF 3,287.500114 540 6006MTL BEAM GD FEN TRANS (THRIE-BEAM)EA 17.000115 540 6010MTL W-BEAM GD FEN ADJUSTMENTLF 1,125.000116 540 6014SHORT RADIUSLF 50.000117 540 6015DRIVEWAY TERMINAL ANCHOR SECTIONEA 2.000118 540 6016DOWNSTREAM ANCHOR TERMINAL SECTIONEA 4.000119 540 6017MTL BM GD FEN (LONG SPAN SYSTEM)LF 200.000120 542 6001REMOVE METAL BEAM GUARD FENCELF 1,125.000121 542 6003REMOVE DOWNSTREAM ANCHOR TERMINALEA 2.000122 542 6004RM MTL BM GD FENCE TRANS (THRIE-BEAM)EA 12.000123 544 6001GUARDRAIL END TREATMENT (INSTALL)EA 33.000124 544 6003GUARDRAIL END TREATMENT (REMOVE)EA 19.000125 545 6003CRASH CUSH ATTEN (MOVE & RESET)EA 6.000126 545 6005CRASH CUSH ATTEN (REMOVE)EA 5.000127 545 6010CRASH CUSH ATTEN (INSTL)(L)(W)(TL3)EA 1.000128 545 6019CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)EA 5.000129 550 6001CHAIN LINK FENCE (INSTALL) (6')LF 2,634.000130 556 6006PIPE UNDERDRAINS (TY 6) (6")LF 1,436.000131 560 6011MAILBOX INSTALL-S (TWW-POST) TY 4EA 22.000132 560 6012MAILBOX INSTALL-D (TWW-POST) TY 4EA 3.000133 560 6013MAILBOX INSTALL-M (TWW-POST) TY 4EA 3.000134 644 6027IN SM RD SN SUP&AM TYS80(1)SA(P)EA 40.000135 644 6028IN SM RD SN SUP&AM TYS80(1)SA(P-BM)EA 22.000136 644 6030IN SM RD SN SUP&AM TYS80(1)SA(T)EA 4.000137 644 6070RELOCATE SM RD SN SUP&AM TY S80EA 3.000138 644 6076REMOVE SM RD SN SUP&AMEA 21.000139 658 6013INSTL DEL ASSM (D-SW)SZ (BRF)CTBEA 124.000140 658 6026INSTL DEL ASSM (D-SY)SZ (BRF)CTBEA 21.000141 658 6061INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2EA 150.000142 658 6064INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2EA 61.000143 658 6095INSTL DEL ASSM (D-DY)SZ 1(YFLX)GNDEA 6.000144 658 6099INSTL OM ASSM (OM-2Z)(WFLX)GNDEA 113.000145 662 6050WK ZN PAV MRK REMOV (REFL) TY II-A-AEA 1,426.000146 662 6067WK ZN PAV MRK REMOV (W)6"(SLD)LF 98,228.000147 662 6098WK ZN PAV MRK REMOV (Y)6"(SLD)LF 98,905.000148 666 6030REFL PAV MRK TY I (W)8"(DOT)(100MIL)LF 902.000149 666 6036REFL PAV MRK TY I (W)8"(SLD)(100MIL)LF 4,769.000150 666 6048REFL PAV MRK TY I (W)24"(SLD)(100MIL)LF 233.000151 666 6141REFL PAV MRK TY I (Y)12"(SLD)(100MIL)LF 2,944.000152 666 6306RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)LF 13,742.000153 666 6309RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)LF 55,660.000154 666 6318RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)LF 6,053.000155 666 6321RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)LF 59,568.000156 668 6010PREFAB PAV MRK TY B (W)(6")(BRK)CNTSTLF 249.000157 668 6077PREFAB PAV MRK TY C (W) (ARROW)EA 16.000158 668 6085PREFAB PAV MRK TY C (W) (WORD)EA 12.000159 672 6007REFL PAV MRKR TY I-CEA 327.000160 672 6009REFL PAV MRKR TY II-A-AEA 773.000161 672 6010REFL PAV MRKR TY II-C-REA 621.000162 677 6001ELIM EXT PAV MRK & MRKS (4")LF 51,646.000163 730 6001STRIP MOWINGAC 388.000164 734 6001LITTER REMOVALAC 388.000165 738 6010CLEANING / SWEEPING (SPOT)MI 12.600166 30776010SP MIXES SP-B SAC-B PG76-22TON 21,645.000167 30776033SP MIXES SP-C SAC-A PG76-22TON 32,107.000168 30846001BONDING COURSEGAL 18,631.000169 40146001INTRLCK ART CONC BLKS (4" MIN)SF 12,404.000170 50016002GEOGRID BASE REINFORCEMENT (TY II)SY 163,248.000171 50886001BIRD EXCLUSION METHODSF 60,714.000172 60016002PORTABLE CHANGEABLE MESSAGE SIGNEA 3.000173 60386004MULTIPOLYMER PAV MRK (W)(6")(SLD)LF 991.000174 60386005MULTIPOLYMER PAV MRK (W)(6")(BRK)LF 249.000175 60386017MULTIPOLYMER PAV MRK (Y)(6")(SLD)LF 991.000176 60386018MULTIPOLYMER PAV MRK (Y)(6")(BRK)LF 139.000177 61856002TMA (STATIONARY)DAY 133.000178 61856005TMA (MOBILE OPERATION)DAY 60.000179 * INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS: CONTRACTOR FORCE ACCOUNT WORK (PARTICIPATING) $1,004,716.71 Total Bid Amount _______________________________ ____________________________________ certifies that the unit prices shown on this completed computer print-out for all of the bid items, alternate items, option items, and add alternate items contained in this proposal are the unit prices intended and that its bid will be tabulated using these unit prices and no other information from this print-out. ____________________________________ acknowledges and agrees that the total bid amount shown will be read as its total bid and further agree that the official total bid amount will be determined by multiplying the unit bid prices shown in this print-out by the respective estimated quantities shown in the proposal and then totaling all of the extended amounts. Signed ______________________________________________ Title ______________________________________________ Date ______________________________________________ Additional Signature for Joint Venture: Signed ______________________________________________ Title ______________________________________________ Date ______________________________________________