Jobs Delayed From The September 2017 Letting
|
Jobs Delayed From The September 2017 Letting |
|
Last Update: Thursday, August 17, 2017 |
Seq No |
County |
Project ID |
CCSJ |
Highway |
Reason for change |
001 |
MC MULLEN |
STP 2018(077) |
0483-02-021 |
SH 72 |
due to environmental clearance issues(dist) |
021 |
SMITH |
STP 2017(443)TAPS |
0910-16-135 |
CS |
Due to late PS&E (outside source) |
024 |
LAMAR |
STP 2017(409)TAPS |
0901-29-088 |
VA |
linked to CCSJ 0901-29-087 |
203 |
BRAZORIA |
BR 2018(103) |
2524-02-022 |
FM 2611 |
due to needing to get a coast guard permit |
206 |
FORT BEND |
STP 2013(736) |
0027-06-051 |
US 90A |
due to environmental clearance issues |
207 |
PECOS |
STP ( ) |
1639-02-017 |
FM 1450 |
added as subordinate to 2262-01-016 |
008 |
EL PASO |
CM 2018(087) |
2121-01-091 |
IH 10 |
due to needing more time for utility adjustment |
209 |
WALKER |
NH 2018(028) |
0675-06-096 |
IH 45 |
in order to accelerate 0016-04-100 into FY 18 |