The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | GALVESTON | Let Date: | 12/04/24 |
Type: | INSTALL/UPGRADE ROADWAY LIGHTING | Seq No: | 3217 |
Time: | 41 WORKING DAYS | Project ID: | C 500-1-155 |
Highway: | IH 45 | Contract #: | 12243217 |
Length: | 0.000 | CCSJ: | 0500-01-155 |
Limits: | |||
From: | SH 275 (HARBORSIDE DR) | Check: | $27,000 |
To: | VIRGINIA POINT ROAD | Misc Cost: |
Estimate | $1,360,850.00 | % Over/Under | Company |
Bidder 1 | $709,916.95 | -47.83% | SICE, INC. |
Bidder 2 | $776,200.00 | -42.96% | DECO CONTRACTORS, INC. |
Bidder 3 | $799,744.44 | -41.23% | THIRD COAST SERVICES LLC |
Bidder 4 | $802,611.79 | -41.02% | CREACOM, INC. |
Bidder 5 | $987,456.88 | -27.44% | HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC |
Bidder 6 | $1,066,200.00 | -21.65% | FLORIDA TRAFFIC CONTROL DEVICES, INC. |
Bidder 7 | $1,072,750.00 | -21.17% | SELECT MAINTENANCE, L.L.C. |
Bidder 8 | $1,164,334.00 | -14.44% | TRAF-TEX, INC. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
5007001 | MOBILIZATION | LS | 1.000 | 136,000.00 | 1 2 3 4 5 6 7 8 | 70,183.777 75,000.000 79,974.440 56,182.780 72,569.060 100,000.000 81,000.000 129,917.000 |
5027001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 4.000 | 10,000.00 | 1 2 3 4 5 6 7 8 | 15,807.227 15,000.000 8,554.810 36,134.080 81,041.110 48,400.000 36,000.000 3,641.000 |
5037001 | PORTABLE CHANGEABLE MESSAGE SIGN | DAY | 240.000 | 200.00 | 1 2 3 4 5 6 7 8 | 232.761 100.000 160.370 85.900 81.740 250.000 25.000 287.100 |
5057001 | TMA (STATIONARY) | DAY | 120.000 | 600.00 | 1 2 3 4 5 6 7 8 | 376.842 300.000 392.150 256.350 395.690 250.000 50.000 255.000 |
5127049 | PORT CTB (REMOVE)(SGL SLP)(TY 1) | LF | 90.000 | 65.00 | 1 2 3 4 5 6 7 8 | 19.741 250.000 660.000 127.580 508.000 131.000 225.000 356.000 |
5147035 | PERM CTB (SGL SLOPE) (MOD) | LF | 90.000 | 250.00 | 1 2 3 4 5 6 7 8 | 357.776 950.000 1,408.250 510.340 889.000 1,243.000 525.000 1,316.000 |
6107008 | REMOVE RD IL ASM (CTB MOUNT) | EA | 26.000 | 1,000.00 | 1 2 3 4 5 6 7 8 | 485.412 150.000 449.860 820.790 610.680 816.000 1,000.000 2,039.000 |
6107235 | IN RD IL (DECORATIVE WAVE SCHEME POLE) | EA | 35.000 | 27,000.00 | 1 2 3 4 5 6 7 8 | 10,304.461 11,500.000 9,611.810 12,214.600 8,768.080 13,819.000 17,500.000 18,729.000 |
6187054 | CONDT (PVC) (SCH 80) (2") | LF | 500.000 | 20.00 | 1 2 3 4 5 6 7 8 | 32.935 8.000 13.840 11.500 13.700 15.400 28.000 21.200 |
6187078 | CONDT (RM) (2") | LF | 1,000.000 | 30.00 | 1 2 3 4 5 6 7 8 | 23.747 45.000 37.370 21.520 45.970 26.150 72.000 30.800 |
6207009 | ELEC CONDR (NO.6) BARE | LF | 1,500.000 | 2.00 | 1 2 3 4 5 6 7 8 | 2.997 2.100 2.330 1.170 1.880 1.650 3.500 1.900 |
6207010 | ELEC CONDR (NO.6) INSULATED | LF | 3,000.000 | 3.00 | 1 2 3 4 5 6 7 8 | 2.776 2.250 1.840 1.380 2.170 2.100 4.500 2.200 |
6247007 | GROUND BOX TY D (162922) | EA | 5.000 | 1,300.00 | 1 2 3 4 5 6 7 8 | 1,357.909 680.000 1,065.320 928.280 1,161.750 786.800 2,000.000 863.000 |
6247008 | GROUND BOX TY D (162922)W/APRON | EA | 5.000 | 1,400.00 | 1 2 3 4 5 6 7 8 | 1,667.938 900.000 1,424.030 1,288.790 1,434.750 1,500.000 3,000.000 1,235.000 |