Tabulation of Bids for Project STP 2019(236)HES
Text version of this page | |||
County: | GRAY | Let Date: | 11/06/18 |
Type: | MILLED EDGELINE & MILLED CENTERLINE RUMBLE STRIPS | Seq No: | 3018 |
Time: | 130 WORKING DAYS | Project ID: | STP 2019(236)HES |
Highway: | SH 70 | Contract #: | 11183018 |
Length: | 23.887 | CCSJ: | 0309-01-043 |
Limits: | |||
From: | US 60 | Check: | $38,000 |
To: | 0.178 MILES S OF IH 40 | Misc Cost: | $15,000.00 |
Estimate | $1,898,557.15 | % Over/Under | Company |
Bidder 1 | $1,357,600.03 | -28.49% | SURFACE PREPARATION TECHNOLOGIES, LLC |
Bidder 2 | $1,371,399.77 | -27.77% | BRANNAN PAVING CO., LTD. |
Bidder 3 | $1,388,333.36 | -26.87% | VIZCAINO, L.P. |
Bidder 4 | $1,469,200.23 | -22.61% | STRIPE-A-ZONE, INC. |
Bidder 5 | $1,643,571.42 | -13.43% | TEXAS PANHANDLE CONSTRUCTION, INC. |
Bidder 6 | $1,852,377.30 | -2.43% | L&L COMPANY |
Bidder 7 | $1,865,369.83 | -1.75% | BARRICADES UNLIMITED |
Bidder 8 | $2,093,524.57 | +10.27% | TRP CONSTRUCTION GROUP, LLC |
Bidder 9 | $2,317,360.91 | +22.06% | TOTAL HIGHWAY MAINTENANCE, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
5006001 | MOBILIZATION | LS | 1.000 | 30,000.00 | 1 2 3 4 5 6 7 8 9 | 101,000.000 40,000.000 28,000.000 25,000.000 2,700.000 1.000 40,000.000 200,000.000 75,000.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 6.000 | 3,500.00 | 1 2 3 4 5 6 7 8 9 | 208.000 1.000 1.000 1,300.000 350.000 1.000 1,000.000 1,000.000 18,500.000 |
5336001 | RUMBLE STRIPS (SHOULDER) | LF | 3,723,719.000 | 0.15 | 1 2 3 4 5 6 7 8 9 | 0.100 0.098 0.110 0.110 0.110 0.180 0.130 0.170 0.160 |
5336002 | RUMBLE STRIPS (CENTERLINE) | LF | 664,376.000 | 0.15 | 1 2 3 4 5 6 7 8 9 | 0.100 0.098 0.160 0.140 0.160 0.200 0.180 0.210 0.280 |
6666035007 | REFL PAV MRK TY I (W)8"(SLD)(090MIL) | LF | 14,151.000 | 1.00 | 1 2 3 4 5 6 7 8 9 | 0.520 0.500 0.400 0.750 0.710 0.800 0.600 0.750 0.920 |
6666047007 | REFL PAV MRK TY I (W)24"(SLD)(090MIL) | LF | 3,128.000 | 5.00 | 1 2 3 4 5 6 7 8 9 | 7.280 4.000 4.000 5.200 3.250 4.000 3.920 12.000 5.160 |
6666283007 | REF PROF PAV MRK TY I(W)4"(SLD)(090MIL) | LF | 323,611.000 | 0.60 | 1 2 3 4 5 6 7 8 9 | 0.410 0.650 0.510 0.488 0.910 0.600 0.820 0.600 0.810 |
6666299007 | RE PM W/RET REQ TY I (W)4"(BRK)(090MIL) | LF | 172,061.000 | 0.30 | 1 2 3 4 5 6 7 8 9 | 0.260 0.240 0.220 0.255 0.273 0.280 0.300 0.320 0.400 |
6666302007 | RE PM W/RET REQ TY I (W)4"(SLD)(090MIL) | LF | 1,376,497.000 | 0.30 | 1 2 3 4 5 6 7 8 9 | 0.220 0.234 0.220 0.255 0.270 0.280 0.300 0.280 0.340 |
6666311007 | RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL) | LF | 145,488.000 | 0.30 | 1 2 3 4 5 6 7 8 9 | 0.220 0.240 0.230 0.255 0.270 0.280 0.300 0.300 0.400 |
6666314007 | RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL) | LF | 1,163,905.000 | 0.30 | 1 2 3 4 5 6 7 8 9 | 0.220 0.234 0.220 0.255 0.270 0.280 0.300 0.290 0.340 |
6786001 | PAV SURF PREP FOR MRK (4") | LF | 50,000.000 | 0.08 | 1 2 3 4 5 6 7 8 9 | 0.310 0.010 0.100 0.300 0.200 0.100 0.300 0.500 0.050 |
61856003 | TMA (MOBILE OPERATION) | HR | 2,600.000 | 40.00 | 1 2 3 4 5 6 7 8 9 | 1.000 0.100 10.000 2.000 10.000 10.000 22.000 10.000 25.000 |