Tabulation of Bids for Project RMC - 633445001
Text version of this page | |||
County: | UPSHUR | Let Date: | 10/03/18 |
Type: | TREE & STUMP REMOVAL (W) | Seq No: | 4217 |
Time: | 150 W | Project ID: | RMC - 633445001 |
Highway: | US0259 | Contract #: | 10184217 |
Length: | 0.001 | CCSJ: | 6334-45-001 |
Limits: | |||
From: | VARIOUS ROADWAYS IN | Check: | $11,000 |
To: | UPSHUR,CAMP,TITUS,CASS,MARION & MOR | Misc Cost: |
Estimate | $531,250.00 | % Over/Under | Company |
Bidder 1 | $494,994.00 | -6.82% | BRYDL CONTRACTING, INC. |
Bidder 2 | $511,954.00 | -3.63% | CATOCON, INC. |
Bidder 3 | $554,000.00 | +4.28% | T.F.R. ENTERPRISES, INC. |
Bidder 4 | $582,150.00 | +9.58% | CROSS PLUS CONSTRUCTION, LLC |
Bidder 5 | $783,500.00 | +47.48% | DREWERY CONSTRUCTION COMPANY, INCORPORATED |
Bidder 6 | $1104602250.00 | +207825.13% | DRC EMERGENCY SERVICES, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
5006033 | MOBILIZATION (CALLOUT) | EA | 4.000 | 1,000.00 | 1 2 3 4 5 6 | 1.000 1.000 20,000.000 100.000 5,000.000 8,000.000 |
7526005 | TREE REMOVAL (4" - 12" DIA) | EA | 4,000.000 | 60.00 | 1 2 3 4 5 6 | 43.000 45.000 20.000 75.000 60.000 220,000.000 |
7526006 | TREE REMOVAL (12" - 18" DIA) | EA | 1,200.000 | 85.00 | 1 2 3 4 5 6 | 76.000 77.000 70.000 85.000 70.000 114,000.000 |
7526007 | TREE REMOVAL (18" - 24" DIA) | EA | 700.000 | 100.00 | 1 2 3 4 5 6 | 120.000 104.000 90.000 90.000 120.000 94,500.000 |
7526008 | TREE REMOVAL (24" - 30" DIA) | EA | 250.000 | 125.00 | 1 2 3 4 5 6 | 225.000 200.000 200.000 199.000 200.000 48,750.000 |
7526009 | TREE REMOVAL (30" - 36" DIA) | EA | 150.000 | 200.00 | 1 2 3 4 5 6 | 300.000 299.000 300.000 200.000 500.000 36,750.000 |
7526010 | TREE REMOVAL (36" - 42" DIA) | EA | 100.000 | 250.00 | 1 2 3 4 5 6 | 300.000 400.000 400.000 200.000 750.000 27,500.000 |
7526011 | TREE REMOVAL (42" - 48" DIA) | EA | 25.000 | 400.00 | 1 2 3 4 5 6 | 300.000 500.000 1,000.000 200.000 2,100.000 8,750.000 |
7526012 | TREE REMOVAL (48" - 60" DIA) | EA | 20.000 | 500.00 | 1 2 3 4 5 6 | 300.000 600.000 1,000.000 200.000 2,700.000 8,500.000 |
7526013 | TREE REMOVAL (60" - 72" DIA) | EA | 10.000 | 500.00 | 1 2 3 4 5 6 | 300.000 500.000 1,000.000 400.000 3,000.000 6,150.000 |
7526014 | STUMP REMOVAL | EA | 20.000 | 100.00 | 1 2 3 4 5 6 | 1.000 20.000 600.000 100.000 450.000 7,000.000 |
61856002 | TMA (STATIONARY) | DAY | 20.000 | 100.00 | 1 2 3 4 5 6 | 1.000 100.000 2,250.000 100.000 500.000 29,000.000 |