Tabulation of Bids for Project BR 1702(601)
Text version of this page | |||
County: | LUBBOCK | Let Date: | 08/09/17 |
Type: | BEAM REPAIR | Seq No: | 3232 |
Time: | 25 WORKING DAYS | Project ID: | BR 1702(601) |
Highway: | CS | Contract #: | 08173232 |
Length: | 0.040 | CCSJ: | 0905-06-110 |
Limits: | |||
From: | BEGIN OF BUFFALO SPILLWAY BRIDGE | Check: | $2,000 |
To: | END OF BUFFALO SPILLWAY BRIDGE | Misc Cost: | $5,000.00 |
Estimate | $92,364.00 | % Over/Under | Company |
Bidder 1 | $93,214.40 | +0.92% | DRS CONSTRUCTION, INC. |
Bidder 2 | $168,636.00 | +82.58% | CHAMPION INFRASTRUCTURE, LLC |
Bidder 3 | $219,160.00 | +137.28% | SCR CIVIL CONSTRUCTION, LLC |
Bidder 4 | $333,600.00 | +261.18% | L.C. JORDAN & SON |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
4206140 | CL S CONC (CAP)(EXTEND) | CY | 8.000 | 2,875.00 | 1 2 3 4 | 2,500.000 3,000.000 1,000.000 3,500.000 |
4426011 | STR STEEL (PEDESTAL) | LB | 1,072.000 | 12.00 | 1 2 3 4 | 12.700 38.000 30.000 150.000 |
5006001 | MOBILIZATION | LS | 1.000 | 8,400.00 | 1 2 3 4 | 10,000.000 20,000.000 21,800.000 10,000.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 2.000 | 5,000.00 | 1 2 3 4 | 3,000.000 3,500.000 8,000.000 5,000.000 |
5126001 | PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | LF | 60.000 | 69.00 | 1 2 3 4 | 30.000 150.000 100.000 40.000 |
5126049 | PORT CTB (REMOVE)(SGL SLP)(TY 1) | LF | 60.000 | 6.00 | 1 2 3 4 | 30.000 65.000 100.000 40.000 |
7886001 | CONCRETE BEAM REPAIR | EA | 8.000 | 4,200.00 | 1 2 3 4 | 5,000.000 8,000.000 16,150.000 15,000.000 |