Tabulation of Bids for Project BR 2018(819)
Text version of this page | |||
County: | WILLIAMSON | Let Date: | 05/01/18 |
Type: | BRIDGE WIDENING & REPLACE APPROACHES | Seq No: | 3051 |
Time: | 142 WORKING DAYS | Project ID: | BR 2018(819) |
Highway: | SH 95 | Contract #: | 05183051 |
Length: | 0.063 | CCSJ: | 0320-03-092 |
Limits: | |||
From: | AT DRAIN | Check: | $7,000 |
To: | STR 0320-03-034 | Misc Cost: | $15,000.00 |
Estimate | $389,914.59 | % Over/Under | Company |
Bidder 1 | $330,317.61 | -15.28% | DAN WILLIAMS COMPANY |
Bidder 2 | $352,347.30 | -9.63% | CAPITAL EXCAVATION COMPANY |
Bidder 3 | $361,642.17 | -7.25% | ANGEL BROTHERS HOLDINGS CORP. |
Bidder 4 | $392,121.11 | +0.57% | JAMES CONSTRUCTION GROUP, L.L.C. |
Bidder 5 | $426,573.20 | +9.40% | AARON CONCRETE CONTRACTORS, L.P. |
Bidder 6 | $433,158.00 | +11.09% | FNH CONSTRUCTION, LLC |
Bidder 7 | $446,335.30 | +14.47% | DENBOW COMPANY INC. |
Bidder 8 | $466,751.00 | +19.71% | JOE BLAND CONSTRUCTION, L.P. |
Bidder 9 | $475,664.80 | +21.99% | ELLIS-MCGINNIS CONSTRUCTION CO. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1006002 | PREPARING ROW | STA | 3.320 | 2,000.00 | 1 2 3 4 5 6 7 8 9 | 4,000.000 5,000.000 4,000.000 5,000.000 2,000.000 3,000.000 7,700.000 2,600.000 3,000.000 |
1046009 | REMOVING CONC (RIPRAP) | SY | 60.000 | 21.00 | 1 2 3 4 5 6 7 8 9 | 8.000 25.000 15.000 50.000 26.000 15.000 20.000 25.000 10.000 |
1056049 | REMOVING STAB BASE & ASPH PAV (4"-22") | SY | 140.000 | 16.00 | 1 2 3 4 5 6 7 8 9 | 12.000 20.000 25.000 13.000 40.000 7.500 12.000 32.000 10.000 |
1106001 | EXCAVATION (ROADWAY) | CY | 1,535.000 | 20.00 | 1 2 3 4 5 6 7 8 9 | 10.000 8.000 15.000 9.000 16.000 25.000 11.000 28.000 16.000 |
1326003 | EMBANKMENT (FINAL)(ORD COMP)(TY B) | CY | 667.000 | 22.50 | 1 2 3 4 5 6 7 8 9 | 14.000 14.000 8.000 12.000 16.000 15.000 35.000 20.000 20.000 |
1606003 | FURNISHING AND PLACING TOPSOIL (4") | SY | 4,091.000 | 3.00 | 1 2 3 4 5 6 7 8 9 | 1.000 3.000 1.500 1.000 1.500 2.500 1.400 2.700 2.000 |
1646003 | BROADCAST SEED (PERM) (RURAL) (CLAY) | SY | 4,091.000 | 0.25 | 1 2 3 4 5 6 7 8 9 | 0.210 0.200 0.170 0.160 0.200 1.000 0.200 0.300 1.000 |
1686001 | VEGETATIVE WATERING | MG | 82.000 | 25.00 | 1 2 3 4 5 6 7 8 9 | 10.000 19.200 20.000 34.010 35.000 80.000 47.000 35.000 48.000 |
1696001 | SOIL RETENTION BLANKETS (CL 1) (TY A) | SY | 4,091.000 | 1.30 | 1 2 3 4 5 6 7 8 9 | 1.300 1.200 1.200 1.200 1.300 4.500 1.400 1.200 1.500 |
2476366 | FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) | CY | 358.000 | 59.00 | 1 2 3 4 5 6 7 8 9 | 56.000 55.000 60.000 85.000 80.000 75.000 61.500 42.000 80.000 |
3106027 | PRIME COAT(MC-30 OR AE-P) | GAL | 161.000 | 9.00 | 1 2 3 4 5 6 7 8 9 | 6.000 6.000 10.000 5.750 5.500 6.000 5.000 5.800 5.800 |
3166015 | ASPH (AC-15P) | GAL | 870.000 | 5.50 | 1 2 3 4 5 6 7 8 9 | 7.000 7.000 5.000 6.500 4.800 6.000 4.500 6.500 6.500 |
3166240 | AGGR(TY-PD GR-4 SAC-B) | CY | 19.000 | 130.00 | 1 2 3 4 5 6 7 8 9 | 300.000 300.000 350.000 295.000 126.000 250.000 120.000 295.000 295.000 |
3406011 | D-GR HMA(SQ) TY-B PG64-22 | TON | 155.000 | 110.00 | 1 2 3 4 5 6 7 8 9 | 125.000 125.000 92.000 119.000 156.000 200.000 149.000 119.000 145.000 |
3406120 | D-GR HMA(SQ) TY-D SAC-B PG70-22 | TON | 73.000 | 200.00 | 1 2 3 4 5 6 7 8 9 | 135.000 130.000 130.000 122.000 192.000 200.000 183.000 122.000 125.000 |
3566017 | FABRIC | SY | 805.000 | 4.00 | 1 2 3 4 5 6 7 8 9 | 2.000 4.000 2.500 2.500 1.100 6.000 2.000 7.000 2.100 |
4016001 | FLOWABLE BACKFILL | CY | 29.000 | 180.00 | 1 2 3 4 5 6 7 8 9 | 130.000 130.000 180.000 140.000 145.000 220.000 200.000 450.000 230.000 |
4036001 | TEMPORARY SPL SHORING | SF | 457.000 | 27.50 | 1 2 3 4 5 6 7 8 9 | 1.000 15.000 25.000 25.000 36.000 12.000 54.000 25.000 5.000 |
4296002 | CONC STR REPAIR (EPOXY MORTAR) | SF | 5.000 | 200.00 | 1 2 3 4 5 6 7 8 9 | 200.000 480.000 200.000 480.000 330.000 12.000 200.000 600.000 85.000 |
4326002 | RIPRAP (CONC)(5 IN) | CY | 26.000 | 480.00 | 1 2 3 4 5 6 7 8 9 | 400.000 480.000 470.000 420.000 570.000 450.000 574.000 395.000 440.000 |
4326045 | RIPRAP (MOW STRIP)(4 IN) | CY | 24.000 | 500.00 | 1 2 3 4 5 6 7 8 9 | 475.000 600.000 500.000 560.000 520.000 450.000 557.000 410.000 485.000 |
4326057 | RIPRAP (STONE TY R)(GROUT)(18 IN) | CY | 34.000 | 300.00 | 1 2 3 4 5 6 7 8 9 | 175.000 350.000 300.000 180.000 375.000 400.000 252.000 380.000 223.000 |
4506006 | RAIL (TY T223) | LF | 64.000 | 105.00 | 1 2 3 4 5 6 7 8 9 | 120.000 120.000 190.000 220.000 125.000 117.000 115.000 400.000 160.000 |
4626055 | CONC BOX CULV (6 FT X 4 FT)(EXTEND) | LF | 101.000 | 600.00 | 1 2 3 4 5 6 7 8 9 | 450.000 405.000 500.000 750.000 700.000 400.000 689.000 685.000 1,300.000 |
4666168 | WINGWALL (FW - S) (HW=7 FT) | EA | 1.000 | 14,000.00 | 1 2 3 4 5 6 7 8 9 | 16,000.000 15,000.000 15,000.000 9,000.000 22,000.000 10,000.000 28,000.000 17,500.000 10,500.000 |
4666170 | WINGWALL (FW - S) (HW=9 FT) | EA | 1.000 | 22,000.00 | 1 2 3 4 5 6 7 8 9 | 18,500.000 22,000.000 24,000.000 15,000.000 30,000.000 15,000.000 29,000.000 24,000.000 17,600.000 |
4806001 | CLEAN EXIST CULVERTS | EA | 1.000 | 2,500.00 | 1 2 3 4 5 6 7 8 9 | 2,000.000 7,142.000 2,500.000 1,000.000 5,000.000 500.000 5,000.000 6,000.000 370.000 |
4966005 | REMOV STR (WINGWALL) | EA | 2.000 | 2,000.00 | 1 2 3 4 5 6 7 8 9 | 1,000.000 1,300.000 2,000.000 2,000.000 1,500.000 1,200.000 1,800.000 4,800.000 8,000.000 |
5006001 | MOBILIZATION | LS | 1.000 | 36,200.00 | 1 2 3 4 5 6 7 8 9 | 31,000.000 35,000.000 36,000.000 39,000.000 41,000.000 40,000.000 43,526.000 46,652.000 40,000.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 6.000 | 3,000.00 | 1 2 3 4 5 6 7 8 9 | 4,000.000 1,000.000 2,000.000 3,500.000 1,000.000 7,000.000 560.000 3,500.000 4,000.000 |
5066002003 | ROCK FILTER DAMS (INSTALL) (TY 2) | LF | 181.000 | 25.00 | 1 2 3 4 5 6 7 8 9 | 25.000 24.500 26.000 28.000 27.000 35.000 29.000 22.000 35.000 |
5066011003 | ROCK FILTER DAMS (REMOVE) | LF | 181.000 | 8.00 | 1 2 3 4 5 6 7 8 9 | 12.000 12.000 6.000 6.000 13.000 10.000 6.000 7.000 10.000 |
5066020003 | CONSTRUCTION EXITS (INSTALL) (TY 1) | SY | 156.000 | 20.00 | 1 2 3 4 5 6 7 8 9 | 13.000 13.000 19.000 20.000 14.000 12.000 21.000 10.500 14.000 |
5066024003 | CONSTRUCTION EXITS (REMOVE) | SY | 156.000 | 7.50 | 1 2 3 4 5 6 7 8 9 | 10.000 10.000 6.000 6.000 11.000 5.000 6.000 6.500 3.000 |
5066038003 | TEMP SEDMT CONT FENCE (INSTALL) | LF | 480.000 | 2.50 | 1 2 3 4 5 6 7 8 9 | 2.500 2.200 2.300 2.500 2.400 4.500 2.500 2.000 3.600 |
5066039003 | TEMP SEDMT CONT FENCE (REMOVE) | LF | 480.000 | 0.60 | 1 2 3 4 5 6 7 8 9 | 0.700 0.700 0.500 0.500 0.800 1.000 0.500 0.700 2.000 |
5406001 | MTL W-BEAM GD FEN (TIM POST) | LF | 200.000 | 22.50 | 1 2 3 4 5 6 7 8 9 | 22.000 20.800 22.000 21.200 23.000 28.000 24.000 22.000 21.000 |
5406006 | MTL BEAM GD FEN TRANS (THRIE-BEAM) | EA | 2.000 | 1,600.00 | 1 2 3 4 5 6 7 8 9 | 1,900.000 1,845.000 1,800.000 1,445.000 2,000.000 2,300.000 1,661.000 1,700.000 1,845.000 |
5406016 | DOWNSTREAM ANCHOR TERMINAL SECTION | EA | 2.000 | 1,025.00 | 1 2 3 4 5 6 7 8 9 | 1,000.000 925.000 1,100.000 1,040.000 990.000 1,500.000 1,195.000 1,050.000 925.000 |
5406018 | MTL BM GD FEN TRANS (NON - SYM) | EA | 2.000 | 675.00 | 1 2 3 4 5 6 7 8 9 | 750.000 695.000 680.000 664.850 750.000 1,000.000 764.000 625.000 695.000 |
5426001 | REMOVE METAL BEAM GUARD FENCE | LF | 375.000 | 1.40 | 1 2 3 4 5 6 7 8 9 | 2.000 2.000 1.500 1.500 2.200 5.000 1.500 1.000 6.000 |
5426002 | REMOVE TERMINAL ANCHOR SECTION | EA | 4.000 | 185.00 | 1 2 3 4 5 6 7 8 9 | 130.000 125.000 100.000 100.000 135.000 300.000 115.000 175.000 300.000 |
5446001 | GUARDRAIL END TREATMENT (INSTALL) | EA | 2.000 | 2,463.00 | 1 2 3 4 5 6 7 8 9 | 2,500.000 2,435.000 2,400.000 2,335.000 2,600.000 2,800.000 2,684.000 2,350.000 2,435.000 |
6586014 | INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) | EA | 6.000 | 14.00 | 1 2 3 4 5 6 7 8 9 | 15.500 15.000 13.000 13.000 16.000 25.000 14.000 13.000 15.000 |
6586016 | INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI) | EA | 12.000 | 35.00 | 1 2 3 4 5 6 7 8 9 | 15.500 15.000 13.000 13.000 16.000 40.000 14.000 13.000 15.000 |
6586047 | INSTL OM ASSM (OM-2Y)(WC)GND | EA | 2.000 | 75.00 | 1 2 3 4 5 6 7 8 9 | 41.000 40.000 45.000 43.840 43.000 100.000 50.000 44.000 40.000 |
6626109 | WK ZN PAV MRK SHT TERM (TAB)TY W | EA | 48.000 | 1.20 | 1 2 3 4 5 6 7 8 9 | 1.400 1.000 0.800 1.000 0.800 1.250 0.500 2.500 4.400 |
6626111 | WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | EA | 32.000 | 0.97 | 1 2 3 4 5 6 7 8 9 | 1.400 1.000 0.800 1.000 1.700 1.250 0.500 2.500 4.400 |
6666299007 | RE PM W/RET REQ TY I (W)4"(BRK)(090MIL) | LF | 166.000 | 0.30 | 1 2 3 4 5 6 7 8 9 | 3.100 4.000 3.000 4.560 3.200 0.500 3.400 4.000 3.000 |
6666302007 | RE PM W/RET REQ TY I (W)4"(SLD)(090MIL) | LF | 663.000 | 0.30 | 1 2 3 4 5 6 7 8 9 | 3.100 3.500 3.000 4.560 3.200 0.500 3.400 3.500 3.000 |
6666314007 | RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL) | LF | 663.000 | 0.20 | 1 2 3 4 5 6 7 8 9 | 3.100 3.500 3.000 4.560 3.200 0.500 3.400 3.500 3.000 |
6726007 | REFL PAV MRKR TY I-C | EA | 8.000 | 3.40 | 1 2 3 4 5 6 7 8 9 | 21.000 35.000 20.000 30.430 22.000 4.000 23.000 35.000 20.000 |
6726009 | REFL PAV MRKR TY II-A-A | EA | 8.000 | 3.30 | 1 2 3 4 5 6 7 8 9 | 21.000 35.000 20.000 30.430 22.000 4.000 23.000 35.000 20.000 |
7806002 | CNC CRACK REPAIR (DISCRETE)(INJECT) | LF | 5.000 | 200.00 | 1 2 3 4 5 6 7 8 9 | 125.000 500.000 120.000 350.000 450.000 100.000 86.000 600.000 170.000 |