Tabulation of Bids for Project BPM - 632701001
Text version of this page | |||
County: | BEXAR | Let Date: | 03/07/18 |
Type: | BRIDGE PREVENTATIVE MAINTENANCE | Seq No: | 4213 |
Time: | 60 W | Project ID: | BPM - 632701001 |
Highway: | SH0016 | Contract #: | 03184213 |
Length: | 0.001 | CCSJ: | 6327-01-001 |
Limits: | |||
From: | SH 16 AT | Check: | $11,000 |
To: | ELM CREEK | Misc Cost: |
Estimate | $534,335.12 | % Over/Under | Company |
Bidder 1 | $427,360.00 | -20.02% | RELMCO, INC. |
Bidder 2 | $435,500.00 | -18.50% | DALRYMPLE GRAVEL AND CONTRACTING COMPANY, INC. |
Bidder 3 | $440,000.00 | -17.65% | DAN WILLIAMS COMPANY |
Bidder 4 | $447,937.00 | -16.17% | BECK-REIT & SONS, LTD. |
Bidder 5 | $472,871.44 | -11.50% | ALL IN CONSTRUCTION, L.L.C. |
Bidder 6 | $538,433.74 | +0.77% | SALINAS CONSTRUCTION TECHNOLOGIES, LTD. |
Bidder 7 | $581,914.00 | +8.90% | CHAMPION INFRASTRUCTURE, LLC |
Bidder 8 | $621,539.00 | +16.32% | MAIN LANE INDUSTRIES LTD. |
Bidder 9 | $625,407.66 | +17.04% | DEANGELO BROTHERS LLC |
Bidder 10 | $695,078.00 | +30.08% | SJ&J CONSTRUCTION, LLC |
Bidder 11 | $719,840.00 | +34.72% | RESTEK, INC. |
Bidder 12 | $799,800.00 | +49.68% | SHANNON-MONK, INC. |
Bidder 13 | $850,927.20 | +59.25% | TMES LLC |
Bidder 14 | $860,310.00 | +61.01% | FNH CONSTRUCTION, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1006002 | PREPARING ROW | STA | 3.000 | 6,256.00 | 1 2 3 4 5 6 7 8 9 10 11 12 13 14 | 6,000.000 3,000.000 14,000.000 2,500.000 5,000.000 3,034.410 1,500.000 15,000.000 4,141.220 2,000.000 2,500.000 9,900.000 12,000.000 10,000.000 |
1046009 | REMOVING CONC (RIPRAP) | SY | 2,520.000 | 12.46 | 1 2 3 4 5 6 7 8 9 10 11 12 13 14 | 10.000 12.000 10.000 11.000 38.090 16.020 26.000 12.000 11.120 30.000 20.000 30.000 11.330 20.000 |
4326001 | RIPRAP (CONC)(4 IN) | CY | 3.000 | 350.00 | 1 2 3 4 5 6 7 8 9 10 11 12 13 14 | 900.000 1,200.000 700.000 700.000 9,500.000 1,086.890 900.000 1,250.000 637.060 800.000 1,000.000 1,500.000 600.000 450.000 |
4326036 | RIPRAP (STONE PROTECTION)(30 IN) | CY | 997.000 | 125.00 | 1 2 3 4 5 6 7 8 9 10 11 12 13 14 | 145.000 125.000 145.000 144.000 90.170 199.130 210.000 190.000 265.950 150.000 250.000 239.000 196.000 225.000 |
4596007 | GABION MATTRESSES (GALV)(12 IN) | SY | 1,327.000 | 58.56 | 1 2 3 4 5 6 7 8 9 10 11 12 13 14 | 65.000 80.000 50.000 66.000 28.786 65.900 76.000 85.000 112.630 90.000 150.000 120.000 151.840 185.000 |
4596009 | GABIONS (3' X 3')(GALV) | CY | 253.000 | 205.00 | 1 2 3 4 5 6 7 8 9 10 11 12 13 14 | 155.000 190.000 155.000 177.000 187.000 170.190 192.000 200.000 200.380 300.000 200.000 270.000 438.000 200.000 |
4596011 | GABIONS (5'X 3')(GALV) | CY | 422.000 | 400.00 | 1 2 3 4 5 6 7 8 9 10 11 12 13 14 | 125.000 200.000 150.000 199.000 206.800 161.410 208.000 200.000 160.130 310.000 250.000 300.000 404.890 300.000 |
5006001 | MOBILIZATION | LS | 1.000 | 30,000.00 | 1 2 3 4 5 6 7 8 9 10 11 12 13 14 | 25,000.000 23,000.000 42,000.000 44,000.000 30,917.688 83,583.490 40,000.000 60,000.000 26,100.000 120,000.000 45,000.000 67,000.000 88,280.000 80,000.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 6.000 | 5,000.00 | 1 2 3 4 5 6 7 8 9 10 11 12 13 14 | 5,500.000 1,000.000 2,500.000 1,100.000 6,131.333 724.630 3,500.000 7,500.000 3,960.000 2,500.000 1,500.000 5,000.000 2,884.890 8,500.000 |
5066040 | BIODEG EROSN CONT LOGS (INSTL) (8") | LF | 27.000 | 3.65 | 1 2 3 4 5 6 7 8 9 10 11 12 13 14 | 15.000 12.000 8.000 3.000 46.296 16.860 30.000 10.000 6.850 12.000 15.000 18.000 10.000 12.000 |
5066043 | BIODEG EROSN CONT LOGS (REMOVE) | LF | 27.000 | 0.75 | 1 2 3 4 5 6 7 8 9 10 11 12 13 14 | 10.000 3.000 2.000 1.000 64.810 5.850 30.000 2.000 4.530 2.000 5.000 3.000 5.000 8.000 |