Tabulation of Bids for Project STP 2017(012)HES
Text version of this page | |||
County: | MCLENNAN | Let Date: | 02/02/17 |
Type: | MILLED CL RUMBLE STRIP | Seq No: | 3031 |
Time: | 60 WORKING DAYS | Project ID: | STP 2017(012)HES |
Highway: | FM 3051 | Contract #: | 02173031 |
Length: | 26.132 | CCSJ: | 2311-01-038 |
Limits: | |||
From: | 0.418 MI W OF FM 1637 | Check: | $4,000.000 |
To: | BU 77, ETC. | Misc Cost: | $3,000.000 |
Estimate | $182,353.64 | % Over/Under | Company |
Bidder 1 | $195,682.45 | +7.31% | NEWMAN & KENG PAVING COMPANY, INC. |
Bidder 2 | $210,313.33 | +15.33% | STRIPE-A-ZONE, INC. |
Bidder 3 | $276,602.21 | +51.68% | RAGLE CONSTRUCTION, INC. |
Bidder 4 | $285,979.81 | +56.83% | TRP CONSTRUCTION GROUP, LLC |
Bidder 5 | $389,826.10 | +113.77% | RBR INFRASTRUCTURE & ROAD, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
3166398 | AGGR (TY-PD GR-4 OR TY-PL GR-4)(SAC-B) | CY | 184.000 | 110.500 | 1 2 3 4 5 | 225.000 370.160 290.000 210.000 179.000 |
3166399 | ASPH(AC-15P,AC-20XP,AC10-2TR,AC-12-5TR) | GAL | 8,062.000 | 3.320 | 1 2 3 4 5 | 3.500 5.610 8.000 10.000 5.000 |
5006001 | MOBILIZATION | LS | 1.000 | 27,000.000 | 1 2 3 4 5 | 25,000.000 15,400.000 27,000.000 25,000.000 30,000.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 4.000 | 5,000.000 | 1 2 3 4 5 | 3,000.000 750.000 6,500.000 5,000.000 23,000.000 |
5336004 | RUMBLE STRIPS (CENTERLINE) ASPHALT | LF | 103,563.000 | 0.200 | 1 2 3 4 5 | 0.250 0.185 0.070 0.430 0.600 |
6626111 | WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | EA | 8,737.000 | 1.000 | 1 2 3 4 5 | 0.500 0.010 1.500 1.500 4.500 |
6666312001 | RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) | LF | 13,270.000 | 0.300 | 1 2 3 4 5 | 0.300 0.435 0.450 0.380 0.500 |
6666315001 | RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) | LF | 163,964.000 | 0.300 | 1 2 3 4 5 | 0.300 0.300 0.450 0.330 0.500 |
6726009001 | REFL PAV MRKR TY II-A-A | EA | 1,409.000 | 4.000 | 1 2 3 4 5 | 4.000 3.100 4.000 3.500 3.200 |