Monthly Local Let Maintenance Report For Yoakum District As Of Apr 12, 2024 Page 2 Of 4

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyFAYETTE
HighwayUS0077
FromDEWITT, LAVACA, FAYETTE, AND GONZALES
ToCOUNTIES
CSJ6426-62-001
Proj IDMMC - 642662001
Work TypeROCK/RIPRAP
 
0.010101500.0030213.6029.7
Work Order00-00-00
Work Began04-26-23
Work Completed
Time Computed05-01-23
Contract Working Days180
Addl Days Granted180
Working Days Charged336
Percent Time Used93
Contractor(s)
DALRYMPLE GRAVEL AND CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6426-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02231311
Totals101500.000.0030213.6029.7

CountyVICTORIA
HighwayUS0059
FromVICTORIA, JACKSON, AND CALHOUN COUNITES
To.
CSJ6426-64-001
Proj IDMMC - 642664001
Work TypeROCK/RIPRAP
 
0.010126000.0055745.3044.2
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed06-01-23
Contract Working Days180
Addl Days Granted180
Working Days Charged305
Percent Time Used84
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6426-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04231303
Totals126000.0018266.4055745.3044.2

CountyCALHOUN
HighwaySH0035
FromCALHOUN, COLORADO, GONZALES, DEWITT,
ToLAVACA, MATAGORDA, VICTORIA, AND WHARTON
CSJ6427-78-001
Proj IDBPM - 642778001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010314460.00149892.4047.6
Work Order00-00-00
Work Began12-26-23
Work Completed
Time Computed01-02-24
Contract Working Days45
Addl Days Granted0
Working Days Charged24
Percent Time Used53
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6427-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04231327
Totals314460.00110764.90149892.4047.6

CountyGONZALES
HighwayUS0183
FromGONZALES COUNTY
To.
CSJ6429-98-001
Proj IDMMC - 642998001
Work TypeHOT MIX
 
0.010240000.00624225.6099.9
Work Order00-00-00
Work Began04-27-23
Work Completed
Time Computed05-01-23
Contract Working Days180
Addl Days Granted180
Working Days Charged336
Percent Time Used93
Contractor(s)
BRAUNTEX MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6429-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02231314
Totals240000.00147605.60624225.6099.9

CountyVICTORIA
HighwayUS0059
FromVICTORIA COUNTY
To.
CSJ6430-04-001
Proj IDMMC - 643004001
Work TypeHOT-MIX COLD-LAID
 
0.010245000.004849.041.9
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed06-01-23
Contract Working Days180
Addl Days Granted180
Working Days Charged305
Percent Time Used84
Contractor(s)
BRAUNTEX MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6430-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04231305
Totals245000.000.004849.041.9

CountyFAYETTE
HighwayUS0077
FromFAYETTE COUNTY
To.
CSJ6432-94-001
Proj IDMMC - 643294001
Work TypeHOT-MIX COLD-LAID
 
0.010270000.0034176.6012.6
Work Order00-00-00
Work Began04-26-23
Work Completed
Time Computed05-01-23
Contract Working Days180
Addl Days Granted180
Working Days Charged336
Percent Time Used93
Contractor(s)
BRAUNTEX MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6432-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02231332
Totals270000.000.0034176.6012.6

CountyFAYETTE
HighwayUS0077
FromFAYETTE, LAVACA, DEWITT, AND
ToGONZALES COUNTIES
CSJ6433-00-001
Proj IDMMC - 643300001
Work TypeHYDRAULIC CEMENT
 
0.01025200.0017640.0070.0
Work Order00-00-00
Work Began04-27-23
Work Completed
Time Computed05-01-23
Contract Working Days180
Addl Days Granted180
Working Days Charged336
Percent Time Used93
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6433-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02231329
Totals25200.000.0017640.0070.0

CountyFAYETTE
HighwayUS0077
FromFAYETTE, LAVACA, DEWITT, AND
ToGONZALES COUNTIES
CSJ6433-02-001
Proj IDMMC - 643302001
Work TypeLIME
 
0.01025200.000.000.0
Work Order00-00-00
Work Began04-27-23
Work Completed
Time Computed05-01-23
Contract Working Days180
Addl Days Granted180
Working Days Charged331
Percent Time Used91
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6433-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02231330
Totals25200.000.000.000.0

CountyFAYETTE
HighwayUS0077
FromFAYETTE, LAVACA, DEWITT, AND
ToGONZALES COUNTIES
CSJ6433-04-001
Proj IDMMC - 643304001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.010150762.506250.004.1
Work Order00-00-00
Work Began04-26-23
Work Completed
Time Computed05-01-23
Contract Working Days180
Addl Days Granted180
Working Days Charged336
Percent Time Used93
Contractor(s)
WALLER COUNTY ASPHALT INC.
SUBCONTRACTOR(S) FOR CCSJ: 6433-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02231331
Totals150762.500.006250.004.1

CountyCALHOUN
HighwaySH0035
FromCALHOUN COUNTY
To.
CSJ6433-12-001
Proj IDMMC - 643312001
Work TypeHOT MIX
 
0.010312000.00584542.4099.9
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed06-01-23
Contract Working Days180
Addl Days Granted180
Working Days Charged305
Percent Time Used84
Contractor(s)
QUALITY HOT MIX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6433-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04231307
Totals312000.0022240.40584542.4099.9

CountyJACKSON
HighwaySH0111
FromJACKSON COUNTY
To.
CSJ6433-14-001
Proj IDMMC - 643314001
Work TypeHOT-MIX COLD-LAID
 
0.010250000.0015150.006.0
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed06-01-23
Contract Working Days180
Addl Days Granted180
Working Days Charged305
Percent Time Used84
Contractor(s)
BRAUNTEX MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6433-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04231308
Totals250000.005047.0015150.006.0

CountyVICTORIA
HighwayUS0059
FromVICTORIA, JACKSON, AND CALHOUN COUNITES
To.
CSJ6433-18-001
Proj IDMMC - 643318001
Work TypeHYDRAULIC CEMENT
 
0.01018900.005880.0031.1
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed06-01-23
Contract Working Days180
Addl Days Granted180
Working Days Charged305
Percent Time Used84
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6433-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04231310
Totals18900.000.005880.0031.1

CountyVICTORIA
HighwayUS0059
FromVICTORIA, JACKSON, AND CALHOUN COUNITES
To.
CSJ6433-20-001
Proj IDMMC - 643320001
Work TypeLIME
 
0.01020475.000.000.0
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed06-01-23
Contract Working Days180
Addl Days Granted180
Working Days Charged305
Percent Time Used84
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6433-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04231311
Totals20475.000.000.000.0

CountyVICTORIA
HighwayUS0059
FromVICTORIA, JACKSON, AND CALHOUN COUNITES
To.
CSJ6433-22-001
Proj IDMMC - 643322001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.010123987.507456.496.0
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed06-01-23
Contract Working Days180
Addl Days Granted180
Working Days Charged305
Percent Time Used84
Contractor(s)
WALLER COUNTY ASPHALT INC.
SUBCONTRACTOR(S) FOR CCSJ: 6433-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04231312
Totals123987.500.007456.496.0

CountyVICTORIA
HighwayUS0059
FromVICTORIA, JACKSON, AND CALHOUN COUNITES
To.
CSJ6433-24-001
Proj IDMMC - 643324001
Work TypeAGGREGATE
 
0.010280800.00123080.4643.8
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed06-01-23
Contract Working Days180
Addl Days Granted180
Working Days Charged305
Percent Time Used84
Contractor(s)
QUALITY HOT MIX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6433-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04231313
Totals280800.000.00123080.4643.8

CountyCOLORADO
HighwayIH0010
FromDISTRICT WIDE
To.
CSJ6433-42-001
Proj IDRMC - 643342001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010274550.00227870.9582.9
Work Order00-00-00
Work Began08-31-23
Work Completed
Time Computed09-05-23
Contract Working Days365
Addl Days Granted0
Working Days Charged203
Percent Time Used55
Contractor(s)
K & R CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 6433-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05231302
Totals274550.0021090.40227870.9582.9

CountyJACKSON
HighwaySH0111
FromJACKSON COUNTY
To.
CSJ6437-29-001
Proj IDRMC - 643729001
Work TypeJANITORIAL MAINTENANCE
 
0.01010100.007490.0074.1
Work Order00-00-00
Work Began05-31-23
Work Completed
Time Computed05-31-23
Contract Working Days365
Addl Days Granted365
Working Days Charged300
Percent Time Used41
Contractor(s)
RWCS JANITORIAL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6437-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04231325
Totals10100.00730.007490.0074.1

CountyVICTORIA
HighwayUS0059
FromVICTORIA MAINT OFFICE
To.
CSJ6437-75-001
Proj IDRMC - 643775001
Work TypeJANITORIAL MAINTENANCE
 
0.01014774.5211949.8680.8
Work Order00-00-00
Work Began05-24-23
Work Completed
Time Computed06-01-23
Contract Working Days365
Addl Days Granted365
Working Days Charged299
Percent Time Used40
Contractor(s)
ACE GLOBAL
SUBCONTRACTOR(S) FOR CCSJ: 6437-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04231326
Totals14774.521578.3111949.8680.8

CountyVICTORIA
HighwayUS0059
FromVICTORIA COUNTY
To.
CSJ6442-46-001
Proj IDRMC - 644246001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010129650.85155500.8599.9
Work Order00-00-00
Work Began07-03-23
Work Completed
Time Computed07-05-23
Contract Working Days365
Addl Days Granted0
Working Days Charged265
Percent Time Used72
Contractor(s)
TREC SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6442-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05231301
Totals129650.850.00155500.8599.9

CountyFAYETTE
HighwayIH0010
FromFAYETTE, GONZALES, COLORADO, AND
ToAUSTIN COUNTIES
CSJ6445-02-001
Proj IDSUP - 644502001
Work TypeSTATE USE CONTRACT
 
0.010752122.00541416.2671.9
Work Order00-00-00
Work Began07-20-23
Work Completed
Time Computed07-20-23
Contract Working Days365
Addl Days Granted0
Working Days Charged250
Percent Time Used68
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6445-02-001
RUCON, INC. (0.00)
Contract #06231301
Totals752122.0066363.66541416.2671.9

page 1 | page 2 | page 3 | page 4