Monthly State Let Construction Report For Yoakum District As Of May 10, 2018 Page 6 Of 7

Last Update: Thursday, May 10, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyFAYETTE
HighwayCR
FromAT MIDDLE CREEK CR 160
To(HERZIK ROAD) STR # AA01-60-001
CSJ0913-28-064
Proj IDBR 2016(325)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.067349287.94262228.3175.0
Work Order11-16-17
Work Began03-12-18
Work Completed
Time Computed02-14-18
Contract Working Days90
Addl Days Granted0
Working Days Charged29
Percent Time Used32
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-28-064
M & D FOUNDATION DRILLING INDUSTRIES, INC. (10.97)
FLASHER LIMITED (1.16)
HOUSTON SAWING & DRILLING (0.56)
J. R. (JOE) RAMON & SONS, INC. (5.14)
LONE STAR PAVING (4.40)
ZENITH SITE SERVICES (12.97)
BOWMAN ENGINEERING & CONSULTING, INC (0.82)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.64)
Contract #10173214
Totals349287.94149468.99262228.3175.0

CountyLAVACA
HighwayCR
FromAT NAVIDAD RIVER
ToSTR# AA05-22-001 (CR 14)
CSJ0913-29-031
Proj IDBR 2007(370)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.138567765.26539328.1296.2
Work Order08-16-17
Work Began11-06-17
Work Completed
Time Computed11-14-17
Contract Working Days75
Addl Days Granted0
Working Days Charged87
Percent Time Used116
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-29-031
FLASHER EQUIPMENT COMPANY (0.92)
FUQUAY, INC. (1.49)
ENVIRONMENTAL SAFETY SERVICES, INC. (3.01)
BEAIRD DRILLING (17.10)
Contract #06173222
Totals567765.2698408.00539328.1296.2

CountyLAVACA
HighwayCR
FromAT SMOTHERS CREEK CR 183
To(CR 183) STR AA01-02-004
CSJ0913-29-033
Proj IDBR 2007(372)
Work TypeREHABILITATE EXISTING BRIDGE
 
0.300733626.26240673.2632.8
Work Order08-08-17
Work Began01-03-18
Work Completed
Time Computed11-06-17
Contract Working Days60
Addl Days Granted0
Working Days Charged23
Percent Time Used38
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-29-033
S & S BRIDGE PAINTING, INC. (20.80)
FLASHER LIMITED (0.51)
FUQUAY, INC. (1.08)
CHOCTAW ERECTORS, INC. (17.03)
Contract #07173215
Totals733626.264500.00240673.2632.8

CountyLAVACA
HighwayCR
FromAT LAVACA RIVER CR 260
To(CR 260) #AA01-69-001
CSJ0913-29-035
Proj IDBR 2018(794)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.135573001.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-14-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DALRYMPLE GRAVEL AND CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-29-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183020
Totals573001.800.000.000.0

CountyLAVACA
HighwayCR
FromAT CAMPBELL BRANCH_____CR 198
ToSTR# 13-143-0-AA01-02-001
CSJ0913-29-050
Proj IDBR 2017(117)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.101451306.00284129.2562.9
Work Order09-21-17
Work Began02-19-18
Work Completed
Time Computed12-20-17
Contract Working Days90
Addl Days Granted0
Working Days Charged27
Percent Time Used30
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-29-050
SPECIALTY DRILLING, LTD. (9.49)
Contract #08173238
Totals451306.00194590.00284129.2562.9

CountyDEWITT
HighwayFM 237
FromSH 72
ToUS 183
CSJ0941-01-024
Proj IDSTP 2018(256)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
15.198856905.050.000.0
Work Order12-08-17
Work Began05-04-18
Work Completed
Time Computed03-08-18
Contract Working Days170
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0941-01-024
JMHP, INC. (3.20)
PAVEMENT MARKINGS INC. (0.60)
FLASHER LIMITED (1.33)
Contract #11173208
Totals856905.050.000.000.0

CountyGONZALES
HighwayFM 532
FromUS 90A
ToLAVACA COUNTY LINE
CSJ1007-02-017
Proj IDSTP 2013(919)
Work TypeROADWAY WIDENING
 
13.7758097588.878232746.4199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-10-13
Work Began12-03-13
Work Completed
Time Computed12-03-13
Contract Working Days285
Addl Days Granted13
Working Days Charged369
Percent Time Used123
Contractor(s)
SMC CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1007-02-017
FOX QUALITY CONCRETE, L.L.C. (3.01)
M.V. HENKE ENTERPRISES, INC. (0.46)
F. N. PLOCH CONSTRUCTION COMPANY, INC. (12.05)
C-3 ENVIRONMENTAL SPECIALTIES, LP (1.07)
LAND STABILIZER, LTD (7.21)
ROADWAY SPECIALTIES, INC. (0.21)
FLASHER EQUIPMENT COMPANY (1.71)
ZAMCO TRUCKING, LLC (1.29)
RELMCO, INC. (3.69)
INTERSTATE BARRICADES & MARKINGS, INC. (0.08)
ARIAS & ASSOCIATES, INC. (0.12)
LONE STAR PAVING (24.35)
FUTURE CONCRETE STRUCTURES (1.28)
A BROTHERS MILLING, LLC (0.45)
BR CARTAGE COMPANY (0.00)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.15)
PENHALL COMPANY (0.05)
Contract #07133251
Totals8097588.870.008232746.4199.9

CountyLAVACA
HighwayFM 532
FromGONZALES C/L
ToSH 95
CSJ1007-03-021
Proj IDSTP 2016(509)
Work TypeRESTORE ROADWAY
 
4.6082721588.222761037.2999.9
CountyLAVACA
HighwayFM 1680
From0.5 MI N OF FM 532
ToFM 532
CSJ1442-04-010
Proj IDSTP 2016(509)
Work TypeRESTORE ROADWAY
 
0.460122619.12156471.2499.9
Work Order05-17-16
Work Began08-15-16
Work Completed
Time Computed08-15-16
Contract Working Days120
Addl Days Granted7
Working Days Charged126
Percent Time Used99
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1007-03-021
BEAVER CONTRACTORS, LLC (6.89)
COWBELL TRAFFIC SERVICES, INC. (0.33)
FLASHER EQUIPMENT COMPANY (0.27)
INTERSTATE BARRICADES & MARKINGS, INC. (2.27)
LONE STAR EROSION CONTROL (0.67)
MURRAY CONSTRUCTION (0.55)
ROADWAY SPECIALTIES, INC. (0.77)
MV HENKE COMPANY, LLC (0.27)
MPB, INC. (6.69)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (0.00)
RAMI MATERIALS TRANSPORT, LLC (0.00)
STRIPE-A-ZONE, INC. (0.33)
Contract #02163245
Totals2844207.340.002917508.5399.9

CountyLAVACA
HighwayFM 958
FromFM 966
ToSH 95
CSJ1008-02-018
Proj IDC 1008-2-18
Work TypeSUBGRADE WIDEN, BASE, RESURFACING
 
5.0123498600.693422541.7398.7
Work Order10-25-16
Work Began12-12-16
Work Completed
Time Computed01-24-17
Contract Working Days135
Addl Days Granted0
Working Days Charged169
Percent Time Used125
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1008-02-018
FLASHER EQUIPMENT COMPANY (3.95)
ROADWAY SPECIALTIES, INC. (1.31)
DELGADO"S CONSTRUCTION (4.22)
ANGEL BROTHERS ENTERPRISES, LTD. (12.00)
WEST TEXAS RUMBLE STRIP (0.15)
Contract #06163219
Totals3498600.690.003422541.7398.7

CountyCALHOUN
HighwayFM 1593
From0.22 MILES NORTH OF SH 35
To0.05 MILES SOUTH OF SH 35
CSJ1090-05-015
Proj IDSTP 1702(172)
Work TypeWIDEN ROADWAY, SIGNAL UPGRADES
 
0.4901354288.45233685.5017.2
Work Order07-14-17
Work Began02-12-18
Work Completed
Time Computed10-12-17
Contract Working Days67
Addl Days Granted10
Working Days Charged35
Percent Time Used45
Contractor(s)
JIMMY EVANS COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1090-05-015
FUQUAY, INC. (49.75)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (7.99)
Contract #05173218
Totals1354288.4567195.00233685.5017.2

CountyDEWITT
HighwayFM 766
FromEND OF STATE MAINTENANCE
To3.922 MI. NORTH OF FM 953
CSJ1113-01-026
Proj IDC 1113-1-26
Work TypeRESTORE ROADWAY
 
8.1394871848.954827367.1799.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-17-16
Work Began10-10-16
Work Completed
Time Computed11-15-16
Contract Working Days165
Addl Days Granted0
Working Days Charged165
Percent Time Used100
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1113-01-026
INTERSTATE BARRICADES & MARKINGS, INC. (1.41)
FLASHER EQUIPMENT COMPANY (0.25)
ROADWAY SPECIALTIES, INC. (1.27)
MPB, INC. (10.98)
(USE 25816)D & S TEXAS ICON CONSTRUCTION, LLC. (1.06)
MURRAY CONSTRUCTION (0.28)
Contract #07163014
Totals4871848.950.004827367.1799.0

CountyFAYETTE
HighwayFM 1115
From0.8 MI W OF FM 2762
ToGONZALES C/L
CSJ1262-01-014
Proj IDSTP 1602(482)
Work TypeRESTORE ROADWAY
 
5.6143558330.173334658.1393.7
Work Order10-05-16
Work Began12-28-16
Work Completed
Time Computed01-04-17
Contract Working Days150
Addl Days Granted0
Working Days Charged150
Percent Time Used100
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1262-01-014
EGGEMEYER LAND CLEARING, LLC (1.52)
FLASHER EQUIPMENT COMPANY (0.23)
LONE STAR EROSION CONTROL (1.52)
MURRAY CONSTRUCTION (0.50)
RELMCO, INC. (18.95)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.48)
ROADWAY SPECIALTIES, INC. (2.72)
NEWMAN & KENG PAVING COMPANY, INC. (2.67)
Contract #08163224
Totals3558330.170.003334658.1393.7

CountyAUSTIN
HighwayFM 1457
FromFAYETTE C/L
ToSH 159
CSJ1411-02-011
Proj IDSTP 1702(489)
Work TypeRESTORE ROADWAY
 
5.8534469341.791420585.0331.7
Work Order08-08-17
Work Began11-20-17
Work Completed
Time Computed11-06-17
Contract Working Days150
Addl Days Granted3
Working Days Charged63
Percent Time Used41
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1411-02-011
ROADWAY SPECIALTIES, INC. (4.36)
AREA WIDE PROTECTIVE, INC. (0.25)
J & M CONTRACTING COMPANY (17.81)
D.I.J. CONSTRUCTION, INC (1.85)
Contract #07173021
Totals4469341.79341470.101420585.0331.7

CountyFAYETTE
HighwayFM 1457
FromAT ROCKY CREEK
ToSTR # 1441-01-001
CSJ1441-01-012
Proj IDBR 2016(062)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.2041089950.261173753.9099.9
Work Order11-16-15
Work Began01-14-16
Work Completed
Time Computed12-16-15
Contract Working Days120
Addl Days Granted0
Working Days Charged106
Percent Time Used88
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 1441-01-012
JJ KOONS, LLC. (17.29)
RICE ENVIRONMENTAL SERVICES (5.36)
N-LINE TRAFFIC MAINTENANCE, L.P. (9.62)
BEAIRD DRILLING (2.11)
LONE STAR PAVING (10.85)
ENVIRONMENTAL SAFETY SERVICES, INC. (8.10)
Contract #09153210
Totals1089950.260.001173753.9099.9

CountyAUSTIN
HighwayFM 1094
From7.2 MI WEST OF SH 36(SCHLUENS RD)
To0.4 MI WEST OF SH 36(HOWARD ST)
CSJ1721-02-012
Proj IDSTP 1502(478)HES
Work TypeSAFETY TREAT FIXED OBJECTS,WIDEN SH
 
6.7493954433.253844565.0397.3
Work Order01-29-16
Work Began03-23-16
Work Completed
Time Computed05-29-16
Contract Working Days150
Addl Days Granted0
Working Days Charged155
Percent Time Used103
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1721-02-012
CEN TEX HYDROSEED, INC. (2.77)
J & M CONTRACTING, COMPANY (11.03)
D.I.J. CONSTRUCTION, INC (3.33)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.27)
ANGEL BROTHERS ENTERPRISES, LTD. (5.54)
Contract #11153009
Totals3954433.250.003844565.0397.3

CountyDEWITT
HighwayFM 966
FromAT DRAW
ToSTR # 130620216602001
CSJ2166-02-007
Proj IDBR 2018(509)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.064338050.00222781.0067.0
Work Order03-14-18
Work Began04-16-18
Work Completed
Time Computed04-14-18
Contract Working Days45
Addl Days Granted0
Working Days Charged10
Percent Time Used22
Contractor(s)
DALRYMPLE GRAVEL AND CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2166-02-007
LONE STAR PAVING COMPANY (6.65)
D. I. J. CONSTRUCTION, INC. (2.65)
Contract #02183019
Totals338050.00222781.00222781.0067.0

CountyVICTORIA
HighwayUS 77
From0.52 MI. EAST OF FM 1685
To1.04 MI. WEST OF US 87
CSJ2350-01-041
Proj IDC 2350-1-41
Work TypeCONSTRUCTING TWO ADDITIONAL LANES
 
2.49321361349.8220938077.7698.0
Work Order11-24-15
Work Began01-18-16
Work Completed
Time Computed12-24-15
Contract Working Days450
Addl Days Granted0
Working Days Charged452
Percent Time Used100
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2350-01-041
CAT SKINNER, LLC. (0.78)
ROADWAY SPECIALTIES, INC. (1.33)
FLASHER EQUIPMENT COMPANY (0.48)
MCL CONTRACTING, LLC (0.50)
W. W. FOUNDATION DRILLING, LTD. (3.01)
WEBBER, LLC (12.42)
THE LEVY COMPANY, L.P. (0.23)
PRIMATE CONSTRUCTION, INC. (0.19)
ANDERSON COLUMBIA CO., INC. (22.71)
VALCO CONSTRUCTION (0.22)
PRIMATE CONSTRUCTION, INC. (0.05)
AARON CONCRETE CONTRACTORS, L.P. (0.62)
W. W. FOUNDATION DRILLING, LTD. (2.01)
SCOTT DERR PAINTING CO (0.02)
CERTIFIED PLACERS LLC (0.08)
MCL CONTRACTING, LLC (0.22)
CPAVE, INC. (0.19)
Contract #09153036
Totals21361349.8225731.3420938077.7698.0

CountyVICTORIA
HighwaySL 463
FromMOCKINGBIRD_LANE
ToBU 59T
CSJ2350-01-054
Proj IDNH 1702(188)
Work TypeCONSTRUCT FRONTAGE ROAD
 
2.0904467052.112049157.4845.8
Work Order09-08-17
Work Began12-13-17
Work Completed
Time Computed12-07-17
Contract Working Days165
Addl Days Granted0
Working Days Charged55
Percent Time Used33
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2350-01-054
THE LEVY COMPANY, L.P. (2.47)
FLASHER EQUIPMENT COMPANY (1.09)
ROADWAY SPECIALTIES, INC. (1.05)
MURRAY CONSTRUCTION (0.33)
Contract #08173223
Totals4467052.11569014.472049157.4845.8

CountyVICTORIA
HighwaySL 463
FromUS 77
To0.6 MI WEST OF FM 1315
CSJ2350-01-057
Proj IDNH 2018(838)
Work TypePAVEMENT REPAIR AND RESURFACING
 
3.3916854284.040.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days135
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2350-01-057
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183042
Totals6854284.040.000.000.0

CountyVICTORIA
HighwayUS 77
FromUS 77(FRONTAGE RD) AT MALLETTE DR
To.
CSJ2350-01-059
Proj IDNH 2018(567)
Work TypeCONSTRUCT TRAFFIC SIGNAL
 
0.010335632.920.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-12-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days49
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 2350-01-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183229
Totals335632.920.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7