Monthly State Let Construction Report For Yoakum District As Of Apr 10, 2018 Page 4 Of 6

Last Update: Friday, April 20, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyAUSTIN
HighwaySH 159
FromFM 109
ToSH 36
CSJ0408-02-045
Proj IDSTP 2015(428)
Work TypeADD SHOULDERS
 
14.07911278713.119776929.9886.6
Work Order02-10-15
Work Began07-13-15
Work Completed
Time Computed06-10-15
Contract Working Days417
Addl Days Granted10
Working Days Charged392
Percent Time Used91
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0408-02-045
ROADWAY SPECIALTIES, INC. (2.18)
WEST TEXAS RUMBLE STRIP (0.16)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.57)
Contract #12143204
Totals11278713.11779999.429776929.9886.6

CountyAUSTIN
HighwaySH 159
FromEAST MILL CREEK
ToSTR # 130080040802024
CSJ0408-02-046
Proj IDBR 2018(508)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.6433793059.920.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-14-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days300
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0408-02-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183218
Totals3793059.920.000.000.0

CountyJACKSON
HighwaySH 172
FromBAKER STREET IN GANADO
ToWASHINGTON STREET IN LA WARD
CSJ0420-01-040
Proj IDSTP 2016(804)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
21.531864757.006184.000.7
Work Order09-21-17
Work Began00-00-00
Work Completed
Time Computed12-20-17
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0420-01-040
D&S TEXAS ICON CONSTRUCTION (6.39)
ACME BARRICADES, LLC (2.96)
JB PINNACLE GROUP, LLC (63.81)
Contract #08173227
Totals864757.006184.006184.000.7

CountyLAVACA
HighwayUS 90A
From@ BRUSHY CREEK
ToSTR # 0446-01-016
CSJ0446-01-047
Proj IDBR 2015(245)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.6063321678.023176331.3498.8
Work Order12-11-14
Work Began06-08-15
Work Completed
Time Computed04-10-15
Contract Working Days150
Addl Days Granted0
Working Days Charged259
Percent Time Used172
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0446-01-047
ANGEL BROTHERS ENTERPRISES, LTD. (9.33)
ROADWAY SPECIALTIES, INC. (1.29)
INTERSTATE BARRICADES & MARKINGS, INC. (0.52)
HEMPHILL PILE DRIVING CO., A CORP. (3.49)
FLASHER EQUIPMENT COMPANY (0.29)
Contract #10143213
Totals3321678.029766.003176331.3498.8

CountyLAVACA
HighwayUS 90A
From0.2 MI W OF FM 530
To4.5 MI E OF FM 530
CSJ0446-01-048
Proj IDSTP 2017(701)HES
Work TypeSAFTEY TREAT FIXED OBJECTS
 
4.700793103.50542111.8072.8
Work Order03-15-17
Work Began06-05-17
Work Completed
Time Computed06-13-17
Contract Working Days90
Addl Days Granted0
Working Days Charged149
Percent Time Used165
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0446-01-048
ROADWAY SPECIALTIES, INC. (9.23)
LONESTAR TRAFFIC SAFETY, LLC (0.50)
Contract #02173018
Totals793103.5036900.00542111.8072.8

CountyCOLORADO
HighwayUS 90A
FromSH 71
ToEAST A STREET IN EAGLE LAKE
CSJ0446-03-049
Proj IDSTP 1502(050)
Work TypeCONSTRUCT SUPER 2 LANES
 
7.9296297396.256768994.7899.9
Work Order05-19-15
Work Began08-26-15
Work Completed
Time Computed08-26-15
Contract Working Days183
Addl Days Granted31
Working Days Charged214
Percent Time Used100
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0446-03-049
WEST TEXAS RUMBLE STRIP (0.20)
M.V. HENKE ENTERPRISES, INC. (0.59)
RICE ENVIRONMENTAL SERVICES (0.69)
DUSTROL, INC. (0.37)
INTERSTATE BARRICADES & MARKINGS, INC. (1.26)
SCMU (3.28)
LONESTAR TRAFFIC SAFETY, LLC (0.19)
ROADWAY SPECIALTIES, INC. (0.84)
Contract #03153232
Totals6297396.250.006768994.7899.9

CountyJACKSON
HighwayFM 616
FromSH 172
To3.2 MI E OF SH 172(W. CARANCAHUA CR
CSJ0497-03-009
Proj IDSTP 2017(702)
Work TypeRESTORE ROADWAY
 
3.3002063461.481857267.8390.2
Work Order03-08-17
Work Began07-10-17
Work Completed
Time Computed06-06-17
Contract Working Days105
Addl Days Granted0
Working Days Charged111
Percent Time Used105
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0497-03-009
ROADSAFE TRAFFIC SYSTEMS, INC. (1.46)
ROADWAY SPECIALTIES, INC. (4.71)
Contract #02173214
Totals2063461.4875009.661857267.8390.2

CountyJACKSON
HighwayFM 234 ETC
From7.6 MI N OF US 59
To3.3 MI N OF US 59
CSJ0515-01-068
Proj IDSTP 2018(390)HES
Work TypeSAFETY TREAT FIXED OBJECTS, WIDEN
 
12.3236463046.290.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-05-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days348
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0515-01-068
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183220
Totals6463046.290.000.000.0

CountyAUSTIN
HighwayFM 1458
From3.4 MI S OF IH 10 (WARD BEND RD)
ToFM 1093
CSJ0527-03-024
Proj IDSTP 2017(493)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
7.9281002148.60981943.2097.9
Work Order03-30-17
Work Began09-08-17
Work Completed
Time Computed06-18-17
Contract Working Days90
Addl Days Granted0
Working Days Charged90
Percent Time Used100
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0527-03-024
LYNCO CONSTRUCTION (5.82)
Contract #01173243
Totals1002148.602920.00981943.2097.9

CountyGONZALES
HighwayIH 10
FromCALDWELL COUNTY LINE
ToSANDY FORK CREEK
CSJ0535-04-030
Proj IDNH 2017(832)
Work TypeACP OVERLAY
 
20.70514770182.695072541.8034.3
Work Order04-24-17
Work Began07-17-17
Work Completed
Time Computed05-24-17
Contract Working Days180
Addl Days Granted0
Working Days Charged70
Percent Time Used38
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0535-04-030
AWP, INC. (0.16)
DIAMOND SURFACE, INC. (0.22)
DUSTROL, INC. (2.82)
PRIMATE CONSTRUCTION, INC. (2.81)
INTERSTATE BARRICADES & MARKINGS, INC. (4.22)
Contract #03173003
Totals14770182.69288345.855072541.8034.3

CountyGONZALES
HighwayFM 1116
FromSH 97
To7.2 MI S OF SH 97
CSJ0573-04-015
Proj IDSTP 1702(643)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
14.4004044139.16449126.7711.1
Work Order09-21-17
Work Began01-09-18
Work Completed
Time Computed12-20-17
Contract Working Days180
Addl Days Granted0
Working Days Charged29
Percent Time Used16
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0573-04-015
MPB, INC. (22.17)
FLASHER LIMITED (0.55)
PAVEMENT MARKINGS INC. (1.40)
ROADWAY SPECIALTIES, INC. (3.53)
MURRAY CONSTRUCTION (0.46)
Contract #08173228
Totals4044139.16329746.00449126.7711.1

CountyDEWITT
HighwayFM 240
FromVFW ROAD (CR 185)
ToSH 72
CSJ0573-05-019
Proj IDSTP 2018(606)
Work TypePAVEMENT REPAIR AND RESURFACING
 
1.7211191777.380.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days67
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0573-05-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183017
Totals1191777.380.000.000.0

CountyMATAGORDA
HighwayFM 457
From0.020 MILES NORTH OF MARINA DRIVE
ToCANAL DRIVE
CSJ0605-01-060
Proj IDBR 2017(973)
Work TypeREPLACE SWING BRIDGE
 
0.60841231131.02284052.000.6
Work Order08-16-17
Work Began00-00-00
Work Completed
Time Computed02-12-18
Contract Working Days405
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0605-01-060
AREA WIDE PROTECTIVE, INC. (0.04)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.12)
COX MCLAIN ENVIRONMENTAL CONSULTING, INC. (0.17)
THE LEVY COMPANY, L.P. (0.96)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.37)
BOWMAN ENGINEERING & CONSTRUCTION, INC. (2.40)
WEBBER BARRIER SERVICES, LLC. (0.32)
MATAGORDA CONSTRUCTION & MATERIALS (0.79)
HIGHWAY BARRICADES AND SERVICES, LLC (0.02)
J.C. COMMUNICATION (0.10)
LONE STAR PAVING COMPANY (0.41)
Contract #07173202
Totals41231131.0256052.00284052.000.6

CountyWHARTON
HighwayFM 3012
FromOLD CANEY RD (CR 154)
ToFM 1096
CSJ0709-03-008
Proj IDSTP 2018(459)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
14.2294587960.510.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-05-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days262
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0709-03-008
RUCOBA & MAYA CONSTRUCTION (17.28)
AREA WIDE PROTECTIVE, INC. (0.60)
HIGHWAY BARRICADES AND SERVICES, LLC (1.25)
MURRAY CONSTRUCTION (0.56)
D&S TEXAS ICON CONSTRUCTION (1.87)
Contract #01183034
Totals4587960.510.000.000.0

CountyGONZALES
HighwayFM 443
FromAT ROCKY CREEK
ToSTR # 0839-01-002
CSJ0839-01-015
Proj IDBR 2017(259)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.3211222090.601194756.0098.0
Work Order12-28-16
Work Began04-06-17
Work Completed
Time Computed01-28-17
Contract Working Days75
Addl Days Granted17
Working Days Charged98
Percent Time Used106
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0839-01-015
HEMPHILL WBE PILE DRIVING CO. (5.11)
HIGHWAY BARRICADES AND SERVICES, LLC (0.43)
(USE 07366)J.R. RAMON & SONS, INC (1.43)
O & S TRAFFIC SUPPLIES (0.29)
PENHALL COMPANY (0.34)
REXCO CONSTRUCTION SERVICES, INC. (24.04)
TEXAS SHAFTS, INC. (6.73)
MCL CONTRACTING, LLC (0.32)
12-1 HIGHWAY AND ENVIRONMENTAL SERVICES, LLC (2.48)
FRANK JR REINFORCEMENT LLC (0.56)
Contract #11163209
Totals1222090.600.001194756.0098.0

CountyMATAGORDA
HighwayFM 521
FromFM 1468
To0.057 MI WEST OF SH 60
CSJ0846-03-046
Proj IDSTP 2018(607)
Work TypeACP OVERLAY
 
8.5691521680.370.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-09-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0846-03-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183018
Totals1521680.370.000.000.0

CountyDEWITT
HighwayVA
FromVARIOUS LOCATIONS
ToIN AUSTIN, MATAGORDA, & WHARTON CO.
CSJ0913-00-088
Proj IDSTP 2012(527)
Work TypeCONSTRUCT CURB RAMPS
 
0.100475081.00577322.1799.9
Work Order06-18-12
Work Began04-05-13
Work Completed
Time Computed10-16-12
Contract Working Days165
Addl Days Granted0
Working Days Charged142
Percent Time Used86
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-00-088
PAVEMENT MARKINGS INC. (1.39)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.79)
SPEEDY PAVING (2.40)
Contract #05123217
Totals475081.000.00577322.1799.9

CountyDEWITT
HighwayVA
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ0913-00-092
Proj IDBR 2016(133)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
0.0023378506.553485715.2199.9
CountyDEWITT
HighwayVA
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ0913-00-094
Proj IDNH 2016(134)
Work TypeCONCRETE RAIL REPAIR
 
0.00190833.20156947.4299.9
Work Order11-24-15
Work Began01-18-16
Work Completed
Time Computed12-24-15
Contract Working Days203
Addl Days Granted105
Working Days Charged305
Percent Time Used99
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-00-092
WEST TEXAS RUMBLE STRIP (0.13)
D & S TEXAS ICON CONSTRUCTION, LLC. (4.10)
TINMAN ENTERPRISES (5.32)
ROADSAFE TRAFFIC SYSTEMS, INC. (6.74)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (19.38)
Contract #10153213
Totals3469339.750.003642662.6399.9

CountyWHARTON
HighwayCR
FromAT WEST MUSTANG CREEK CR 372
To(CR 372) STR # AA06-59-001
CSJ0913-09-053
Proj IDBR 2012(407)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.074629675.00597441.4098.0
Work Order07-07-15
Work Began11-11-15
Work Completed
Time Computed10-06-15
Contract Working Days75
Addl Days Granted0
Working Days Charged108
Percent Time Used144
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-053
HEMPHILL PILE DRIVING CO., A CORP. (4.74)
ODUM SERVICES, L.P. (3.89)
JUST GROOVING, LTD. (0.25)
CEN TEX HYDROSEED, INC. (0.33)
Contract #05153048
Totals629675.000.00597441.4098.0

CountyWHARTON
HighwayCR
FromAT EAST CARANCAHUA CREEK CR 458
To(CR 322) STR # AA04-58-001
CSJ0913-09-056
Proj IDBR 2012(409)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.061552981.25543131.0798.2
Work Order06-14-17
Work Began10-25-17
Work Completed
Time Computed09-12-17
Contract Working Days73
Addl Days Granted0
Working Days Charged72
Percent Time Used98
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-056
TRIPLE J-SA CONSTRUCTION (15.34)
HEMPHILL WBE PILE DRIVING CO. (11.34)
LONESTAR TRAFFIC SAFETY, LLC (0.52)
HOUSTON SAWING & DRILLING (0.29)
ZENITH SITE SERVICES (11.00)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.87)
Contract #05173236
Totals552981.2532781.52543131.0798.2

page 1 | page 2 | page 3 | page 4 | page 5 | page 6