Monthly State Let Construction Report For Yoakum District As Of Oct 11, 2018 Page 1 Of 7

Last Update: Thursday, October 11, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyGONZALES
HighwayUS 90A
FromGUADALUPE C/L
To8.702 MI E OF GUADALUPE C/L
CSJ0025-05-021
Proj IDSTP 1802(494)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
16.2892179041.090.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days192
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MPB, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-05-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08183036
Totals2179041.090.000.000.0

CountyGONZALES ETC
HighwaySH 97 ETC
FromSH 304
ToSANDY FORK SOUTH RELIEF
CSJ0025-07-064
Proj IDSTP 2018(255)
Work TypeSEAL COAT
 
186.2305889198.085630350.4395.6
Work Order12-14-17
Work Began07-12-18
Work Completed
Time Computed01-14-18
Contract Working Days45
Addl Days Granted0
Working Days Charged41
Percent Time Used91
Contractor(s)
F. N. PLOCH CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-07-064
BATTERSON,LLP (17.59)
Contract #11173207
Totals5889198.082056341.825630350.4395.6

CountyGONZALES
HighwayUS 90
From0.013 MI W OF FM 1680
To0.01 MI W OF FAYETTE C/L
CSJ0026-01-027
Proj IDSTP 2018(604)
Work TypePAVEMENT REPAIR AND RESURFACING
 
6.4762613600.861230979.2847.0
Work Order04-18-18
Work Began06-26-08
Work Completed
Time Computed06-01-18
Contract Working Days135
Addl Days Granted0
Working Days Charged52
Percent Time Used38
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0026-01-027
ROADWAY SPECIALTIES, INC. (0.85)
CHEROKEE SERVICES (1.21)
FLASHER LIMITED (0.35)
TRP CONSTRUCTION GROUP, LLC (4.02)
UNDER CONSTRUCTION INC. (1.79)
Contract #03183221
Totals2613600.86127204.441230979.2847.0

CountyFAYETTE
HighwayUS 90
FromAT MIDDLE CREEK
ToSTR # 0026-03-028
CSJ0026-03-042
Proj IDBR 2017(318)
Work TypeWIDEN BRIDGE AND APPROACHES
 
0.288831842.19814791.3299.9
Work Order01-10-17
Work Began03-03-17
Work Completed
Time Computed04-10-17
Contract Working Days60
Addl Days Granted0
Working Days Charged121
Percent Time Used201
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0026-03-042
DELGADO"S CONSTRUCTION (60.07)
EGGEMEYER LAND CLEARING, LLC (2.87)
ROADWAY SPECIALTIES, INC. (3.88)
FLASHER EQUIPMENT COMPANY (0.39)
PAVEMENT MARKINGS INC. (0.94)
Contract #12163022
Totals831842.190.00814791.3299.9

CountyFAYETTE
HighwayUS 90
FromUS 77
ToIH 10
CSJ0026-03-043
Proj IDSTP 2016(506)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
3.326958370.00920233.4797.5
Work Order05-09-16
Work Began10-05-16
Work Completed
Time Computed08-08-16
Contract Working Days75
Addl Days Granted0
Working Days Charged99
Percent Time Used132
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0026-03-043
F. N. PLOCH CONSTRUCTION COMPANY, INC. (2.12)
Contract #01163220
Totals958370.000.00920233.4797.5

CountyCOLORADO
HighwayUS 90
FromAT COLORADO RIVER
ToSTR # 0027-01-001
CSJ0027-01-040
Proj IDBR 2016(507)
Work TypeCONSTRUCT ONE WAY BRIDGE AND APPR
 
0.3647142388.401183770.0016.5
Work Order06-21-17
Work Began00-00-00
Work Completed
Time Computed09-19-17
Contract Working Days350
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0027-01-040
HIGHWAY 1, LLC (0.60)
LONESTAR TRAFFIC SAFETY, LLC (0.25)
HOUSTON SAWING & DRILLING (0.11)
W. W. FOUNDATION DRILLING, LTD. (6.76)
CHOCTAW ERECTORS, INC. (7.10)
Contract #05173011
Totals7142388.400.001183770.0016.5

CountyCOLORADO
HighwayUS 90A
FromFM 102 IN EAGLE LAKE
ToWHARTON COUNTY LINE
CSJ0027-03-071
Proj IDSTP 1702(426)
Work TypeCONSTRUCT SUPER 2 LANES
 
5.0284487326.992243606.2749.9
Work Order08-11-17
Work Began10-25-17
Work Completed
Time Computed11-09-17
Contract Working Days160
Addl Days Granted0
Working Days Charged109
Percent Time Used68
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0027-03-071
AREA WIDE PROTECTIVE, INC. (0.26)
D. I. J. CONSTRUCTION, INC. (1.88)
D&S TEXAS ICON CONSTRUCTION (0.35)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.27)
RIOS TRUCKING CO. (1.40)
STRIPE-A-ZONE, INC. (0.27)
Contract #06173243
Totals4487326.99498408.452243606.2749.9

CountyVICTORIA
HighwayUS 59
FromBU 59T
ToGOLIAD C/L
CSJ0088-04-070
Proj IDNH 2018(158)
Work TypeACP OVERLAY
 
6.1794506272.520.000.0
Work Order05-17-18
Work Began00-00-00
Work Completed
Time Computed06-17-18
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-04-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183231
Totals4506272.520.000.000.0

CountyVICTORIA
HighwayUS 59
From0.5 MI S OF FM 1686
ToSL 463
CSJ0088-05-085
Proj IDC 88-5-85
Work TypeCONSTRUCT FRONTAGE ROADS
 
2.76927884764.50254240.000.9
CountyVICTORIA
HighwayUS 59
From0.5 MI S OF FM 1686
ToSL 463
CSJ0088-05-099
Proj IDROW 88-5-99
Work TypeUTILITY ONLY
 
3.329708858.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-19-18
Work Began09-17-18
Work Completed
Time Computed00-00-00
Contract Working Days600
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-085
AWP, INC. DBA AREA WIDE PROTECTIVE (0.02)
Contract #05183003
Totals28593622.70254240.00254240.000.8

CountyVICTORIA
HighwayUS 59
FromLP 463
ToSPUR 91
CSJ0088-05-091
Proj IDNH 2018(506)
Work TypeACP OVERLAY
 
10.5889267866.660.000.0
Work Order03-15-18
Work Began00-00-00
Work Completed
Time Computed04-15-18
Contract Working Days165
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-091
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183235
Totals9267866.660.000.000.0

CountyVICTORIA
HighwayUS 59
From1.26 MI NORTH OF US 87
To1.73 MI NORTH OF US 87
CSJ0088-05-092
Proj IDC 88-5-92
Work TypeCONSTRUCT 4-LANE OVERPASS
 
0.4908914435.178583195.3196.5
Work Order11-23-16
Work Began07-06-17
Work Completed
Time Computed02-21-17
Contract Working Days165
Addl Days Granted5
Working Days Charged194
Percent Time Used114
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-092
HOUSTON SAWING & DRILLING (0.04)
LONE STAR EROSION CONTROL (0.18)
MCL CONTRACTING, LLC (0.34)
ROADWAY SPECIALTIES, INC. (0.96)
STRIPE LINES, INC. (0.74)
V.C. HUFF, L.L.C. (2.16)
WEST TEXAS RUMBLE STRIP (0.05)
W. W. FOUNDATION DRILLING, LTD. (2.31)
AARON CONCRETE CONTRACTORS, L.P. (2.83)
INDUS CONSTRUCTION, L.P. (0.25)
Contract #10163032
Totals8914435.177746.098583195.3196.5

CountyVICTORIA ETC
HighwayUS 59 ETC
From2.00 MI N OF SP 91
ToSP 91
CSJ0088-05-094
Proj IDSTP 1702(483)HES
Work TypeINSTALL MEDIAN BARRIER
 
16.4791983066.571802867.5891.9
Work Order08-08-17
Work Began11-13-17
Work Completed
Time Computed11-06-17
Contract Working Days90
Addl Days Granted0
Working Days Charged115
Percent Time Used127
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-094
(USE 25816)D & S TEXAS ICON CONSTRUCTION, LLC. (6.00)
LONESTAR TRAFFIC SAFETY, LLC (0.69)
Contract #07173008
Totals1983066.570.001802867.5891.9

CountyVICTORIA
HighwayBU 59-T
FromAT FM 236
To.
CSJ0088-06-004
Proj IDSTP 2018(836)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
0.400316189.2880777.2025.5
Work Order06-11-18
Work Began09-04-18
Work Completed
Time Computed09-09-18
Contract Working Days50
Addl Days Granted0
Working Days Charged3
Percent Time Used6
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0088-06-004
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183216
Totals316189.2880777.2080777.2025.5

CountyVICTORIA
HighwayUS 59
From0.4 MI. EAST OF FM 1686
ToJACKSON C/L
CSJ0089-01-090
Proj IDNH 2016(965)
Work TypeACP OVERLAY
 
8.0107280415.335139244.3970.5
Work Order00-00-00
Work Began03-06-17
Work Completed
Time Computed05-31-16
Contract Working Days105
Addl Days Granted10
Working Days Charged111
Percent Time Used96
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0089-01-090
CHEROKEE SERVICES (2.45)
DIAMOND K SERVICES, INC. (0.24)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.45)
Contract #04163208
Totals7280415.330.005139244.3970.5

CountyJACKSON
HighwayUS 59
FromFROM 0.5 MI. NORTH OF LAVACA RIVER
ToVICTORIA COUNTY LINE
CSJ0089-03-088
Proj IDNH 2016(508)
Work TypeACP OVERLAY
 
6.5646620873.225497977.4283.0
Work Order03-01-16
Work Began03-06-17
Work Completed
Time Computed03-16-16
Contract Working Days90
Addl Days Granted0
Working Days Charged89
Percent Time Used98
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0089-03-088
MPB, INC. (8.62)
DIAMOND SURFACE, INC. (0.24)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.37)
Contract #01163029
Totals6620873.22858576.305497977.4283.0

CountyWHARTON
HighwayUS 59
FromFM 647 (NORTHBOUND ONLY)
ToJACKSON COUNTY LINE
CSJ0089-06-079
Proj IDNH 2016(700)
Work TypePAVEMENT REPAIR & ACP OVERLAY
 
8.9743681313.693508904.7695.5
Work Order03-07-16
Work Began08-23-16
Work Completed
Time Computed03-19-16
Contract Working Days60
Addl Days Granted28
Working Days Charged95
Percent Time Used107
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-079
FLASHER EQUIPMENT COMPANY (2.62)
WEST TEXAS RUMBLE STRIP (0.18)
MPB, INC. (5.42)
Contract #02163029
Totals3681313.690.003508904.7695.5

CountyWHARTON
HighwayUS 59
FromBU 59 SOUTH OF EL CAMPO
ToFM 1163
CSJ0089-06-081
Proj IDNH 1502(476)
Work TypeCONSTRUCT FRONTAGE RO025809111
 
2.60218889263.0319004278.6599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-07-16
Work Began06-14-16
Work Completed
Time Computed10-04-16
Contract Working Days324
Addl Days Granted0
Working Days Charged360
Percent Time Used111
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-081
ROADSAFE TRAFFIC SYSTEMS, INC. (0.64)
WILLOW CITY SIGN & RAIL, INC. (1.38)
MBN ENTERPRISES LLC (2.93)
SEMARCK LANDSCAPE SERVICES, INC. (0.69)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (4.23)
J & M CONTRACTING, COMPANY (6.90)
Contract #11153007
Totals18889263.030.0019004278.6599.9

CountyWHARTON
HighwayUS 59
FromLP 524 N. OF HILLJE (NB LANES ONLY)
To0.130 MI.N.OF FM 647(NB LANES ONLY)
CSJ0089-06-088
Proj IDNH 1702(485)
Work TypeACP OVERLAY
 
17.2038161719.844607674.3356.7
Work Order08-16-17
Work Began01-08-18
Work Completed
Time Computed11-14-17
Contract Working Days84
Addl Days Granted0
Working Days Charged103
Percent Time Used122
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-088
BATTERSON,LLP (3.59)
DEVTEX INC. (2.18)
A BROTHERS MILLING, LLC (1.99)
WEST TEXAS RUMBLE STRIP (0.17)
Contract #07173210
Totals8161719.849082.854607674.3356.7

CountyWHARTON
HighwayUS 59
FromFM 1163
ToLP 524 N. OF HILLJE
CSJ0089-06-090
Proj IDC 89-6-90
Work TypeACP OVERLAY
 
8.4497009733.690.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-24-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days133
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-090
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08183021
Totals7009733.690.000.000.0

CountyWHARTON
HighwayBU 59-R
From0.9 MI. SOUTH OF SH 60
ToSH 60 IN WHARTON
CSJ0089-10-022
Proj IDBR 1602(449)
Work TypeREHABILITATE EXISTING BRIDGE
 
0.9194875271.506845893.6399.9
Work Order01-17-17
Work Began02-15-17
Work Completed
Time Computed02-15-17
Contract Working Days170
Addl Days Granted193
Working Days Charged322
Percent Time Used88
Contractor(s)
CEKRA INC.
SUBCONTRACTOR(S) FOR CCSJ: 0089-10-022
HAYWARD BAKER, INC. (4.92)
PENHALL COMPANY (AUSTIN) (7.14)
ANGEL BROTHERS ENTERPRISES, LTD. (3.40)
STRIPE LINES, INC. (1.04)
Contract #11163222
Totals4875271.500.006845893.6399.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7