Monthly State Let Construction Report For Wichita Falls District As Of Jun 08, 2018 Page 2 Of 3

Last Update: Tuesday, June 12, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBAYLOR
HighwayUS 82
FromAPPROX. 1 MILE WEST OF US 183 (WB)
ToAPPROX. 1 MILE EAST OF US 183 (WB)
CSJ0156-06-052
Proj IDNH 1802(199)
Work TypeREHABILITATION OF EXISTING ROAD
 
1.9903745737.670.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days212
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0156-06-052
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183053
Totals3745737.670.000.000.0

CountyWICHITA
HighwayIH 44
From0.023 MI. S OF SH 240
ToOKLAHOMA STATE LINE
CSJ0156-07-109
Proj IDSTP 1702(401)HES
Work TypeHAZARD ELIMINATION SAFETY
 
2.5001167403.501194466.0099.9
Work Order07-20-17
Work Began10-11-17
Work Completed
Time Computed08-19-17
Contract Working Days85
Addl Days Granted2
Working Days Charged82
Percent Time Used94
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0156-07-109
CONTRACTORS SERVICE COMPANY (0.85)
AARON CONCRETE CONTRACTORS, L.P. (6.60)
W.S. CONSTRUCTION COMPANY (12.69)
Contract #06173038
Totals1167403.50120149.001194466.0099.9

CountyMONTAGUE
HighwaySH 59
FromFM 1758
ToMILL STREET
CSJ0239-02-037
Proj IDSTP 2018(557)
Work TypeREHABILITATION OF EXISTING ROAD
 
1.8671182793.98553826.5846.8
Work Order03-07-18
Work Began04-18-18
Work Completed
Time Computed04-06-18
Contract Working Days60
Addl Days Granted0
Working Days Charged28
Percent Time Used46
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0239-02-037
TOTAL HIGHWAY MAINTENANCE, LLC (0.34)
WOLFE CONSTRUCTION GROUP, INC. (0.37)
TOTAL HIGHWAY MAINTENANCE, LLC (1.90)
Contract #02183006
Totals1182793.98412671.33553826.5846.8

CountyCOOKE
HighwayFM 51
FromELM FORK TRINITY RIVER
ToONE HORSE LANE
CSJ0312-01-078
Proj IDSTP 2017(403)
Work TypeREHABILITATION OF EXISTING ROAD
 
0.467706189.82704773.3499.7
Work Order05-18-17
Work Began09-21-17
Work Completed
Time Computed06-19-17
Contract Working Days102
Addl Days Granted10
Working Days Charged78
Percent Time Used69
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0312-01-078
WOLFE CONSTRUCTION GROUP, INC. (1.85)
COMEN ENTERPRISE LLC (6.26)
TOTAL HIGHWAY MAINTENANCE, LLC (1.05)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION, LTD. (8.47)
ALTUS TRAFFIC MANAGEMENT LLC (0.63)
GOLDEN TREE MAINTENANCE (0.84)
W.O.E. CONSTRUCTION (0.60)
Contract #04173233
Totals706189.824990.08704773.3499.7

CountyTHROCKMORTON
HighwayUS 380
FromHASKELL COUNTY LINE
ToNEAR WEST CL OF THROCKMORTON
CSJ0360-05-029
Proj IDC 360-5-29
Work TypeRESTORATION
 
15.8543381084.970.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days48
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0360-05-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183242
Totals3381084.970.000.000.0

CountyCLAY
HighwayFM 810
FromFM 171
ToSH 79
CSJ0391-02-018
Proj IDSTP 1702(124)
Work TypeREHABLITATION OF EXISTING ROAD
 
15.9031895820.801791104.5894.4
Work Order06-14-17
Work Began08-21-17
Work Completed
Time Computed07-14-17
Contract Working Days170
Addl Days Granted0
Working Days Charged123
Percent Time Used72
Contractor(s)
BEAR CREEK CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0391-02-018
ODUM SERVICES, L.P. (4.46)
ALTUS TRAFFIC MANAGEMENT LLC (0.11)
Contract #05173003
Totals1895820.800.001791104.5894.4

CountyWICHITA
HighwaySH 240
FromAT CHINA CREEK
To.
CSJ0514-01-041
Proj IDBR 2018(764)
Work TypeBRIDGE REPLACEMENT
 
0.076877613.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-14-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days153
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0514-01-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183031
Totals877613.800.000.000.0

CountyWILBARGER
HighwayFM 91
FromFM 91 AT WANDERERS CREEK
To.
CSJ0702-01-014
Proj IDBR 2016(928)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.7672458571.502542508.1799.9
Work Order06-02-16
Work Began09-13-16
Work Completed
Time Computed07-02-16
Contract Working Days187
Addl Days Granted15
Working Days Charged241
Percent Time Used119
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0702-01-014
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.47)
DALLAS LITE AND BARRICADE INC. (0.76)
BARRICADES UNLIMITED (1.40)
HOUSTON SAWING & DRILLING (0.30)
LANCO TURF & SEEDING, INC. (2.01)
MCL CONTRACTING, LLC (0.57)
RK HALL, LLC (5.01)
Contract #04163019
Totals2458571.500.002542508.1799.9

CountyWICHITA
HighwayFM 369
FromNEAR MCNIEL AVE
ToNEAR RHEA RD
CSJ0802-02-053
Proj IDNH 2017(606)
Work TypeMISCELLANEOUS WORK
 
0.2004475438.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days155
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0802-02-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183046
Totals4475438.000.000.000.0

CountyCOOKE
HighwayFM 373
FromCR 450
ToMUENSTER
CSJ0823-01-029
Proj IDSTP 2018(824)
Work TypeREHABILITAITON OF EXISTION ROAD
 
18.1132899372.260.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days204
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0823-01-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183218
Totals2899372.260.000.000.0

CountyWICHITA
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
ToVARIOUS LOCATIONS DISTRICTWIDE
CSJ0903-00-083
Proj IDSTP 1702(126)
Work TypeTRAFFIC MANAGEMENT
 
1.000938930.00945641.1499.9
Work Order06-08-17
Work Began10-25-17
Work Completed
Time Computed10-06-17
Contract Working Days68
Addl Days Granted0
Working Days Charged62
Percent Time Used91
Contractor(s)
MICA CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-083
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173214
Totals938930.0046060.50945641.1499.9

CountyWICHITA
HighwayVA
FromON IH 44, US 287, US 82, AND US 281
ToIN WICHITA AND WILBARGER COUNTIES
CSJ0903-00-088
Proj IDSTP 2018(583)
Work TypeSIGN UPGRADE
 
0.100497863.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-13-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days43
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-088
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183032
Totals497863.800.000.000.0

CountyWICHITA
HighwayCS
FromON MAPLEWOOD AVENUE SOUTH BOUND AT
ToDRAINAGE DITCH
CSJ0903-03-083
Proj IDBR 2006(550)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.2001293885.00737542.6957.0
Work Order07-20-17
Work Began03-13-18
Work Completed
Time Computed08-19-17
Contract Working Days123
Addl Days Granted0
Working Days Charged47
Percent Time Used38
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0903-03-083
LANCO TURF & SEEDING, INC. (0.99)
ALTUS TRAFFIC MANAGEMENT LLC (0.31)
PREMIER PAVING, LTD. (6.75)
BARRICADES UNLIMITED (0.69)
Contract #06173206
Totals1293885.00220551.89737542.6957.0

CountyMONTAGUE
HighwayCR
FromCR 541 (SIGNED CARTER LAKE)
ToAT HERRING BRANCH OF BIG SANDY
CSJ0903-28-064
Proj IDBR 1702(567)
Work TypeBRIDGE REPLACEMENT
 
0.062376569.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-14-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0903-28-064
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183025
Totals376569.500.000.000.0

CountyARCHER
HighwayCR
FromCR 246 (BRITTON LANE) AT DRAW
To.
CSJ0903-29-026
Proj IDBR 1702(564)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.200265264.900.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-17-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
REECE CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-29-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183205
Totals265264.900.000.000.0

CountyYOUNG
HighwayFM 209
FromFM 578
To3.69 MI WEST OF SH 67
CSJ1076-02-040
Proj IDSTP 2017(881)
Work TypeRESTORATION
 
14.0332333357.951014199.3243.4
Work Order04-19-17
Work Began06-16-17
Work Completed
Time Computed05-19-17
Contract Working Days213
Addl Days Granted6
Working Days Charged204
Percent Time Used93
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1076-02-040
W.S. CONSTRUCTION COMPANY (40.00)
ALTUS TRAFFIC MANAGEMENT LLC (0.72)
COMEN ENTERPRISE LLC (3.42)
TOTAL HIGHWAY MAINTENANCE, LLC (1.43)
WOLFE CONSTRUCTION GROUP, INC. (0.80)
NIXON ENGINEERING (0.12)
Contract #03173036
Totals2333357.95110092.761014199.3243.4

CountyMONTAGUE
HighwayFM 455
From1.056 MI WEST OF FM 730
To0.056 MI WEST OF FM 730
CSJ1352-02-021
Proj IDSTP 1702(127)HES
Work TypeHAZARD ELIMINATION SAFETY
 
1.000554791.65648299.7399.9
Work Order06-08-17
Work Began11-27-17
Work Completed
Time Computed07-08-17
Contract Working Days103
Addl Days Granted0
Working Days Charged73
Percent Time Used70
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1352-02-021
TOTAL HIGHWAY MAINTENANCE, LLC (1.04)
WOLFE CONSTRUCTION GROUP, INC. (1.89)
SOUTHERN CROSS CONTRACTORS, LLC (1.59)
TOTAL HIGHWAY MAINTENANCE, LLC (2.53)
Contract #05173205
Totals554791.6578094.49648299.7399.9

CountyCOOKE
HighwayFM 678
FromFM 3164
To0.339 MILES SOUTH OF US 82.
CSJ1357-02-012
Proj IDSTP 1602(201)
Work TypeREHABILITATION OF EXISTING ROADWAY
 
2.5451677816.781670396.1299.5
Work Order08-17-16
Work Began10-24-16
Work Completed
Time Computed09-16-16
Contract Working Days125
Addl Days Granted0
Working Days Charged124
Percent Time Used99
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1357-02-012
ALTUS TRAFFIC MANAGEMENT LLC (0.49)
W.S. CONSTRUCTION COMPANY (12.10)
TOTAL HIGHWAY MAINTENANCE, LLC (1.19)
MARCOM"S MOWING SERVICE, LLC (0.52)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (8.99)
TEXAS ALTERNATIVE GRASSER, INC. (0.52)
OSCAR ORDUNO, INC. (2.62)
Contract #06163009
Totals1677816.785342.401670396.1299.5

CountyYOUNG
HighwayFM 1769
FromSH 114
ToUS 380
CSJ1711-01-029
Proj IDSTP 2017(404)
Work TypeREHABILITATION OF EXISTING ROAD
 
7.9863310004.481208349.6636.5
Work Order01-10-18
Work Began03-05-18
Work Completed
Time Computed02-09-18
Contract Working Days153
Addl Days Granted0
Working Days Charged57
Percent Time Used37
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1711-01-029
WEST TEXAS RUMBLE STRIP (0.12)
COMEN ENTERPRISE LLC (0.67)
WOLFE CONSTRUCTION GROUP, INC. (1.11)
DUSTIN ALLEN, INC. (1.46)
TOTAL HIGHWAY MAINTENANCE, LLC (3.60)
DUSTROL, INC. (2.04)
Contract #12173209
Totals3310004.48516994.891208349.6636.5

CountyCLAY
HighwayFM 2393
FromN OF WESTBOUND FRONTAGE ROAD
ToRR ROW
CSJ2405-01-012
Proj IDSTP 2018(558)
Work TypeREHABILITATION OF EXISTING ROAD
 
2.7042307479.20319083.1013.8
Work Order03-08-18
Work Began04-16-18
Work Completed
Time Computed04-07-18
Contract Working Days95
Addl Days Granted0
Working Days Charged31
Percent Time Used32
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2405-01-012
W.S. CONSTRUCTION COMPANY (11.11)
TOTAL HIGHWAY MAINTENANCE, LLC (2.57)
HJC FARMS, INC. (0.89)
WEST TEXAS RUMBLE STRIP (0.16)
Contract #02183209
Totals2307479.20153509.66319083.1013.8

page 1 | page 2 | page 3