|
Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | CLAY |
Highway | SH 79 |
From | FM 171 (SOUTH) |
To | RED RIVER RELIEF STRUCTURE |
CSJ | 0282-02-031 |
Proj ID | F 2023(806) |
Work Type | OVERLAY |
|
| | 3246126.19 | | 671456.17 | 20.6 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 06-07-23 |
Work Began | 09-18-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 60 |
Addl Days Granted | 0 |
Working Days Charged | 15 |
Percent Time Used | 25 |
Contractor(s) |
ZACK BURKETT CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0282-02-031 TRP CONSTRUCTION GROUP, LLC (2.22) HJC FARMS, INC. (1.20) LANCO TURF & SEEDING, INC. (0.23) BARRICADES UNLIMITED (0.22)
|
Contract # | 05233057 |
| Totals | 3246126.19 | 548913.85 | 671456.17 | 20.6 |
|
County | CLAY |
Highway | SH 79 |
From | APPROX 1 MILE NORTH OF FM 2393 |
To | SH 148 |
CSJ | 0282-03-031 |
Proj ID | F 2023(794) |
Work Type | OVERLAY |
|
| | 4472468.25 | | 1883873.30 | 42.2 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 06-07-23 |
Work Began | 08-14-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 127 |
Addl Days Granted | 0 |
Working Days Charged | 133 |
Percent Time Used | 104 |
Contractor(s) |
ZACK BURKETT CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0282-03-031 JR WEST TEXAS CONCRETE LLC (15.21) HJC FARMS, INC. (3.23) TRP CONSTRUCTION GROUP, LLC (1.61) FC TRAFFIC CONTROL, INC. (0.36) LANCO TURF & SEEDING, INC. (0.41)
|
Contract # | 05233021 |
| Totals | 4472468.25 | 613818.21 | 1883873.30 | 42.2 |
|
County | WICHITA ETC |
Highway | FM 2380 ETC |
From | FM 369 |
To | ARCHER COUNTY LINE |
CSJ | 0283-01-018 |
Proj ID | F 2023(810) |
Work Type | OVERLAY |
|
| | 7479603.50 | | 241611.16 | 3.2 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 06-07-23 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 119 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
ZACK BURKETT CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0283-01-018 CHEROKEE SERVICES (0.35) BARRICADES UNLIMITED (0.73) DUSTROL, INC. (8.75) TRP CONSTRUCTION GROUP, LLC (2.51)
|
Contract # | 05233254 |
| Totals | 7479603.50 | 0.00 | 241611.16 | 3.2 |
|
County | THROCKMORTON |
Highway | SH 79 |
From | YOUNG COUNTY LINE |
To | MEXICAN SPRINGS RD |
CSJ | 0284-02-026 |
Proj ID | F 2023(922) |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| | 7963304.67 | | 1633344.58 | 20.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 07-12-23 |
Work Began | 12-12-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 238 |
Addl Days Granted | 0 |
Working Days Charged | 70 |
Percent Time Used | 29 |
Contractor(s) |
DUININCK, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0284-02-026 SURFACE PREPARATION TECHNOLOGIES, LLC (0.20) TEXOP CONSTRUCTION (0.24) BARRICADES UNLIMITED (0.48) FLAT LINE, INC. (0.78) MARCOMS CONSTRUCTION LLC (0.73) WOLFE CONSTRUCTION GROUP, INCORPORATED (0.91) DUSTIN ALLEN, INC. (0.65) W. S. CONSTRUCTION COMPANY (2.51) CLARK HAULING SOLUTIONS LLC (0.50) ZACK BURKETT CO. (0.50) WEST INFRASTRUCTURE CONSTRUCTION, LLC (0.62) SAENZ TRANSPORT, LLC (0.62) RILEY INDUSTRIAL SERVICES, INC. (0.41)
|
Contract # | 06233214 |
| Totals | 7963304.67 | 420369.92 | 1633344.58 | 20.5 |
|
County | THROCKMORTON |
Highway | SH 79 |
From | MEXICAN SPRINGS RD |
To | US 183 |
CSJ | 0284-02-027 |
Proj ID | C 284-2-27 |
Work Type | WIDEN NON-FREEWAY |
|
| | 7882206.69 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 02-02-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 178 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
A. L. HELMCAMP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0284-02-027 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01243012 |
| Totals | 7882206.69 | 0.00 | 0.00 | 0.0 |
|
County | CLAY |
Highway | SH 148 |
From | FM 1883 |
To | RUSSELL CREEK |
CSJ | 0391-04-030 |
Proj ID | STP 2022(627)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 0.554 | 3432425.50 | | 359068.09 | 11.7 |
County | ZERO COUNTIES |
Highway | |
From | |
To | |
CSJ | 0391-05-021 |
Proj ID | |
Work Type | |
|
| | 0.00 | | 2067976.57 | 0.0 |
County | ZERO COUNTIES |
Highway | |
From | |
To | |
CSJ | 0391-05-022 |
Proj ID | |
Work Type | |
|
| | 0.00 | | 855044.14 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 07-11-22 |
Work Began | 10-04-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 181 |
Addl Days Granted | 0 |
Working Days Charged | 225 |
Percent Time Used | 124 |
Contractor(s) |
ZACK BURKETT CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0391-04-030 W. S. CONSTRUCTION COMPANY (11.64) HJC FARMS, INC. (5.12) TOTAL HIGHWAY MAINTENANCE, LLC (0.38) WOLFE CONSTRUCTION GROUP, INCORPORATED (1.28) TRP CONSTRUCTION GROUP, LLC (1.61)
|
Contract # | 06223218 |
| Totals | 3432425.50 | 5000.00 | 3282088.80 | 96.8 |
|
County | CLAY |
Highway | SH 148 |
From | SH 148 AT RUSSELL CREEK |
To | . |
CSJ | 0391-05-023 |
Proj ID | BR 2022(628) |
Work Type | BRIDGE MAINTENANCE |
|
| | 141638.30 | | 0.00 | 0.0 |
County | CLAY |
Highway | SH 148 |
From | SH 148 AT E FORK OF THE LITTLE WICHITA R |
To | . |
CSJ | 0391-05-024 |
Proj ID | BR 2022(628) |
Work Type | BRIDGE MAINTENANCE |
|
| | 125478.30 | | 0.00 | 0.0 |
County | CLAY |
Highway | SH 148 |
From | FM 174 |
To | NEAR W PLEASANT VALLEY RD |
CSJ | 0391-05-025 |
Proj ID | F 2023(923) |
Work Type | WIDEN NON-FREEWAY |
|
| | 4499454.60 | | 898772.10 | 19.9 |
County | CLAY |
Highway | SH 148 |
From | NEAR W PLEASANT VALLEY RD |
To | JACK CL |
CSJ | 0391-05-026 |
Proj ID | F 2023(923) |
Work Type | WIDEN NON-FREEWAY |
|
| | 2113038.51 | | 391203.05 | 18.5 |
Work Order | 07-26-23 |
Work Began | 10-02-23 |
Work Completed | |
Time Computed | 08-28-23 |
Contract Working Days | 316 |
Addl Days Granted | 0 |
Working Days Charged | 94 |
Percent Time Used | 29 |
Contractor(s) |
A. L. HELMCAMP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0391-05-023 WOLFE CONSTRUCTION GROUP, INCORPORATED (1.10) COLD CREEK CONSTRUCTION, LTD (4.15) DUSTIN ALLEN, INC. (2.77) FC TRAFFIC CONTROL, INC. (0.47) FLAT LINE, INC. (0.55) MARCOMS CONSTRUCTION LLC (0.52) SURFACE PREPARATION TECHNOLOGIES, LLC (0.24) W. S. CONSTRUCTION COMPANY (15.25)
|
Contract # | 06233009 |
| Totals | 6879609.71 | 195595.00 | 1289975.15 | 18.7 |
|
County | MONTAGUE |
Highway | FM 677 |
From | FM 677 |
To | AT COBB HOLLOW |
CSJ | 0423-02-025 |
Proj ID | F 2023(620) |
Work Type | BRIDGE REPLACEMENT |
|
| | 2630598.36 | | 2126494.08 | 80.8 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 05-10-23 |
Work Began | 09-18-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 220 |
Addl Days Granted | 0 |
Working Days Charged | 117 |
Percent Time Used | 53 |
Contractor(s) |
COPPELL CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0423-02-025 BARRICADES UNLIMITED (0.38) GREGORY PILE DRIVING, INC. (1.84) REYNOLDS ASPHALT & CONSTRUCTION COMPANY (3.17) HODGES AND SON CONSTRUCTION COMPANY, INC. (7.86) TORO BRAVO CONSTRUCTION, LLC (0.22) MORRIS COUNTY CONTRACTORS, L.L.C. (0.81) GARY A. CRAIN, INC. (0.12)
|
Contract # | 04233034 |
| Totals | 2630598.36 | 260949.66 | 2126494.08 | 80.8 |
|
County | YOUNG |
Highway | SH 114 |
From | SH 79 |
To | 0.8 MI WEST OF FM 1769 |
CSJ | 0444-01-044 |
Proj ID | F 2023(055) |
Work Type | SUPER-2 HIGHWAY |
|
| | 10524957.68 | | 1146912.81 | 10.8 |
County | YOUNG |
Highway | SH 114 |
From | SH 114 AT SALT CREEK |
To | . |
CSJ | 0444-01-046 |
Proj ID | F 2023(207) |
Work Type | BRIDGE MAINTENANCE |
|
| | 87937.50 | | 88396.88 | 99.9 |
Work Order | 10-06-22 |
Work Began | 03-06-23 |
Work Completed | |
Time Computed | 12-20-22 |
Contract Working Days | 275 |
Addl Days Granted | 0 |
Working Days Charged | 234 |
Percent Time Used | 85 |
Contractor(s) |
ZACK BURKETT CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0444-01-044 W. S. CONSTRUCTION COMPANY (11.72) LANCO TURF & SEEDING, INC. (1.04) CONTRACTORS SERVICE, LTD. (0.64) TRP CONSTRUCTION GROUP, LLC (1.61) HJC FARMS, INC. (3.38)
|
Contract # | 09223021 |
| Totals | 10612895.18 | 105715.96 | 1235309.69 | 11.6 |
|
County | YOUNG |
Highway | FM 701 |
From | FM 701 |
To | AT CLEAR FORK OF THE BRAZOS RIVER |
CSJ | 0570-03-019 |
Proj ID | BR 2023(333) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.114 | 3033426.36 | | 1863648.35 | 61.4 |
County | YOUNG |
Highway | FM 701 |
From | FM 701 |
To | AT CLEAR FORK BRAZOS RIVER |
CSJ | 0570-03-020 |
Proj ID | BR 1802(482) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.105 | 2535575.11 | | 802201.51 | 31.6 |
County | YOUNG |
Highway | FM 1974 |
From | FM 1974 |
To | AT CLEAR FORK OF THE BRAZOS RIVER |
CSJ | 2217-01-015 |
Proj ID | BR 2023(334) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.087 | 2276443.53 | | 2355003.88 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 02-27-23 |
Work Began | 05-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 336 |
Addl Days Granted | 0 |
Working Days Charged | 197 |
Percent Time Used | 58 |
Contractor(s) |
INDUS ROAD & BRIDGE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0570-03-019 FC TRAFFIC CONTROL, INC. (0.03) WYLIE DRILLING & DRAINAGE, INC. (6.29) ODUM SERVICES, LLC (1.30) PENHALL COMPANY (0.13) S & S BRIDGE PAINTING, INC. (0.77) HERMANOS STEEL, LLC (0.53) KING GEORGE TRAFFIC SOLUTIONS LLC (0.32) PEACHTREE CONSTRUCTION, LTD. (7.84) WOLFE CONSTRUCTION GROUP, INCORPORATED (0.63) TORO BRAVO CONSTRUCTION, LLC (0.20)
|
Contract # | 01233211 |
| Totals | 7845445.00 | 74392.18 | 5020853.74 | 63.9 |
|
County | BAYLOR |
Highway | FM 422 |
From | FM 422 |
To | AT GODWIN CREEK |
CSJ | 0814-01-037 |
Proj ID | BR 2024(544) |
Work Type | BRIDGE REPLACEMENT |
|
| | 2860939.10 | | 670268.60 | 23.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 01-17-24 |
Work Began | 02-20-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 144 |
Addl Days Granted | 0 |
Working Days Charged | 29 |
Percent Time Used | 20 |
Contractor(s) |
THK CONSTRUCTION LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0814-01-037 SUPERIOR TRAFFIC CONTROL, LLC (1.63) TRAFFIC HIGHWAY MAINTENANCE, LLC (1.77) MORRIS COUNTY CONTRACTORS, L.L.C. (1.81) TORO BRAVO CONSTRUCTION, LLC (0.05) WOLFE CONSTRUCTION GROUP, INCORPORATED (0.78) PEACHTREE CONSTRUCTION, LTD. (9.14) HODGES AND SON CONSTRUCTION COMPANY, INC. (5.33) AWP SAFETY (0.10)
|
Contract # | 12233029 |
| Totals | 2860939.10 | 338650.60 | 670268.60 | 23.4 |
|
County | WICHITA |
Highway | VA |
From | VARIOUS LOCATIONS IN THE |
To | WICHITA AND GRAHAM AREAS |
CSJ | 0903-00-119 |
Proj ID | F 2022(378) |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 689012.10 | | 689757.84 | 99.9 |
Work Order | 06-22-22 |
Work Began | 12-15-22 |
Work Completed | |
Time Computed | 09-20-22 |
Contract Working Days | 70 |
Addl Days Granted | 0 |
Working Days Charged | 74 |
Percent Time Used | 105 |
Contractor(s) |
WG ENGINEERING & CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-119 MEDELLIN HDD LLC (8.25)
|
Contract # | 05223024 |
| Totals | 689012.10 | 3222.40 | 689757.84 | 99.9 |
|
County | WICHITA |
Highway | VA |
From | VARIOUS LOCATIONS IN THE |
To | GAINESVILLE AREA |
CSJ | 0903-00-120 |
Proj ID | F 2022(377) |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 833158.86 | | 757937.83 | 92.6 |
Work Order | 06-22-22 |
Work Began | 02-15-23 |
Work Completed | |
Time Computed | 09-20-22 |
Contract Working Days | 78 |
Addl Days Granted | 0 |
Working Days Charged | 101 |
Percent Time Used | 129 |
Contractor(s) |
WG ENGINEERING & CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-120 MEDELLIN HDD LLC (6.41)
|
Contract # | 05223229 |
| Totals | 833158.86 | 3399.00 | 757937.83 | 92.6 |
|
County | WICHITA |
Highway | VA |
From | VARIOUS LOCATIONS |
To | IN THE WICHITA FALLS DISTRICT |
CSJ | 0903-00-122 |
Proj ID | C 903-00-122 |
Work Type | BRIDGE MAINTENANCE |
|
| | 1041194.00 | | 1073294.10 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 06-14-23 |
Work Began | 09-05-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 68 |
Addl Days Granted | 0 |
Working Days Charged | 51 |
Percent Time Used | 75 |
Contractor(s) |
SHALOM SERVICES CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-122 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05233042 |
| Totals | 1041194.00 | 0.00 | 1073294.10 | 99.9 |
|
County | WICHITA |
Highway | VA |
From | VARIOUS LOCATIONS |
To | IN WICHITA AND CLAY COUNTIES |
CSJ | 0903-00-123 |
Proj ID | C 903-00-123 |
Work Type | BRIDGE MAINTENANCE |
|
| | 1166854.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 153 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
PATHFIELD INVESTMENTS LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-123 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03243224 |
| Totals | 1166854.00 | 0.00 | 0.00 | 0.0 |
|
County | CLAY |
Highway | VA |
From | WITHIN LAKE ARROWHEAD STATE PARK |
To | . |
CSJ | 0903-06-022 |
Proj ID | C 903-6-22 |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 0.100 | 2547006.80 | | 2873010.94 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 10-11-22 |
Work Began | 11-30-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 85 |
Addl Days Granted | 30 |
Working Days Charged | 98 |
Percent Time Used | 85 |
Contractor(s) |
DUININCK, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0903-06-022 DUSTROL, INC. (0.85) BARRICADES UNLIMITED (0.18) LANCO TURF & SEEDING, INC. (0.30) H & F TRUCKING (0.98)
|
Contract # | 09223015 |
| Totals | 2547006.80 | 0.00 | 2873010.94 | 99.9 |
|
County | ARCHER |
Highway | CR |
From | CR 232 (SIGNED WILSON RANCH ROAD) |
To | AT HOLLIDAY CREEK |
CSJ | 0903-29-027 |
Proj ID | BR 2020(351) |
Work Type | BRIDGE REPLACEMENT |
|
| | 385530.00 | | 371905.84 | 96.4 |
County | ARCHER |
Highway | CR |
From | CR 261 (SIGNED RIVER ROAD) |
To | AT DRAW |
CSJ | 0903-29-029 |
Proj ID | BR 2022(780) |
Work Type | BRIDGE REPLACEMENT |
|
| | 438686.00 | | 416352.39 | 94.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 02-16-23 |
Work Began | 04-03-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 102 |
Addl Days Granted | 0 |
Working Days Charged | 95 |
Percent Time Used | 93 |
Contractor(s) |
HODGES AND SON CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0903-29-027 LANCO TURF & SEEDING, INC. (3.41) DUSTIN ALLEN, INC. (5.33) TRAFFIC HIGHWAY MAINTENANCE, LLC (0.72) TORO BRAVO CONSTRUCTION, LLC (0.46)
|
Contract # | 01233023 |
| Totals | 824216.00 | 0.00 | 788258.23 | 95.6 |
|
County | COOKE |
Highway | FM 1198 |
From | US 82 |
To | FM 1630 |
CSJ | 1351-01-016 |
Proj ID | F 2023(924) |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 5.113 | 7202957.37 | | 2149005.75 | 29.8 |
County | COOKE |
Highway | FM 1198 |
From | FM 1630 |
To | FM 922 |
CSJ | 1351-02-007 |
Proj ID | F 2023(924) |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 5.539 | 4904538.62 | | 810445.95 | 16.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 07-19-23 |
Work Began | 10-16-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 407 |
Addl Days Granted | 0 |
Working Days Charged | 79 |
Percent Time Used | 19 |
Contractor(s) |
EUROVIA ATLANTIC COAST LLC |
SUBCONTRACTOR(S) FOR CCSJ: 1351-01-016 WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.57) SOUTHERN CROSS CONTRACTORS, LLC (1.56) DALLAS LITE AND BARRICADE, INC. (0.44) WEST TEXAS ROCK RESOURCES, LLC (0.15) JR WEST TEXAS CONCRETE LLC (15.65) JOE"S TREE SERVICE (0.17) TRP CONSTRUCTION GROUP, LLC (0.52)
|
Contract # | 06233208 |
| Totals | 12107495.99 | 369568.63 | 2959451.70 | 24.4 |
|
County | COOKE |
Highway | FM 1630 |
From | MONTAGUE COUNTY LINE |
To | CR 341 |
CSJ | 1609-01-029 |
Proj ID | STP 2B23(120)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 2744283.78 | | 1965357.06 | 71.6 |
County | COOKE |
Highway | FM 1630 |
From | CR 341 |
To | FM 373 |
CSJ | 1609-01-030 |
Proj ID | STP 2B23(120)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 1866856.85 | | 1097361.77 | 58.7 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 08-03-23 |
Work Began | 09-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 170 |
Addl Days Granted | 0 |
Working Days Charged | 108 |
Percent Time Used | 63 |
Contractor(s) |
JAGOE-PUBLIC COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1609-01-029 TEXAS TRAFFIC AND BARRICADE, LLC (0.34) DUSTROL, INC. (1.31) TRP CONSTRUCTION GROUP, LLC (3.33) SOUTHERN CROSS CONTRACTORS, LLC (1.67) WOLFE CONSTRUCTION GROUP, INCORPORATED (0.56)
|
Contract # | 06233618 |
| Totals | 4611140.63 | 341528.70 | 3062718.83 | 66.4 |
|
County | ARCHER |
Highway | FM 1954 |
From | US 281 |
To | CLAY COUNTY LINE |
CSJ | 1837-02-017 |
Proj ID | F 2023(091) |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 7.272 | 7814963.76 | | 2941444.98 | 37.6 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 10-06-22 |
Work Began | 01-16-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 221 |
Addl Days Granted | 74 |
Working Days Charged | 242 |
Percent Time Used | 82 |
Contractor(s) |
A. L. HELMCAMP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1837-02-017 W. S. CONSTRUCTION COMPANY (20.80) LANCO TURF & SEEDING, INC. (1.66) DUSTIN ALLEN, INC. (1.04) BARRICADES UNLIMITED (0.26) MARCOM"S MOWING SERVICE, LLC (0.63) TRAFFIC HIGHWAY MAINTENANCE, LLC (0.85)
|
Contract # | 09223235 |
| Totals | 7814963.76 | 402983.35 | 2941444.98 | 37.6 |
|