AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - TYLER DISTRICT

Last Update: Friday, June 29, 2018
ITEMS 247 6001 TO 275 6011
ItemsItemsBid Code Range
0100 - 0193
0247 - 0275
0310 - 0361
0400 - 0496
0500 - 0560
0610 - 0686
0712 - 0740
1002 - 1010
3000 - 3028
5040 - 5048
6000 - 6185
247 6001 - 275 6011
Item NoDescriptionUnitsJune 30, 2018Twelve-Month-MovingUsage
QuantityAvg BidQuantityAvg Bid
247 6001FL BS (CMP IN PLACE)(TYA GR1-2)(IN VEHCY  6,245.00063.261012
247 6061FL BS (CMP IN PLC)(TYA GR1-2) (6")SY  161,376.00011.171902
247 6232FL BS (CMP IN PLACE)(TY A GR 1-2)(11")SY56,107.00020.5000056,107.00020.500001
247 6233FL BS (CMP IN PLACE)(TY A GR 1-2)(12")SY  67,408.00023.500001
251 6033REWORK BS MTL (TY C) (6") (ORD COMP)SY  64,427.0001.000001
251 6034REWORK BS MTL (TY C) (8") (ORD COMP)SY  70,053.0002.870001
260 6001LIME (HYDRATED LIME (DRY))TON696.000169.816091,273.000174.432053
260 6027LIME TRT (EXST MATL)(8")SY39,510.0002.1909875,279.0002.812963
275 6001CEMENTTON696.000153.821844,097.000146.369547
275 6002CEMENT TREAT (EXIST MATL) (6")SY  652.0001.480001
275 6010CEMENT TREAT (SUBGRADE) (8")SY  9,611.0005.650001
275 6011CEMENT TREAT(EXIST MATL)(8")SY39,510.0001.69098243,389.0002.927185