Monthly State Let Maintenance Report For San Angelo District As Of Apr 12, 2024 Page 1 Of 2

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyKIMBLE
Highway0000000
From2124 NORTH MAIN (LOOP 481), JUNCTION
To.
CSJ4704-01-167
Proj IDCBC - 470401167
Work TypeJIM TATE PROJECT MANAGER
 
0.0011209888.001003145.0082.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days270
Addl Days Granted53
Working Days Charged262
Percent Time Used81
Contractor(s)
KENDNEL KASPER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-167
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07144217
Totals1209888.000.001003145.0082.9

CountyTOM GREEN
Highway0000000
From4502 KNICKERBOCKER RD
ToSAN ANGELO TX
CSJ4704-01-685
Proj IDCBC - 470401685
Work TypeRENOVATION AND REPAIR
 
0.001769600.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CS ADVANTAGE USAA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-685
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164223
Totals769600.000.000.000.0

CountySUTTON
HighwayRM1312
FromIRION COUNTY
ToSUTTON COUNTY
CSJ6205-40-001
Proj IDRMC - 620540001
Work TypeINSTALL BRIDGE RAIL & GUARD RAIL END TRE
 
0.001308769.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days70
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6205-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04104022
Totals308769.000.000.000.0

CountyCROCKETT
HighwaySH0163
FromVARIOUS LOCATIONS IN CROCKETT COUNTY
ToVARIOUS LOCATIONS IN CROCKETT COUNTY
CSJ6232-09-001
Proj IDRMC - 623209001
Work TypeSTRIP MOWING OF RIGHT OF WAY CROCKETT CO
 
0.001103536.0051768.0050.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-07-12
Work Began06-01-12
Work Completed
Time Computed06-01-12
Contract Working Days44
Addl Days Granted0
Working Days Charged9
Percent Time Used20
Contractor(s)
SPARKLES TRUCKING
SUBCONTRACTOR(S) FOR CCSJ: 6232-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10114005
Totals103536.000.0051768.0050.0

CountyTOM GREEN
HighwayUS0067
FromVARIOUS LOCATIONS IN TOM GREEN URBAN
ToVARIOUS LOCATIONS IN TOM GREEN URBAN
CSJ6245-64-001
Proj IDRMC - 624564001
Work TypeRIGHT OF WAY MOWING FOR TOM GREEN URBAN
 
0.001167384.880.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days24
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6245-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08124031
Totals167384.880.000.000.0

CountyKIMBLE
HighwayIH0010
FromVARIOUS LOCATIONS IN SAN ANGELO DISTRICT
ToVARIOUS LOCATIONS IN SAN ANGELO DISTRICT
CSJ6289-21-001
Proj IDRMC - 628921001
Work TypeMETAL BEAM GUARDFENCE
 
0.001319646.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6289-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08154210
Totals319646.000.000.000.0

CountyKIMBLE
HighwayIH0010
FromVARIOUS LOCATIONS IN SAN ANGELO DISTRICT
ToVARIOUS LOCATIONS IN SAN ANGELO DISTRICT
CSJ6343-31-001
Proj IDRMC - 634331001
Work TypeMETAL BEAM GUARDFENCE
 
0.001632830.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6343-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07194019
Totals632830.000.000.000.0

CountyKIMBLE
HighwayUS0377
FromVARIOUS LOCATIONS IN THE SAN ANGELO DIST
ToVARIOUS LOCATIONS IN THE SAN ANGELO DIST
CSJ6392-16-001
Proj IDRMC - 639216001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010636070.751213060.2699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-20-22
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged345
Percent Time Used47
Contractor(s)
T&L CLEANING SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6392-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04224015
Totals636070.7578165.251213060.2699.9

CountyTOM GREEN
HighwaySH0208
FromVARIOUS LOCATIONS IN TOM GREEN COUNTY
ToVARIOUS LOCATIONS IN TOM GREEN COUNTY
CSJ6400-98-001
Proj IDRMC - 640098001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.010628587.101360660.8099.9
Work Order07-12-22
Work Began07-18-22
Work Completed
Time Computed07-18-22
Contract Working Days365
Addl Days Granted365
Working Days Charged621
Percent Time Used85
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6400-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05224222
Totals628587.1041110.001360660.8099.9

CountyTOM GREEN
HighwayUS0067
FromCOUNTY WIDE
ToCOUNTY WIDE
CSJ6420-67-001
Proj IDRMC - 642067001
Work TypeREFLECTORIZED PAVEMENT MARKINGS & MARKE
 
0.010345145.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days44
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6420-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244003
Totals345145.100.000.000.0

CountyTOM GREEN
HighwaySH0208
FromVARIOUS LOCATIONS IN THE SAN ANGELO DIST
ToVARIOUS LOCATIONS IN SAN ANGELO DISTRICT
CSJ6420-75-001
Proj IDRMC - 642075001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101253756.001044007.5083.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-27-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
ROSS SA ENTERPRISE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6420-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02234210
Totals1253756.0090337.501044007.5083.2

CountyCONCHO
HighwayUS0083
FromVARIOUS LOCATIONS IN THE SAN ANGELO DIST
ToVARIOUS LOCATIONS IN SAN ANGELO DISTRICT
CSJ6422-14-001
Proj IDBPM - 642214001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010643690.00452930.0073.2
Work Order02-21-23
Work Began02-27-23
Work Completed
Time Computed02-27-23
Contract Working Days180
Addl Days Granted0
Working Days Charged231
Percent Time Used128
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6422-14-001
S&S BRIDGE PAINTING (2.33)
Contract #10224218
Totals643690.0011742.00452930.0073.2

CountyTOM GREEN
HighwaySH0208
FromVARIOUS LOCATIONS IN THE SAN ANGELO DIST
ToVARIOUS LOCATIONS IN THE SAN ANGELO DIST
CSJ6437-35-001
Proj IDRMC - 643735001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010661351.45648235.9098.0
Work Order06-02-23
Work Began06-05-23
Work Completed
Time Computed06-05-23
Contract Working Days365
Addl Days Granted0
Working Days Charged261
Percent Time Used71
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6437-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234217
Totals661351.4570740.83648235.9098.0

CountyKIMBLE
HighwayIH0010
FromIH 10 AT TRM 458.67
ToIH 10 AT TRM 461.37
CSJ6439-46-001
Proj IDRMC - 643946001
Work TypeASPHALT PAVEMENT WIDENING
 
0.0101132775.55915491.5581.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-11-23
Work Completed
Time Computed00-00-00
Contract Working Days55
Addl Days Granted0
Working Days Charged59
Percent Time Used107
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6439-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234023
Totals1132775.55194975.25915491.5581.1

CountyTOM GREEN
HighwaySH0208
FromDISTRICT WIDE
ToDISTRICT WIDE
CSJ6442-20-001
Proj IDRMC - 644220001
Work TypeCRACK SEAL
 
0.010490412.31428642.6787.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged41
Percent Time Used68
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6442-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234026
Totals490412.31428642.67428642.6787.4

CountyTOM GREEN
HighwayUS0087
FromVARIOUS LOCATIONS IN THE SAN ANGELO DIST
ToVARIOUS LOCATIONS IN SAN ANGELO DISTRICT
CSJ6442-22-001
Proj IDBPM - 644222001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010659949.00236500.0035.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged41
Percent Time Used22
Contractor(s)
DELGADO'S CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6442-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234027
Totals659949.0063000.00236500.0035.8

CountyKIMBLE
HighwayUS0377
FromVARIOUS LOCATIONS IN THE SAN ANGELO DIST
ToVARIOUS LOCATIONS IN THE SAN ANGELO DIST
CSJ6442-66-001
Proj IDRMC - 644266001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010648564.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
T&L CLEANING SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6442-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244004
Totals648564.000.000.000.0

CountyKIMBLE
HighwayIH0010
FromPECOS COUNTY LINE
ToKERR COUNTY LINE
CSJ6446-94-001
Proj IDRMC - 644694001
Work TypeDEBRIS REMOVAL
 
0.010643568.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN BARRICADE COMPANY, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6446-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234024
Totals643568.200.000.000.0

CountyKIMBLE
HighwayIH0010
FromPECOS COUNTY LINE
ToKERR COUNTY LINE
CSJ6460-37-001
Proj IDRMC - 646037001
Work TypeDEBRIS REMOVAL
 
0.010491390.4658050.0011.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged56
Percent Time Used15
Contractor(s)
SWEEPING CORPORATION OF AMERICA, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6460-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234040
Totals491390.4627584.1858050.0011.8

CountyTOM GREEN
HighwaySL0306
FromUS 87
To0.65 MILES NORTH OF FM 765
CSJ6462-13-001
Proj IDRMC - 646213001
Work TypeASPHALT
 
0.0102383456.900.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6462-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244012
Totals2383456.900.000.000.0

page 1 | page 2