Monthly State Let Construction Report For San Antonio District As Of Apr 10, 2018 Page 5 Of 6

Last Update: Friday, April 20, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2018
To.
CSJ0915-00-181
Proj IDSTP 2018(318)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.0011424651.889545.170.6
Work Order03-08-18
Work Began00-00-00
Work Completed
Time Computed05-01-18
Contract Working Days320
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-181
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183215
Totals1424651.889545.179545.170.6

CountyBEXAR
HighwayVA
FromDISTRICTWIDE GUIDESIGNS FY18
To.
CSJ0915-00-182
Proj IDSTP 2018(733)
Work TypeDISTRICTWIDE GUIDESIGNS FY18
 
0.0011921528.610.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days360
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-182
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183207
Totals1921528.610.000.000.0

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0915-00-186
Proj IDSTP 1702(556)
Work TypeTRAFFIC SIGNAL REHAB/UPGRADE
 
0.0012664496.9036343.501.3
Work Order08-11-17
Work Began00-00-00
Work Completed
Time Computed09-10-17
Contract Working Days319
Addl Days Granted0
Working Days Charged21
Percent Time Used6
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-186
FIBERTEL, LLC (1.82)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (0.47)
Contract #07173035
Totals2664496.9019302.0036343.501.3

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2017
To.
CSJ0915-00-204
Proj IDSTP 2017(894)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.0011349187.00898560.9566.6
Work Order05-09-17
Work Began07-18-17
Work Completed
Time Computed07-03-17
Contract Working Days320
Addl Days Granted0
Working Days Charged147
Percent Time Used45
Contractor(s)
D&G ENERGY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-204
L & R FOUNDATION DRILLING, INC. (1.03)
M & M STRIPING & POWER WASHING, LLC (4.15)
MINTCO GROUP LLC (1.60)
Contract #04173003
Totals1349187.00105584.50898560.9566.6

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2018
To.
CSJ0915-00-205
Proj IDSTP 2018(682)
Work TypeDISTRICTWIDE TRAFFIC CONTROL DEVICE
 
0.0011479469.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days320
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D&G ENERGY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-205
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183004
Totals1479469.000.000.000.0

CountyKENDALL
HighwayCS
FromSEVENTH ST AT CYPRESS CREEK
To.
CSJ0915-11-028
Proj IDBR 1102(443)
Work TypeREHABILITATE BRIDGE AND APPROACHES
 
0.067514522.70138297.7726.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-13-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days86
Addl Days Granted0
Working Days Charged47
Percent Time Used54
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0915-11-028
BEAIRD DRILLING (11.56)
ENVIRONMENTAL SAFETY SERVICES, INC. (3.32)
BOWMAN ENGINEERING & CONSTRUCTION, INC. (2.89)
FLASHER LIMITED (0.97)
HOUSTON SAWING & DRILLING (0.54)
GEOSOURCE, INC. (0.40)
Contract #10173226
Totals514522.7056534.00138297.7726.8

CountyBEXAR
HighwayCS
FromMILLER RD AT MARTINEZ CREEK
To.
CSJ0915-12-533
Proj IDBR 2014(912)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.102882311.770.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-14-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days237
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-533
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183208
Totals882311.770.000.000.0

CountyBEXAR
HighwayVA
FromVARIOUS BRIDGES IN BEXAR COUNY
To.
CSJ0915-12-551
Proj IDBR 1502(471)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
0.0011723801.411947939.6199.9
Work Order12-08-15
Work Began02-22-16
Work Completed
Time Computed02-06-16
Contract Working Days221
Addl Days Granted26
Working Days Charged250
Percent Time Used101
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-551
RICE ENVIRONMENTAL SERVICES (3.67)
FLASHER EQUIPMENT COMPANY (3.58)
RAMMING PAVING COMPANY (22.61)
CHEROKEE SERVICES (4.59)
Contract #10153005
Totals1723801.410.001947939.6199.9

CountyBEXAR
HighwayVA
FromIN SAN ANTONIO ON US 281, LOOP 345
ToFM 78 AND FM 1516 CORRIDORS
CSJ0915-12-555
Proj IDSTP 2016(870)TP
Work TypeGRD, BSE, SIDEWALKS, SIGN, PAVT MRK
 
0.0011771321.261641990.1993.1
CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BEXAR COUNTY
To.
CSJ0915-12-559
Proj IDSTP 1602(380)
Work TypeSIDEWALK
 
0.0013515369.102976451.0084.6
Work Order10-06-16
Work Began11-10-16
Work Completed
Time Computed11-05-16
Contract Working Days309
Addl Days Granted0
Working Days Charged316
Percent Time Used102
Contractor(s)
J3 COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-555
ROADWAY SPECIALTIES, INC. (2.66)
AUSTIN MATERIALS, LLC (1.91)
JARCO TRANSPORT, LLC (1.76)
LONE STAR EROSION CONTROL (4.43)
SAECO ELECTRIC & UTILITY, LTD. (0.20)
WEBB & BEXAR CONSTRUCTION, LLC. (8.59)
M & M STRIPING & POWER WASHING, LLC (0.11)
FLASHER EQUIPMENT COMPANY (0.36)
C & C ALCOSER TRUCKING (1.04)
Contract #08163211
Totals5286690.36399081.134618441.1987.5

CountyBEXAR
HighwayCS
FromON INGRAM RD
ToAT RICHLAND HILLS
CSJ0915-12-570
Proj IDSTP 1702(042)HES
Work TypeINSTALL TRAFFIC SIGNAL
 
0.200188897.500.000.0
CountyBEXAR
HighwayFM 1976
FromAT MIDCROWN
To.
CSJ1890-01-048
Proj IDSTP 1702(043)HES
Work TypeTRAFFIC SIGNALS & ILLUMINATION
 
0.200217051.50149411.0068.8
Work Order06-14-17
Work Began00-00-00
Work Completed
Time Computed07-14-17
Contract Working Days100
Addl Days Granted0
Working Days Charged57
Percent Time Used57
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-570
HEARN CO. (10.41)
Contract #05173209
Totals405949.0059300.00149411.0036.8

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS ON IH 10, IH 35,
ToIH 37, IH 410, US 90 AND US 281
CSJ0915-12-577
Proj IDSTP 2018(598)MM
Work TypeSIGNING
 
0.0012897980.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days296
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-577
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183037
Totals2897980.500.000.000.0

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BEXAR COUNTY
To.
CSJ0915-12-591
Proj IDNH 1702(678)
Work TypeLANDSCAPE DEVELOPMENT
 
0.001510193.0059500.0011.6
Work Order09-14-17
Work Began01-02-18
Work Completed
Time Computed10-14-17
Contract Working Days95
Addl Days Granted0
Working Days Charged43
Percent Time Used45
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-591
FLASHER EQUIPMENT COMPANY (2.92)
Contract #08173010
Totals510193.0023000.0059500.0011.6

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BEXAR COUNTY
To.
CSJ0915-12-592
Proj IDNH 1702(679)
Work TypeLANDSCAPE DEVELOPMENT
 
0.001682419.00243750.0035.7
Work Order09-14-17
Work Began01-08-18
Work Completed
Time Computed10-14-17
Contract Working Days82
Addl Days Granted0
Working Days Charged36
Percent Time Used43
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-12-592
FLASHER EQUIPMENT COMPANY (3.12)
Contract #08173230
Totals682419.00103000.00243750.0035.7

CountyWILSON
HighwayCR
FromCR 348 AT DRY HOLLOW CREEK
To.
CSJ0915-14-031
Proj IDBR 1702(781)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.067315294.890.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-14-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days86
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-14-031
M & D FOUNDATION DRILLING INDUSTRIES, INC. (11.89)
ENVIRONMENTAL SAFETY SERVICES, INC. (8.31)
FLASHER LIMITED (2.80)
Contract #01183231
Totals315294.890.000.000.0

CountyMEDINA
HighwayCR
From4.1 MI SW OF FM 471
To.
CSJ0915-45-052
Proj IDBR 1502(643)
Work TypeREPLACE BRIDGE & APPROACHES
 
0.001422407.38325095.4180.1
Work Order08-23-17
Work Began11-08-17
Work Completed
Time Computed09-22-17
Contract Working Days64
Addl Days Granted0
Working Days Charged87
Percent Time Used135
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-45-052
BEAIRD DRILLING (6.07)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (0.70)
AZA BARRICADES (0.66)
ROADWAY SPECIALTIES, INC. (6.86)
Contract #07173238
Totals422407.3838500.61325095.4180.1

CountyKENDALL
HighwayRM 474
FromFM 473
ToKEMMER TRAIL
CSJ1042-01-032
Proj IDSTP 2013(720)
Work TypeGRAD, BSE, SURF, PAVMT MARKINGS
 
6.6734456842.621480167.0633.2
Work Order07-20-17
Work Began00-00-00
Work Completed
Time Computed08-19-17
Contract Working Days261
Addl Days Granted0
Working Days Charged130
Percent Time Used49
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1042-01-032
RELMCO, INC. (23.70)
GEOSOURCE, INC. (3.41)
D.I.J. CONSTRUCTION, INC (2.59)
FLASHER EQUIPMENT COMPANY (1.89)
LONE STAR EROSION CONTROL (1.58)
Contract #06173027
Totals4456842.62284293.651480167.0633.2

CountyMEDINA
HighwayPR 37
FromSH 16
ToBANDERA C/L
CSJ1066-02-017
Proj IDSTP 2018(078)HESG
Work TypeGRAD, SURF, BASE, PAVEMENT MARKINGS
 
4.2861099115.25177898.2016.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-16-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days153
Addl Days Granted0
Working Days Charged53
Percent Time Used34
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1066-02-017
ENVIRONMENTAL SAFETY SERVICES, INC. (18.67)
FLASHER EQUIPMENT COMPANY (6.51)
GEOSOURCE, INC. (6.46)
ROADWAY SPECIALTIES, INC. (5.55)
THE LEVY COMPANY, INC. (4.73)
Contract #09173010
Totals1099115.2568653.95177898.2016.1

CountyBEXAR
HighwayFM 1516
FromFM 78
ToFM 1976
CSJ1477-01-040
Proj IDSTP 2017(798)MM
Work TypeGRD, BSE, STR, SURF, PAV'T MRK
 
0.7625733862.95693951.6012.1
CountyBEXAR
HighwayFM 1516
FromFM 78
ToFM 1976
CSJ1477-01-041
Proj IDSTP 1502(217)
Work TypeACQUISITION, RELOCATION ASSISTANCE
 
0.7621655042.651281006.8177.4
Work Order06-26-17
Work Began00-00-00
Work Completed
Time Computed07-28-17
Contract Working Days586
Addl Days Granted0
Working Days Charged87
Percent Time Used14
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1477-01-040
DU-MOR ENTERPRISES_INC. (0.39)
FUQUAY, INC. (0.58)
AUSTIN WOOD RECYCLING (0.17)
LONE STAR PAVING (13.50)
E-Z BEL CONSTRUCTION, LLC (5.71)
FLASHER EQUIPMENT COMPANY (1.44)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.15)
ROADWAY SPECIALTIES, INC. (0.71)
Contract #03173203
Totals7388905.60189757.881974958.4126.7

CountyCOMAL
HighwayFM 306
FromRIVER CHASE WAY
ToHOFFMANN LANE
CSJ1728-02-059
Proj IDSTP 1602(300)MM
Work TypeGRAD, STR, BASE, SURF
 
1.3275996508.485394824.6989.9
Work Order09-06-16
Work Began10-06-16
Work Completed
Time Computed10-06-16
Contract Working Days364
Addl Days Granted0
Working Days Charged300
Percent Time Used82
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1728-02-059
OSCAR ORDUNO, INC. (10.30)
SOUTH TEXAS PAINTING COMPANY (0.32)
F & W ELECTRICAL CONTRACTORS, INC. (3.51)
FLASHER EQUIPMENT COMPANY (1.00)
ENVIRONMENTAL SAFETY SERVICES, INC. (7.37)
EGGEMEYER LAND CLEARING, LLC (0.55)
TEXAS LANDSCAPE & IRRIGATION (1.03)
FUQUAY, INC. (1.39)
GK CONSTRUCTION, LLC (0.19)
CENTURY ASPHALT MATERIALS (0.39)
HEARN CO. (0.38)
CUATRO T CONSTRUCTION, INC. (0.00)
CLAUDIA SERNA DBA SERNA"S TRUCKING (0.00)
Contract #07163211
Totals5996508.48433931.295394824.6989.9

CountyMCMULLEN
HighwayFM 791
From2.19 MILES EAST OF SH 16
To2.76 MILES EAST OF SH 16
CSJ1739-04-010
Proj IDCC 1739-4-10
Work TypeGRAD, BASE, STRUCTURE & SURF
 
0.5684956163.243407190.1068.7
Work Order08-16-17
Work Began10-03-17
Work Completed
Time Computed09-15-17
Contract Working Days176
Addl Days Granted2
Working Days Charged119
Percent Time Used66
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1739-04-010
EGGEMEYER LAND CLEARING, LLC (0.40)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.41)
PRIMATE CONSTRUCTION, INC. (0.13)
ROADWAY SPECIALTIES, INC. (2.17)
TADPOLE FENCE COMPANY, LLC (0.51)
AWP, INC. DBA AREA WIDE PROTECTIVE (0.37)
D.I.J. CONSTRUCTION, INC (1.09)
MCL CONTRACTING, LLC (0.30)
Contract #07173045
Totals4956163.24228857.893407190.1068.7

page 1 | page 2 | page 3 | page 4 | page 5 | page 6