Monthly State Let Construction Report For Pharr District As Of Apr 12, 2024 Page 3 Of 4

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHIDALGO
HighwayCS
From0.1 MILES WEST OF MINNESOTA RD.
To0.1 MILES EAST OF MINNESOTA RD.
CSJ0921-02-508
Proj IDSTP 2B23(057)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
126942.3145872.8336.1
CountyHIDALGO
HighwayCR
From0.1 MILES WEST OF WESTERN RD.
To0.1 MILES EAST OF WESTERN RD.
CSJ0921-02-509
Proj IDSTP 2B23(058)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
65230.2623717.7536.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-06-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days57
Addl Days Granted0
Working Days Charged15
Percent Time Used26
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-508
TEXAS HIGHWAY SYSTEMS, INC. (5.51)
FOREMOST PAVING, INC. (21.59)
PAVEMENT MARKINGS INC. (3.08)
Contract #08233266
Totals192172.5753494.1569590.5836.2

CountyCAMERON
HighwayCS
FromS. PARALLEL CORRIDOR, FM 509 (PASO REAL)
ToFM 2520 (SAM HOUSTON RD)
CSJ0921-06-252
Proj IDCBI 2022(173)
Work TypeNEW LOCATION NON-FREEWAY
 
3.0609511089.368883496.3493.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-10-22
Work Began02-09-22
Work Completed
Time Computed00-00-00
Contract Working Days376
Addl Days Granted0
Working Days Charged356
Percent Time Used94
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-06-252
GP7 CONSTRUCTION INC. (10.80)
SOIL TECH ADVANCE INC. (5.45)
HIGHWAY BARRICADES AND SERVICES, LLC (0.47)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.78)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.07)
Contract #12213011
Totals9511089.360.008883496.3493.4

CountyCAMERON
HighwayVA
FromWITHIN LAS PALOMAS WMA
ToARROYO COLORADO UNIT
CSJ0921-06-267
Proj IDC 921-6-267
Work TypeTRANSPORTATION NON-ROADWAY
 
0.100170130.000.000.0
CountyCAMERON
HighwayVA
FromWITHIN BROWNSVILLE FIELD STATION
To.
CSJ0921-06-268
Proj IDC 921-6-268
Work TypeTRANSPORTATION NON-ROADWAY
 
0.10092230.000.000.0
CountyCAMERON
HighwayVA
FromWITHIN WORLD BIRDING CENTER
ToRESACA DE LAS PALMAS STATE PARK
CSJ0921-06-269
Proj IDC 921-6-269
Work TypeTRANSPORTATION NON-ROADWAY
 
0.100435557.250.000.0
CountyZAPATA
HighwayVA
FromWITHIN FALCON STATE PARK
To.
CSJ0921-28-008
Proj IDC 921-28-8
Work TypeTRANSPORTATION NON-ROADWAY
 
0.100731793.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-13-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days56
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CK NEWBERRY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0921-06-267
SOIL TECH ADVANCE INC. (0.67)
PAVEMENT MARKINGS INC. (3.48)
HIGHWAY BARRICADES AND SERVICES, LLC (0.73)
Contract #11233025
Totals1429710.500.000.000.0

CountyCAMERON
HighwayCS
FromON OWENS RD., 0.10 MI S OF SH 4
ToSTR#CO14-10-001 @RESACA DELA GUERRA
CSJ0921-06-306
Proj IDBR 2023(387)
Work TypeBRIDGE REPLACEMENT
 
864313.48165315.3019.1
CountyWILLACY
HighwayCR
FromCR 180, 0.6 MI SOUTH OF FM 1761
ToSTR# AA01-52-004 @ OLD WEST MAIN
CSJ0921-27-038
Proj IDBR 2020(316)
Work TypeBRIDGE REPLACEMENT
 
888780.70758899.4085.3
Work Order02-27-23
Work Began03-27-23
Work Completed
Time Computed03-27-23
Contract Working Days234
Addl Days Granted0
Working Days Charged162
Percent Time Used69
Contractor(s)
LUCANIA CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0921-06-306
PAVEMENT MARKINGS INC. (0.58)
GREGORY PILE DRIVING, INC. (7.78)
TEXAS HIGHWAY SYSTEMS, INC. (1.29)
PATMO SERVICES, L.L.C. (3.70)
ASAGO, LLC (1.01)
Contract #01233017
Totals1753094.180.00924214.7052.7

CountyCAMERON
HighwayCS
FromSTUART PL RD, .18MI N OF PRIMERA RD
ToFM 2994/WILSON RD.
CSJ0921-06-311
Proj IDSTP 2020(601)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
939378.65869083.2392.5
Work Order06-16-22
Work Began09-15-22
Work Completed
Time Computed07-18-22
Contract Working Days215
Addl Days Granted0
Working Days Charged197
Percent Time Used91
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-06-311
SOIL TECH ADVANCE INC. (3.15)
GP7 CONSTRUCTION INC. (15.12)
HIGHWAY BARRICADES AND SERVICES, LLC (0.87)
TEXAS HIGHWAY SYSTEMS, INC. (1.49)
Contract #05223028
Totals939378.65500.00869083.2392.5

CountyCAMERON
HighwayCS
FromGARRETT RD.
ToFM 1479
CSJ0921-06-356
Proj IDSTP 2B23(056)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
368889.30331181.3089.7
Work Order09-07-23
Work Began12-01-23
Work Completed
Time Computed12-01-23
Contract Working Days57
Addl Days Granted0
Working Days Charged26
Percent Time Used45
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-06-356
TEXAS CORDIA CONSTRUCTION, LLC (4.29)
G & E ESCOBEDO CONSTRUCTION, INC. (0.74)
Contract #08233264
Totals368889.303400.00331181.3089.7

CountyCAMERON
HighwayCS
FromWITHIN WORLD BIRDING CENTER &
ToRESACA DE LAS PALMAS STATE PARK
CSJ0921-06-363
Proj IDC 921-6-363
Work TypeTEXAS PARK AND WILDLIFE
 
64546.0056143.4786.9
Work Order10-23-23
Work Began11-20-23
Work Completed
Time Computed11-23-23
Contract Working Days7
Addl Days Granted0
Working Days Charged6
Percent Time Used85
Contractor(s)
LUCANIA CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0921-06-363
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09233033
Totals64546.000.0056143.4786.9

CountyCAMERON
HighwayFM 510
FromFM 3462
ToFM 1847
CSJ1057-03-045
Proj IDSTP 2B23(055)
Work TypeREHABILITATION OF EXISTING ROAD
 
7.60715675730.801609947.8110.2
Work Order09-06-23
Work Began00-00-00
Work Completed
Time Computed01-15-24
Contract Working Days347
Addl Days Granted15
Working Days Charged35
Percent Time Used9
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1057-03-045
HIGHWAY BARRICADES AND SERVICES, LLC (2.52)
LAREDO STRIPING, INC. (2.07)
TEXAS HIGHWAY SYSTEMS, INC. (0.48)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.00)
SOIL-TECH, INC. (0.00)
SOIL TECH ADVANCE INC. (2.52)
Contract #08233210
Totals15675730.80700531.691609947.8110.2

CountyHIDALGO
HighwayFM 676
FromSH 364, EAST
ToSH 107
CSJ1064-01-032
Proj IDC 1064-1-32
Work TypeWIDEN NON-FREEWAY
 
2.56615880158.306304083.3339.6
Work Order03-08-23
Work Began06-19-23
Work Completed
Time Computed03-08-23
Contract Working Days468
Addl Days Granted0
Working Days Charged192
Percent Time Used41
Contractor(s)
TEXAS CORDIA CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1064-01-032
HIGHWAY BARRICADES AND SERVICES, LLC (1.02)
GULF COAST CONTRACTORS, INC. (1.58)
DUSTROL, INC. (0.82)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (6.70)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.08)
MUNOZ FOUNDATION DRILLING, INC. (0.00)
Contract #02233011
Totals15880158.301101448.366304083.3339.6

CountyHIDALGO
HighwayFM 676
FromTAYLOR RD.
ToFM 2220
CSJ1064-01-043
Proj IDSTP 2024(158)MM
Work TypeWIDEN NON-FREEWAY
 
10832564.500.000.0
CountyHIDALGO
HighwayFM 676
From@ EDINBURG MAIN CANAL STR#: K00011001
To.
CSJ1064-01-046
Proj IDBR 2024(076)
Work TypeBRIDGE REPLACEMENT
 
0.100979047.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days472
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS CORDIA CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1064-01-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243205
Totals11811611.500.000.000.0

CountyCAMERON
HighwayFM 1846
FromSAN JOSE RANCH ROAD
ToBUS 77
CSJ1065-02-039
Proj IDF 2022(108)
Work TypeREHABILITATION OF EXISTING ROAD
 
3889216.023982560.1799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-16-21
Work Began02-18-22
Work Completed
Time Computed00-00-00
Contract Working Days206
Addl Days Granted25
Working Days Charged235
Percent Time Used101
Contractor(s)
TEXAS CORDIA CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1065-02-039
HIGHWAY BARRICADES AND SERVICES, LLC (2.42)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (3.83)
SOIL TECH ADVANCE INC. (0.72)
DUSTROL, INC. (1.70)
GUERRA CONSTRUCTION COMPANY (0.61)
Contract #11213211
Totals3889216.020.003982560.1799.9

CountyCAMERON
HighwayFM 802
FromFM 1847
ToOLD PORT ISABEL RD.
CSJ1140-02-038
Proj IDNH 2B20(157)
Work TypeWIDEN NON-FREEWAY
 
6262978.187033395.1199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-20
Work Began01-04-21
Work Completed
Time Computed00-00-00
Contract Working Days230
Addl Days Granted76
Working Days Charged334
Percent Time Used109
Contractor(s)
TEXAS CORDIA CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1140-02-038
HIGHWAY BARRICADES AND SERVICES, LLC (1.58)
GREGORY PILE DRIVING, INC. (0.89)
DUSTROL, INC. (0.70)
TRAF-TEX, INC. (4.77)
EXTERIOR DESIGNS (1.30)
PURLITO, INC. (0.35)
G & E ESCOBEDO CONSTRUCTION, INC. (0.00)
MUNOZ FOUNDATION DRILLING, INC. (0.25)
HOUSTON SAWING & DRILLING (0.05)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.82)
Contract #08203218
Totals6262978.180.007033395.1199.9

CountyHIDALGO
HighwayFM 1015
FromMILE 9
ToIH-2
CSJ1228-03-050
Proj IDC 1228-3-50
Work TypeREHABILITATION OF EXISTING ROAD
 
8435308.85915343.3010.8
Work Order10-23-23
Work Began01-08-24
Work Completed
Time Computed12-01-23
Contract Working Days294
Addl Days Granted0
Working Days Charged46
Percent Time Used15
Contractor(s)
REIM CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1228-03-050
HIGHWAY BARRICADES AND SERVICES, LLC (2.62)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (4.99)
TEXAS ICON CONSTRUCTION, LLC (0.15)
Contract #09233005
Totals8435308.8563501.49915343.3010.8

CountyHIDALGO
HighwayFM 1015
FromIH-2
To2.584 MILES SOUTH OF IH-2
CSJ1228-03-051
Proj IDC 1228-3-51
Work TypeREHABILITATION OF EXISTING ROAD
 
11217266.061489651.6013.2
Work Order11-01-23
Work Began01-10-24
Work Completed
Time Computed12-01-23
Contract Working Days410
Addl Days Granted0
Working Days Charged53
Percent Time Used12
Contractor(s)
TEXAS CORDIA CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1228-03-051
SOIL TECH ADVANCE INC. (0.15)
HIGHWAY BARRICADES AND SERVICES, LLC (2.28)
EXTERIOR DESIGNS (0.46)
TOP NOTCH CONSTRUCTION (0.56)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (4.47)
DUSTROL, INC. (2.96)
Contract #09233211
Totals11217266.06399682.401489651.6013.2

CountyWILLACY
HighwayFM 1018
FromIH-69E NB FRONTAGE RD.
ToFM 1420
CSJ1236-01-015
Proj IDF 2021(843)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
12.37512441758.7011893268.9895.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-16-21
Work Began11-08-21
Work Completed
Time Computed00-00-00
Contract Working Days379
Addl Days Granted55
Working Days Charged434
Percent Time Used100
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1236-01-015
GP7 CONSTRUCTION INC. (6.65)
HIGHWAY BARRICADES AND SERVICES, LLC (3.08)
SOIL TECH ADVANCE INC. (4.30)
Contract #08213009
Totals12441758.700.0011893268.9895.5

CountyHIDALGO
HighwayFM 1425
FromMILE 12 N. RD.
ToIH-2
CSJ1428-01-027
Proj IDF 2B23(005)
Work TypeREHABILITATION OF EXISTING ROAD
 
7.5008656176.691022577.7811.8
CountyHIDALGO
HighwayFM 1425
FromIH-2
ToBUS 83
CSJ1428-01-028
Proj IDF 2B23(005)
Work TypeREHABILITATION OF EXISTING ROAD
 
683724.680.000.0
CountyHIDALGO
HighwayFM 1425
FromSH 107
ToMILE 12 N. RD.
CSJ1428-01-033
Proj IDSTP 2B23(002)VRU
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3917294.762579395.7865.8
Work Order08-07-23
Work Began09-12-23
Work Completed
Time Computed09-11-23
Contract Working Days487
Addl Days Granted14
Working Days Charged120
Percent Time Used23
Contractor(s)
ASAGO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1428-01-027
TEXAS ICON CONSTRUCTION, LLC (2.44)
HIGHWAY BARRICADES AND SERVICES, LLC (3.33)
Contract #06233413
Totals13257196.13460188.243601973.5627.1

CountyWILLACY
HighwayFM 490
From0.74 MI E OF FM 1015
To@ WILLACY CO. MAIN CANAL
CSJ1430-01-025
Proj IDBR 2B23(009)
Work TypeBRIDGE REPLACEMENT
 
929232.95769185.0082.7
CountyWILLACY
HighwayFM 490
From0.70 MI E OF FM 1015
To@ DELTA LAKE DRAIN
CSJ1430-01-026
Proj IDBR 2B23(009)
Work TypeBRIDGE REPLACEMENT
 
1044061.45820429.5078.5
CountyWILLACY
HighwayFM 490
FromFM 1015
ToFM 1425
CSJ1430-01-031
Proj IDSTP 2B23(003)VRU
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.2233970779.901317832.4233.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-26-23
Work Began10-31-23
Work Completed
Time Computed00-00-00
Contract Working Days136
Addl Days Granted0
Working Days Charged94
Percent Time Used69
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1430-01-025
TEXAS ICON CONSTRUCTION, LLC (0.86)
TEXAS HIGHWAY SYSTEMS, INC. (0.59)
SOIL TECH ADVANCE INC. (4.64)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.01)
HIGHWAY BARRICADES AND SERVICES, LLC (1.31)
DEPENDABLE FENCE (3.33)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.22)
HOUSTON SAWING & DRILLING (0.10)
Contract #06233611
Totals5944074.30649927.522907446.9248.9

CountyCAMERON
HighwaySH 4
FromIH-69E
ToSH 48
CSJ1504-01-037
Proj IDF 2B23(010)
Work TypeREHABILITATION OF EXISTING ROAD
 
1.57320955780.742942330.5614.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-07-23
Work Began01-08-24
Work Completed
Time Computed00-00-00
Contract Working Days445
Addl Days Granted4
Working Days Charged49
Percent Time Used10
Contractor(s)
POSILLICO CIVIL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1504-01-037
DUSTROL, INC. (1.82)
HIGHWAY BARRICADES AND SERVICES, LLC (1.88)
TRAF-TEX, INC. (3.03)
CERTIFIED PLACERS LLC (1.54)
AMERICAN FENCE (0.04)
Contract #06233410
Totals20955780.74268998.662942330.5614.0

CountyHIDALGO ETC
HighwayFM 907 ETC
From0.1 MILES NORTH OF MILE 17 1/2 N. RD.
To0.1 MILES SOUTH OF MILE 17 1/2 N RD.
CSJ1586-01-089
Proj IDF 2022(934)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1313573.101232125.6796.4
Work Order09-20-22
Work Began03-13-23
Work Completed
Time Computed03-13-23
Contract Working Days140
Addl Days Granted0
Working Days Charged190
Percent Time Used135
Contractor(s)
D&G ENERGY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1586-01-089
VALLEY STRIPING CORP. (10.70)
R&T CONSTRUCTION (0.80)
Contract #08223031
Totals1313573.1017297.501232125.6796.4

CountyHIDALGO
HighwayFM 1925
FromFM 907 (ALAMO RD)
ToSHARP RD.
CSJ1803-02-035
Proj IDF 2024(623)
Work TypeWIDEN NON-FREEWAY
 
1.6218283398.470.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-05-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days334
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ASAGO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1803-02-035
HIGHWAY BARRICADES AND SERVICES, LLC (1.79)
D&G ENERGY CORPORATION (2.80)
IZAGUIRRE CONSTRUCTION LLC (3.49)
TEXAS ICON CONSTRUCTION, LLC (0.46)
Contract #01243209
Totals8283398.470.000.000.0