Monthly State Let Construction Report For Pharr District As Of Apr 10, 2018 Page 2 Of 3

Last Update: Friday, April 20, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCAMERON
HighwaySH 48 ETC
FromMCLELLAND ST.
ToMEDICAL ST.
CSJ0220-05-070
Proj IDSTP 2018(636)MM
Work TypeINSTALL TRAFFIC SIGNAL
 
1.6001198847.310.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days331
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0220-05-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183005
Totals1198847.310.000.000.0

CountyBROOKS
HighwayUS 281
From0.747 MI SOUTH OF FM 755
ToBROOKS/HIDALGO C.L.
CSJ0255-05-040
Proj IDNH 2018(316)
Work TypeOVERLAY
 
7.1441846295.380.000.0
CountyBROOKS
HighwayUS 281
From3.14 MI N OF FM 755
To0.740 MI N OF FM 755
CSJ0255-05-042
Proj IDNH 2018(316)
Work TypeOVERLAY
 
2.396665574.840.000.0
Work Order12-19-17
Work Began00-00-00
Work Completed
Time Computed01-19-18
Contract Working Days69
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0255-05-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11173218
Totals2511870.220.000.000.0

CountyHIDALGO ETC
HighwayIH 69C ETC
FromSH 107
To3.052 MI N OF SH 107
CSJ0255-07-141
Proj IDNH 1702(836)
Work TypeSEAL COAT_(NB & SB FRONTAGE ROADS)
 
23.4101572940.5210165.000.6
Work Order11-10-17
Work Began00-00-00
Work Completed
Time Computed12-10-17
Contract Working Days79
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0255-07-141
CHEROKEE SERVICES (3.80)
PAVEMENT MARKINGS INC. (26.26)
INTERSTATE BARRICADES & MARKINGS, INC. (1.62)
Contract #10173228
Totals1572940.520.0010165.000.6

CountyWILLACY
HighwayUS 77
From0.93 MI S OF WILLACY/KENEDY CL
ToBUSINESS 77
CSJ0327-10-057
Proj IDNH 1702(492)
Work TypeCONSTRUCT MAINLANES & OVERPASS
 
3.97722671108.133035295.7213.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-20-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days480
Addl Days Granted0
Working Days Charged53
Percent Time Used11
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0327-10-057
SOIL-TECH, INC (4.94)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.55)
AARON CONCRETE CONTRACTORS, L.P. (1.26)
WEST TEXAS RUMBLE STRIP (0.03)
PAVEMENT MARKINGS INC. (0.60)
LAREDO STRIPING INC. (3.89)
Contract #08173005
Totals22671108.13986173.023035295.7213.3

CountyCAMERON
HighwaySH 100
From4.0 EAST OF FM 1847
To6.27 MI EAST OF FM 1847
CSJ0331-01-044
Proj IDNH 1502(584)
Work TypeINSTALL WILDLIFE CROSSINGS
 
2.2532561306.502783457.0199.9
CountyCAMERON
HighwaySH 100
From6.27 MI EAST OF FM 1847
To1.75 MILES WEST OF FM 510
CSJ0331-02-052
Proj IDNH 1502(584)
Work TypeINSTALL WILDLIFE CROSSINGS
 
4.8183778680.753675472.9897.2
Work Order05-18-16
Work Began09-06-16
Work Completed
Time Computed05-31-16
Contract Working Days340
Addl Days Granted0
Working Days Charged338
Percent Time Used99
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0331-01-044
GP7 CONSTRUCTION, INC. (3.57)
SOIL-TECH, INC. (4.39)
TEXAS HIGHWAY SYSTEMS, INC. (0.01)
VALLEY STRIPING CORP. (1.13)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.07)
PENHALL COMPANY (AUSTIN) (0.17)
Contract #03163031
Totals6339987.2584365.206458929.9999.9

CountyCAMERON
HighwayPR 100
FromCITY OF SPI CONVENTION CENTER SOUTH
ToQUEEN ISABELA CAUSEWAY
CSJ0331-04-067
Proj IDSTP 2017(193)TAPS
Work TypeCONST. SIDEWALKS,RAMPS,CURBS
 
3.9303351562.061666100.6549.7
CountyCAMERON
HighwayCS
FromQUEEN ISABELA CAUSEWAY SOUTH_.67 MI
ToISLA BLANCA PARK ENTRANCE
CSJ0921-06-299
Proj IDSTP 2017(193)TAPS
Work TypeCONST. SIDEWALKS,RAMPS,CURBS
 
0.670100947.1337773.7037.4
Work Order03-16-17
Work Began05-02-17
Work Completed
Time Computed04-16-17
Contract Working Days316
Addl Days Granted0
Working Days Charged239
Percent Time Used75
Contractor(s)
REIM CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0331-04-067
SOIL-TECH, INC. (14.00)
GP7 CONSTRUCTION, INC. (23.08)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (7.12)
G & E ESCOBEDO CONSTRUCTION, INC. (2.82)
MVP INSTALLATIONS, L.P. (2.39)
Contract #01173038
Totals3452509.1943604.171703874.3549.3

CountyCAMERON
HighwaySH 107
FromBUSINESS 77_(COMBES)
ToIH-69E
CSJ0342-04-032
Proj IDNH 2017(971)
Work TypeWIDEN TO 4 LANE UNDIVIDED C&G
 
0.4654313269.701228925.6928.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days285
Addl Days Granted0
Working Days Charged103
Percent Time Used36
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0342-04-032
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (4.65)
GP7 CONSTRUCTION, INC. (5.92)
GULF COAST CONTRACTORS, INC. (2.83)
PAVEMENT MARKINGS INC. (1.08)
VALLEY INFRASTRUCTURE, INC. (18.54)
Contract #04173209
Totals4313269.70253274.301228925.6928.4

CountyHIDALGO
HighwaySH 186
FromUS 281
ToHIDALGO/ WILLACY C.L.
CSJ0433-01-030
Proj IDSTP 1702(838)
Work TypeREHABILITATE ROADWAY_(SUPER 2)
 
9.50012133439.10231013.191.9
Work Order11-13-17
Work Began00-00-00
Work Completed
Time Computed12-13-17
Contract Working Days566
Addl Days Granted0
Working Days Charged32
Percent Time Used5
Contractor(s)
ASAGO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0433-01-030
GULF COAST CONTRACTORS, INC. (1.34)
HIGHWAY BARRICADES AND SERVICES, LLC (3.28)
Contract #10173018
Totals12133439.1021512.19231013.191.9

CountyCAMERON
HighwayFM 106
From@ RIO HONDO LIFT BRIDGE
To.
CSJ0630-02-041
Proj IDBR 1502(468)
Work TypeBRIDGE REHABILITATION
 
0.10012406043.3012196467.3698.3
Work Order10-30-15
Work Began00-00-00
Work Completed
Time Computed11-30-15
Contract Working Days651
Addl Days Granted0
Working Days Charged500
Percent Time Used76
Contractor(s)
PCL CIVIL CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0630-02-041
RHYNER CONSTRUCTION SERVICES, INC. (2.57)
TX TINMAN ENTERPRISES, LLC. (0.60)
HIGHWAY BARRICADES AND SERVICES, LLC (0.58)
FOREMOST PAVING, INC. (1.83)
S & S BRIDGE PAINTING, INC. (14.21)
FAITH TECHNOLOGIES, INC. (8.51)
RG PAINTING, INC. (0.64)
AIRS COMPANY, INC. (0.06)
AIRE TECHNICS, INC (0.07)
Contract #07153019
Totals12406043.30321393.3012196467.3698.3

CountyHIDALGO
HighwayFM 681
FromFM 681 (N) @ FM 2221
ToSH 107
CSJ0669-01-043
Proj IDSTP 2013(039)MM
Work TypeWIDEN TO 4 LANE DIVIDED URBAN
 
1.78412345193.529244039.0374.8
CountyHIDALGO
HighwayFM 2221
From0.25 MI W OF SH 364 (LA HOMA)
To.25 MI W OF MOOREFIELD RD
CSJ0862-01-037
Proj IDSTP 2013(040)MM
Work TypeWIDEN TO 4 LANE DIVIDED
 
0.5742333144.96345700.0414.8
CountyHIDALGO
HighwayFM 2221
From0.25 MI W OF MOOREFIELD RD
ToFM 681
CSJ0862-01-047
Proj IDSTP 2013(039)MM
Work TypeWIDEN TO 4 LANE DIVIDED URBAN
 
0.3382162777.75733499.8433.9
Work Order08-19-13
Work Began09-04-13
Work Completed
Time Computed09-04-13
Contract Working Days540
Addl Days Granted0
Working Days Charged148
Percent Time Used27
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0669-01-043
GO UNDERGROUND, LIMITED LIABILITY COMPANY (20.85)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.29)
SOIL-TECH, INC. (1.94)
PAVEMENT MARKINGS INC. (1.01)
VALLEY INFRASTRUCTURE, INC. (10.14)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.76)
Contract #06133203
Totals16841116.2314444.5210323238.9161.2

CountyHIDALGO
HighwayFM 681
From1.66 MILES NORTH OF FM 2058
To0.02 MILES SOUTH OF FM 1925
CSJ0669-01-049
Proj IDSTP 2017(317)
Work TypeREHABILITATE ROADWAY
 
8.2088889677.744133507.7346.4
Work Order01-17-17
Work Began06-05-17
Work Completed
Time Computed02-17-17
Contract Working Days576
Addl Days Granted0
Working Days Charged235
Percent Time Used40
Contractor(s)
ASAGO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0669-01-049
HIGHWAY BARRICADES AND SERVICES, LLC (3.46)
D&S TEXAS ICON CONSTRUCTION (0.81)
L & R PRECAST CONCRETE WORKS, INC. (1.21)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.69)
Contract #12163023
Totals8889677.74364914.424133507.7346.4

CountyCAMERON
HighwayFM 511
FromPORT OF BROWNSVILLE
ToSH 4
CSJ0684-01-069
Proj IDNH 2018(643)
Work TypeREHABILITATE PAVEMENT
 
1.0003399954.240.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0684-01-069
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183033
Totals3399954.240.000.000.0

CountyHIDALGO ETC
HighwayFM 88 ETC
FromWILLACY/ HIDALGO COUNTY LINE
ToFM 1422
CSJ0698-02-052
Proj IDSTP 2018(336)HES
Work TypePROFILE EDGELINE MARKINGS
 
42.540428221.04432864.4399.9
Work Order01-10-18
Work Began00-00-00
Work Completed
Time Computed03-05-18
Contract Working Days125
Addl Days Granted0
Working Days Charged29
Percent Time Used23
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 0698-02-052
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173027
Totals428221.04282589.73432864.4399.9

CountyHIDALGO
HighwayFM 493
FromCHAMPION ST.
ToUS 281
CSJ0863-01-047
Proj IDHP 2014(907)
Work TypeRECONSTRUCT & ADD SHOULDERS
 
5.68111333645.325787305.5851.0
CountyHIDALGO
HighwayFM 493
FromBUSINESS 83
ToCHAMPION AVE
CSJ0863-01-053
Proj IDHP 2014(907)
Work TypeOVERLAY
 
0.768579679.561080.720.1
CountyZERO COUNTIES
Highway
From
To
CSJ0863-01-057
Proj ID
Work Type
 
0.00257988.350.0
Work Order09-09-14
Work Began07-13-15
Work Completed
Time Computed09-25-14
Contract Working Days480
Addl Days Granted0
Working Days Charged358
Percent Time Used74
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0863-01-047
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.32)
PAVEMENT MARKINGS INC. (1.32)
LAREDO STRIPING INC. (1.35)
SOIL-TECH, INC. (4.05)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.03)
Contract #07143208
Totals11913324.88218812.656046374.6550.7

CountyHIDALGO
HighwayCS
FromON OWASSA RD, FROM JACKSON RD
ToI 69-C
CSJ0921-02-140
Proj IDSTP 2008(328)MM
Work TypeRECONSTRUCTION AND WIDENING
 
1.1004819279.374166166.8686.4
CountyHIDALGO
HighwayCS
FromON OWASSA RD, FROM JACKSON RD
ToI 69-C
CSJ0921-02-357
Proj IDSTP 2017(218)
Work TypeROW ACQUISITION
 
1.100386829.00396554.0099.9
Work Order02-22-17
Work Began05-17-17
Work Completed
Time Computed03-22-17
Contract Working Days440
Addl Days Granted0
Working Days Charged213
Percent Time Used48
Contractor(s)
IOC COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-140
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (5.99)
SOIL-TECH, INC. (0.26)
SALAZAR UTILITY CONSTRUCTION INC. (0.44)
VALLEY STRIPING CORP. (1.06)
Contract #01173031
Totals5206108.37266919.734562720.8687.6

CountyHIDALGO
HighwayVA
FromUS CUSTOMS PORT OF ENTRY EXIT
ToUS 281
CSJ0921-02-173
Proj IDBOR 2002(632)
Work TypeCONSTRUCT BSIF
 
1.35020116428.4517566408.9287.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-25-11
Work Began10-18-11
Work Completed
Time Computed09-10-11
Contract Working Days380
Addl Days Granted115
Working Days Charged495
Percent Time Used100
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-173
BULLARD CONSTRUCTION, INC. (19.38)
HIGHWAY TECHNOLOGIES, INC. (1.61)
HURRICANE FENCE COMPANY (0.96)
METTLER TOTLEDO (5.03)
NORTH TEXAS REBAR, LLC (0.54)
ROVAN, LLC (3.33)
SOIL-TECH, INC. (1.21)
STAR OPERATIONS, INC. (19.28)
TSI LABORATORIES SOUTH,INC. (0.04)
RGV ALLIANCE CONSTRUCTION, LLC (0.54)
FOREMOST PAVING, INC. (9.34)
CONTINENTAL REFRIGERATION (1.12)
M & A PAINTING SERVICE, INC. (0.39)
L & G CONCRETE CONSTRUCTION, INC. (3.86)
SOUTHERN STEEL FABRICATORS (4.27)
CANTU"S PLUMBING (0.88)
METRO ELECTRIC, INC. (1.81)
ROUND ROCK INDUSTRIAL EQUIPMENT COMPANY, INC. (0.07)
INTERTECH FLOORING (0.33)
WEIGHT AND TEST SOLUTIONS, INC. (0.70)
RGV ALLIANCE CONSTRUCTION, LLC (0.12)
MCALLEN PEST CONTROL (0.03)
THE CABINET SHOP (0.24)
PRIME CONSTRUCTION (0.10)
TAYLOR LIGHTNING PROTECTION (0.14)
TAMU, DBA CONSTRUCTION SPECIALTIES (0.37)
T & D SOLUTIONS, LTD (0.87)
Contract #07113207
Totals20116428.450.0017566408.9287.3

CountyHIDALGO
HighwayCR
FromON LOS EBANOS, 1.0 MI W OF FM 1016
ToSTR#AA08-72-001 @ MISSION BR PILOT
CSJ0921-02-212
Proj IDBR 2011(281)
Work TypeREPLACE BRIDGE & RECONST APPROACHES
 
0.076568428.97111619.0319.6
CountyBROOKS
HighwayCR
FromON CR 101, 1.4 MI N OF SH 285
ToSTR# AA01-30-002 @ CIBOLO CREEK
CSJ0921-22-004
Proj IDBR 2014(845)
Work TypeREPLACE BRIDGE & RECONST APPROACHES
 
0.070465334.060.000.0
Work Order09-20-17
Work Began00-00-00
Work Completed
Time Computed10-20-17
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
IOC COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-212
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173030
Totals1033763.0348160.83111619.0310.7

CountyHIDALGO
HighwayCR
FromSTR #AA06-53-001 @ S FLOODWAY CHANL
To.40 MI E OF FM 907
CSJ0921-02-252
Proj IDBR 2010(761)
Work TypeREPLACE BRIDGE & RECONST APPROACHES
 
0.080635348.47127859.0220.1
CountyBROOKS
HighwayCR
FromCR 113
ToOVER LOS OLMOS CREEK
CSJ0921-22-003
Proj IDBR 2012(630)
Work TypeREPLACE BRIDGE & RECONST APPROACHES
 
0.087332099.500.000.0
Work Order12-20-16
Work Began00-00-00
Work Completed
Time Computed01-20-17
Contract Working Days173
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
REIM CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-252
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07163220
Totals967447.970.00127859.0213.2

CountyHIDALGO
HighwayVA
FromVARIOUS LOCATIONS IN HIDALGO COUNTY
To.
CSJ0921-02-318
Proj IDSTP 2017(830)
Work TypeCONSTRUCT CURB RAMPS
 
0.1001608279.041458465.5190.6
Work Order04-24-17
Work Began06-06-17
Work Completed
Time Computed05-24-17
Contract Working Days335
Addl Days Granted0
Working Days Charged196
Percent Time Used58
Contractor(s)
SOUTH TEXAS ILLUMINATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-318
HIGHWAY BARRICADES AND SERVICES, LLC (8.60)
LAKEY, INC (28.27)
D&S TEXAS ICON CONSTRUCTION (5.51)
ARTILLERY, LLC (17.73)
Contract #03173222
Totals1608279.04139074.261458465.5190.6

CountyHIDALGO
HighwayVA
FromCOUNTYWIDE
ToVARIOUS LOCATIONS ON IH-2 & IH-69C
CSJ0921-02-347
Proj IDC 921-2-347
Work TypeREHAB CONTINOUOUS ILLUMINATION
 
0.1002161095.302180828.3999.9
CountyCAMERON
HighwayVA
FromCOUNTYWIDE
ToVARIOUS LOCATIONS ON IH-2 & IH-69E
CSJ0921-06-300
Proj IDC 921-6-300
Work TypeREHAB CONTINOUS ILLUMINATION
 
10.200569144.20345612.3760.7
CountyCAMERON
HighwayVA
FromCOUNTYWIDE
ToVARIOUS LOCATIONS ON IH-69E
CSJ0921-06-301
Proj IDC 921-6-301
Work TypeREHAB CONTINOUS ILLUMINATION
 
1.000444310.00443791.4799.8
Work Order09-15-16
Work Began01-23-17
Work Completed
Time Computed10-17-16
Contract Working Days371
Addl Days Granted0
Working Days Charged265
Percent Time Used71
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-347
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08163234
Totals3174549.5055602.942970232.2393.5

page 1 | page 2 | page 3