Monthly Local Let Maintenance Report For Laredo District As Of Mar 13, 2024 Page 4 Of 4
Last Update: Wednesday, March 13, 2024
|
|
Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | DUVAL |
Highway | SH0044 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6455-79-001 |
Proj ID | MMC - 645579001 |
Work Type | LIMESTONE ROCK ASPHALT |
|
| 0.010 | 282500.00 | | 148676.36 | 52.6 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 12-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 182 |
Addl Days Granted | 0 |
Working Days Charged | 91 |
Percent Time Used | 50 |
Contractor(s) |
VULCAN CONSTRUCTION MATERIALS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6455-79-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10232202 |
| Totals | 282500.00 | 79739.58 | 148676.36 | 52.6 |
|
County | ZAVALA |
Highway | US0057 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6455-81-001 |
Proj ID | MMC - 645581001 |
Work Type | LIMESTONE ROCK ASPHALT |
|
| 0.010 | 269390.00 | | 172656.72 | 64.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 11-16-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 182 |
Addl Days Granted | 0 |
Working Days Charged | 106 |
Percent Time Used | 58 |
Contractor(s) |
VULCAN CONSTRUCTION MATERIALS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6455-81-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10232203 |
| Totals | 269390.00 | 87455.57 | 172656.72 | 64.0 |
|
County | MAVERICK |
Highway | US0277 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6455-85-001 |
Proj ID | MMC - 645585001 |
Work Type | LIMESTONE ROCK ASPHALT |
|
| 0.010 | 264830.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 01-01-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 182 |
Addl Days Granted | 0 |
Working Days Charged | 60 |
Percent Time Used | 32 |
Contractor(s) |
MARTIN MARIETTA MATERIALS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6455-85-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10232204 |
| Totals | 264830.00 | 0.00 | 0.00 | 0.0 |
|
County | WEBB |
Highway | US0083 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6455-87-001 |
Proj ID | SUP - 645587001 |
Work Type | LANDSCAPE MAINTENANCE |
|
| 0.010 | 20393.76 | | 4248.70 | 20.8 |
Work Order | 10-01-23 |
Work Began | 10-01-23 |
Work Completed | |
Time Computed | 10-01-23 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 148 |
Percent Time Used | 20 |
Contractor(s) |
WORKQUEST WORLD TECHNICAL SERVICES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6455-87-001 WORLD TECHNICAL SERVICES, INC. (0.00)
|
Contract # | 09232207 |
| Totals | 20393.76 | 849.74 | 4248.70 | 20.8 |
|
County | WEBB |
Highway | IH0035 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6455-92-001 |
Proj ID | RMC - 645592001 |
Work Type | LANDSCAPE MAINTENANCE |
|
| 0.010 | 277860.00 | | 22890.00 | 8.2 |
Work Order | 12-01-23 |
Work Began | 12-01-23 |
Work Completed | |
Time Computed | 12-01-23 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 87 |
Percent Time Used | 23 |
Contractor(s) |
RK POWER DRIVE SERVICES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6455-92-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 09232206 |
| Totals | 277860.00 | 0.00 | 22890.00 | 8.2 |
|
County | WEBB |
Highway | IH0035 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6463-11-001 |
Proj ID | RMC - 646311001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 356335.20 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
R&M INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6463-11-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02242201 |
| Totals | 356335.20 | 0.00 | 0.00 | 0.0 |
|