Monthly State Let Construction Report For Lufkin District As Of Mar 13, 2024 Page 1 Of 3

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySHELBY ETC
HighwaySL 157 ETC
FromUS 59 NORTH
ToUS 96 SOUTH
CSJ0063-07-003
Proj IDF 2024(392)
Work TypeSEAL COAT
 
2.69012827779.2060000.000.4
Work Order12-21-23
Work Began00-00-00
Work Completed
Time Computed05-01-24
Contract Working Days106
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0063-07-003
INTERSTATE BARRICADES & MARKINGS, INC. (12.80)
Contract #11233024
Totals12827779.2060000.0060000.000.4

CountySHELBY ETC
HighwaySH 87 ETC
FromSH 7
ToSH 147
CSJ0064-01-069
Proj IDF 2023(196)
Work TypeSEAL COAT
 
42.13815659341.6910357076.6866.1
Work Order12-14-22
Work Began07-19-23
Work Completed
Time Computed05-01-23
Contract Working Days125
Addl Days Granted0
Working Days Charged102
Percent Time Used81
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0064-01-069
INTERSTATE BARRICADES & MARKINGS, INC. (11.56)
Contract #11223006
Totals15659341.69645459.9510357076.6866.1

CountyHOUSTON ETC
HighwayUS 287
FromBU 287V NORTH
ToBU 287V SOUTH
CSJ0109-03-041
Proj IDSTP 2024(815)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
388546.190.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days81
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0109-03-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243233
Totals388546.190.000.000.0

CountyHOUSTON
HighwayUS 287
FromANDERSON COUNTY LINE
To2.198 MI N OF FM 2663
CSJ0109-03-044
Proj IDC 109-3-44
Work TypeOVERLAY
 
11224367.450.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days140
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0109-03-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243006
Totals11224367.450.000.000.0

CountyHOUSTON
HighwaySH 21
FromSH 21 AT TRINITY RIVER
To.
CSJ0117-06-047
Proj IDBR 2022(446)
Work TypeBRIDGE REPLACEMENT
 
0.10027844040.2120261605.0272.7
Work Order05-10-22
Work Began08-08-22
Work Completed
Time Computed08-08-22
Contract Working Days418
Addl Days Granted3
Working Days Charged312
Percent Time Used74
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0117-06-047
DUSTIN ALLEN, INC. (0.13)
HERMANOS STEEL, LLC (0.97)
PINNACLE GRINDING AND GROOVING LLC (0.01)
PRIMATE CONSTRUCTION, LP (0.14)
STRIPE LINES, INC. (0.42)
CEN TEX HYDROSEED, INC. (0.70)
LINDAMOOD, INC. (3.52)
Contract #04223202
Totals27844040.21688865.2520261605.0272.7

CountyHOUSTON
HighwaySH 21
From2.56 MILES WEST OF FM 1733
ToCHEROKEE COUNTY LINE
CSJ0118-02-036
Proj IDF 2024(613)
Work TypeWIDEN NON-FREEWAY
 
14327451.660.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-02-24
Work Began00-00-00
Work Completed
Time Computed05-02-24
Contract Working Days314
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0118-02-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01243205
Totals14327451.660.000.000.0

CountyNACOGDOCHES
HighwaySH 21
FromSH 21 AT CARRIZO CREEK
To.
CSJ0118-08-075
Proj IDBR 2022(295)
Work TypeBRIDGE REPLACEMENT
 
0.3852490124.752260826.2192.4
Work Order02-16-22
Work Began03-10-22
Work Completed
Time Computed03-18-22
Contract Working Days230
Addl Days Granted3
Working Days Charged285
Percent Time Used122
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0118-08-075
AMERICAN REMEDIATION OPTIONS, INC. (4.43)
C&J CONTRACTORS LLC (37.99)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.91)
PANOLA SIGN & BARRICADE, INC. (0.54)
STRIPING TECHNOLOGY, L.P. (0.87)
HEMPHILL WBE PILE DRIVING CO. (0.40)
MESA ROD BUSTERS, INC. (0.27)
Contract #01223212
Totals2490124.7526135.552260826.2192.4

CountyNACOGDOCHES
HighwaySH 21
FromSH 21 AT ATASCOSO CREEK
ToSH 21 AT ATASCOSO CREEK
CSJ0118-08-076
Proj IDBR 2021(343)
Work TypeBRIDGE REPLACEMENT
 
0.0285478921.254356776.8780.1
Work Order06-17-21
Work Began09-17-21
Work Completed
Time Computed09-15-21
Contract Working Days321
Addl Days Granted0
Working Days Charged353
Percent Time Used109
Contractor(s)
ATLANTIC SPECIALTY INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0118-08-076
MORRIS COUNTY CONTRACTORS, L.L.C. (1.81)
PANOLA SIGN & BARRICADE, INC. (0.32)
PRIMATE CONSTRUCTION, LP (0.18)
RAYFORD"S TRUCK & TRACTOR (9.44)
(INACTIVE)STRIPE-A-ZONE, INC. (0.45)
PREMIER PAVING, LTD. (4.38)
TEXOP CONSTRUCTION (0.49)
PANOLA SIGN & BARRICADE, INC. (0.15)
SKYLINE BRIDGE LLC (54.03)
Contract #05213230
Totals5478921.2597791.324356776.8780.1

CountyNACOGDOCHES
HighwayBS 21-P ETC
FromFM 225
ToBU 59F
CSJ0118-08-090
Proj IDSTP 2023(289)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
329755.020.000.0
Work Order01-26-23
Work Began00-00-00
Work Completed
Time Computed02-25-23
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ECONOLITE SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0118-08-090
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12223029
Totals329755.020.000.000.0

CountyNACOGDOCHES
HighwayUS 59
From0.25 MILES SOUTH OF FM 95
ToUS 59/US 259 INTERCHANGE
CSJ0175-07-065
Proj IDF 2B23(190)
Work TypeOVERLAY
 
6975521.460.000.0
Work Order12-05-23
Work Began00-00-00
Work Completed
Time Computed01-04-24
Contract Working Days119
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0175-07-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09233011
Totals6975521.460.000.000.0

CountyNACOGDOCHES
HighwayUS 59
FromSH 7
To1.242 MI SOUTH OF SPRADLEY ST.
CSJ0176-01-081
Proj IDNH 1902(081)
Work TypeINC
 
3.05083149848.4365093071.0578.2
CountyNACOGDOCHES
HighwayUS 59
FromSH 7
To1.242 MI SOUTH OF SPRADLEY ST.
CSJ0176-01-110
Proj IDNH 2017(212)
Work TypeRIGHT OF WAY
 
3.0503048521.003044374.2499.8
Work Order08-13-19
Work Began08-20-19
Work Completed
Time Computed11-11-19
Contract Working Days523
Addl Days Granted46
Working Days Charged544
Percent Time Used95
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0176-01-081
AMERICAN REMEDIATION OPTIONS, INC. (1.50)
MCL CONTRACTING, LLC (4.68)
SOUTH TEXAS PAINTING COMPANY (0.13)
JOHN WRIGHT CONSTRUCTION (3.34)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (1.79)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.33)
TOTAL HIGHWAY MAINTENANCE, LLC (0.18)
BOWMAN ENGINEERING & CONSULTING, INC. (0.15)
STRIPING TECHNOLOGY, L.P. (0.33)
FARR FOUNDATION, INC. (0.30)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (0.21)
EXPRESS EMPLOYMENT PROFESSIONALS (0.00)
AARON CONCRETE CONTRACTORS, L.P. (0.80)
TORO BRAVO CONSTRUCTION, LLC (0.05)
J & KD, L.L.C. (0.07)
ANTIGO CONSTRUCTION, INC. (0.05)
SNOWHILL CONTRACTING LLC (0.36)
A&J REBAR LLC (3.43)
MATRIX CONCRETE ROAD & BRIDGE, LLC (0.67)
PRIMATE CONSTRUCTION, LP (0.00)
SOUTHEAST GRINDING AND GROOVING LLC (0.00)
Contract #07193002
Totals86198369.43647334.6768137445.2979.0

CountyANGELINA
HighwayUS 59
FromFM 2021
To0.34 MILE NORTH OF SL 287
CSJ0176-02-118
Proj IDF 2021(440)
Work TypeCONVERT NON-FREEWAY TO FREEWAY
 
2.45062405510.6926360385.4842.2
CountyANGELINA
HighwayUS 59
FromFM 2021
To0.34 MILE NORTH OF SL 287
CSJ0176-02-121
Proj IDROW 0176-02-121
Work TypeRIGHT OF WAY
 
2.450740165.70728902.9098.4
Work Order07-20-22
Work Began09-14-22
Work Completed
Time Computed10-18-22
Contract Working Days512
Addl Days Granted46
Working Days Charged235
Percent Time Used42
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-118
ANCORTEX, INC. (2.26)
BUYERS BARRICADES, INC. (0.13)
J. H. ODEN CONTRACTING COMPANY (0.95)
JOHN WRIGHT CONSTRUCTION (1.04)
MOORE BROTHERS CONSTRUCTION COMPANY (8.44)
S & S BRIDGE PAINTING, INC. (0.01)
STRIPING TECHNOLOGY, L.P. (0.64)
WEST TEXAS ROCK RESOURCES, LLC (0.02)
TRAF-TEX, INC. (0.71)
AMERICAN REMEDIATION OPTIONS, INC. (0.08)
ANTIGO CONSTRUCTION, INC. (0.04)
HERMANOS STEEL, LLC (5.49)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.62)
A&J REBAR LLC (0.12)
HODGES AND SON CONSTRUCTION COMPANY, INC. (2.00)
A&J REBAR LLC (0.08)
AT STAFFING (0.00)
Contract #06223201
Totals63145676.391657521.4127089288.3842.8

CountyANGELINA
HighwayUS 59
FromFM 2108
To1.15 MI SOUTH OF WHITE OAK CREEK
CSJ0176-03-097
Proj IDNH 2013(218)
Work TypeNEW LOCATION FREEWAY
 
8.200140098697.0094257104.4967.2
CountyANGELINA
HighwayUS 59
FromFM 2108
To1.15 MI SOUTH OF WHITE OAK CREEK
CSJ0176-03-116
Proj IDROW 176-3-116
Work TypeRIGHT OF WAY
 
8.200767232.00782872.5199.9
Work Order01-15-20
Work Began05-04-20
Work Completed
Time Computed04-14-20
Contract Working Days713
Addl Days Granted29
Working Days Charged592
Percent Time Used79
Contractor(s)
SACYR CONSTRUCTION USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-03-097
LONESTAR TRAFFIC SAFETY, LLC (0.04)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.57)
ADVANCE SITE PREP LLC (1.00)
FREDONIA CONSTRUCTION SERVICES (0.03)
TEXAS SCORPION HAULERS LLC, DBA TEXAS PRIDE HAULERS (0.05)
TERRY BLACK CONSTRUCTION COMPANY (0.40)
ANCORTEX, INC. (2.56)
A&J REBAR LLC (0.11)
LS HIGHWAY PRODUCTS, INC. (7.01)
A&J REBAR LLC (0.91)
PANTHER CREEK TRANSPORTATION, INC. (0.33)
CREACOM, INC. (1.63)
RME CONCRETE PUMPERS, INC (0.42)
JOHN DAVID HANOVER, LLC (0.07)
C&J CONTRACTORS LLC (1.37)
DREWERY CONSTRUCTION COMPANY, INCORPORATED (0.54)
ENGLISH DRILLING, INC. (0.01)
STRIPING TECHNOLOGY, L.P. (0.22)
STRAIGHT LINE SAWING & SEALING, INC. (0.28)
TEXOP CONSTRUCTION (0.47)
SOUTH TEXAS PAINTING CO. (0.23)
J. RUEDAS TRUCKING, LLC (0.08)
A.E.A. TRANSPORTATION (0.47)
TIGER CREEK ENTERPRISES, INC. (0.01)
SOUTHEAST GRINDING AND GROOVING LLC (0.08)
KC PROPERTY MANAGEMENT, LLC (0.52)
STRUCTURAL TECHNOLOGIES, LLC (0.06)
ALLEN LOGGINGS & SONS, INC. (0.55)
TEXAS SOLUTIONS TRUCKING, INC. (0.17)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.70)
H&A DISCOUNT CORING (0.08)
GILGAL STONES CONSULTING, LLC (0.12)
Contract #12193201
Totals140865929.002966550.5695039977.0067.4

CountyPOLK
HighwayUS 59
From3.4 MI N OF US 287
ToUS 287
CSJ0176-04-056
Proj IDNH 2013(222)
Work TypeNEW LOCATION FREEWAY
 
7.060172740741.4646530464.2326.9
CountyPOLK
HighwayUS 59
From3.4 MI N OF US 287
ToUS 287
CSJ0176-04-074
Proj IDNH 2001(590)
Work TypeRIGHT OF WAY
 
3.80058366.620.000.0
Work Order06-27-22
Work Began10-03-22
Work Completed
Time Computed09-25-22
Contract Working Days902
Addl Days Granted0
Working Days Charged267
Percent Time Used29
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-04-056
LONESTAR TRAFFIC SAFETY, LLC (0.06)
ANCORTEX, INC. (2.19)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (1.70)
EAGLE CONSTRUCTION LLC (7.16)
ISAACS CONSTRUCTION SERVICES LLC (0.25)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.37)
PRATER DIRT WORK LLC (0.35)
J & M CONTRACTING, COMPANY (2.10)
CHOCTAW ERECTORS, INC. (0.42)
BATTERSON, LLP (0.27)
MOORE BROTHERS CONSTRUCTION COMPANY (8.23)
WEST TEXAS ROCK RESOURCES, LLC (0.03)
CCC BLACKTOPPING LLC (0.46)
J.H. PAINTING COMPANY (0.16)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.62)
WILLOW CITY SIGN & RAIL, INC. (0.07)
PRIMATE CONSTRUCTION, LP (0.23)
B & N LOGGING, LLC (0.00)
RAY"S THREADING AND FAB SHOP (0.23)
LITTLE BEAUCHAMP TRUCKING (0.00)
A&J REBAR LLC (0.83)
GRAHAM RESOURCES, LLC (0.13)
Contract #05223201
Totals172799108.085592733.8346530464.2326.9

CountyPOLK
HighwayUS 59
From0.9 MILES N. PINEY CREEK
To0.3 MILES N. OLD HWY 35
CSJ0176-04-087
Proj IDF 2021(561)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
6239710.196180636.2899.7
Work Order07-20-21
Work Began10-12-21
Work Completed
Time Computed08-19-21
Contract Working Days174
Addl Days Granted18
Working Days Charged229
Percent Time Used119
Contractor(s)
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-04-087
J & M CONTRACTING, COMPANY (5.59)
CEN TEX HYDROSEED, INC. (0.81)
AREA WIDE PROTECTIVE, INC. (1.25)
PINNACLE GRINDING AND GROOVING LLC (0.08)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (3.86)
BATTERSON, LLP (1.10)
PROFESSIONAL TRAFFIC CONTROL LLC (0.08)
CPAVE, INC. (0.32)
HOLES INCORPORATED (0.38)
Contract #06213034
Totals6239710.1931640.736180636.2899.7

CountyPOLK
HighwayUS 59
From0.2 MILE NORTH FM 62
To1.5 M NORTH OF FM 942 E (NB LANES ONLY)
CSJ0176-05-199
Proj IDC 176-5-199
Work TypeOVERLAY
 
5599219.465871448.2199.9
Work Order02-16-23
Work Began07-10-23
Work Completed
Time Computed05-17-23
Contract Working Days69
Addl Days Granted0
Working Days Charged74
Percent Time Used107
Contractor(s)
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-05-199
SOUTHWEST ENVIRONMENT SERVICES LLC (0.21)
LONESTAR TRAFFIC SAFETY, LLC (0.25)
TRP CONSTRUCTION GROUP, LLC (2.80)
Contract #01233007
Totals5599219.463257.275871448.2199.9

CountyPOLK ETC
HighwayBU 59-J ETC
FromUS 59 NORTH
ToFM 1988
CSJ0176-06-016
Proj IDF 2023(076)
Work TypeOVERLAY
 
9240613.283348758.0036.2
Work Order05-17-23
Work Began08-30-23
Work Completed
Time Computed08-15-23
Contract Working Days121
Addl Days Granted0
Working Days Charged52
Percent Time Used42
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0176-06-016
PANOLA SIGN & BARRICADE, INC. (0.24)
DUSTROL, INC. (0.59)
STRIPING TECHNOLOGY, L.P. (7.35)
AT STAFFING (0.00)
Contract #01233207
Totals9240613.2872608.603348758.0036.2

CountySAN JACINTO
HighwayUS 59
FromFM 2914
ToLIBERTY C/L
CSJ0177-02-057
Proj IDF 2023(773)
Work TypeCONVERT NON-FREEWAY TO FREEWAY
 
3.580104794177.1411002139.9510.4
CountyLIBERTY
HighwayUS 59
FromSAN JACINTO C/L
To.65 MILE SOUTH OF SL 573
CSJ0177-03-099
Proj IDF 2023(992)
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
3.04085026476.895712262.966.7
Work Order09-08-23
Work Began12-14-23
Work Completed
Time Computed12-07-23
Contract Working Days1,309
Addl Days Granted0
Working Days Charged52
Percent Time Used3
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0177-02-057
ANTIGO CONSTRUCTION, INC. (0.11)
GMJ PAVING CO. (5.87)
MBN ENTERPRISES LLC (0.52)
MTAM CORPORATION (0.07)
PRIMATE CONSTRUCTION, LP (0.05)
PROFESSIONAL TRAFFIC CONTROL LLC (0.00)
SCOTT DERR PAINTING CO, LLC (0.03)
SK CONCRETE SERVICES LLC (0.20)
J. H. ODEN CONTRACTING COMPANY (0.14)
BELLA PAVING, INC. (0.34)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.91)
LONESTAR TRAFFIC SAFETY, LLC (0.07)
RDI FOUNDATION DRILLING (3.89)
WILLOW CITY SIGN & RAIL, INC. (0.35)
JAM MATERIALS, LLC (0.19)
MESA ROD BUSTERS, INC. (1.73)
VALLEY PLACERS, LLC (0.19)
J & D TEX SERV, INCORPORATED (1.89)
THOMAS TRACTOR WORKS, INC. (0.20)
Contract #06233402
Totals189820654.034588569.3416714402.918.8

CountyANGELINA
HighwayUS 69
FromFM 844
ToZAVALLA
CSJ0200-02-039
Proj IDNH 2018(811)
Work TypeGR STRS BASE & SURF
 
11.05271614966.8274290062.6599.9
Work Order06-14-18
Work Began07-24-18
Work Completed
Time Computed07-16-18
Contract Working Days571
Addl Days Granted255
Working Days Charged779
Percent Time Used94
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0200-02-039
AMERICAN REMEDIATION OPTIONS, INC. (0.70)
BOWMAN ENGINEERING & CONSULTING, INC. (0.28)
JB PINNACLE GROUP, LLC (1.26)
SOUTH TEXAS PAINTING COMPANY (0.07)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.77)
ANTIGO CONSTRUCTION, INC. (0.02)
ATS DRILLING, INC. (2.34)
STRIPING TECHNOLOGY, L.P. (0.71)
BUYERS BARRICADES HOUSTON, LLC. (0.01)
EAGLE CONSTRUCTION LLC (4.62)
PRIMATE CONSTRUCTION, INC. (0.06)
BOWMAN ENGINEERING & CONSULTING, INC. (0.08)
OVEMAN TRUCKING, LLC (0.39)
TEXOP CONSTRUCTION (0.21)
LINDAMOOD DEMOLITION, INC. (0.02)
DREWERY CONSTRUCTION COMPANY, INCORPORATED (2.00)
LONGVIEW BRIDGE AND ROAD, LTD. (0.00)
PINTO CONSTRUCTION CO., INC. (0.07)
NORTEX CONCRETE LIFT & STABILIZATION, INC. (0.01)
MOORE BROTHERS CONSTRUCTION COMPANY (0.02)
STRIPE-A-ZONE, LLC (0.03)
H. V. CAVER, INC. (3.67)
FLORES CONCRETE (0.84)
Contract #05183206
Totals71614966.820.0074290062.6599.9

CountyANGELINA
HighwayUS 69
FromFM 1270
ToJASPER COUNTY LINE
CSJ0200-03-021
Proj IDNH 2014(444)
Work TypeWIDEN NON-FREEWAY
 
7.00037447954.8837693097.9799.9
Work Order07-17-19
Work Began11-05-19
Work Completed
Time Computed10-15-19
Contract Working Days475
Addl Days Granted30
Working Days Charged527
Percent Time Used104
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0200-03-021
PANOLA SIGN & BARRICADE, INC. (0.15)
STRIPING TECHNOLOGY, L.P. (0.64)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.42)
JAMES BRADLEY HODGES DBA BRAD HODGES TRUCKING & LOGGING (0.00)
MOORE BROTHERS CONSTRUCTION COMPANY (9.07)
A R BROTHERS CONSTRUCTION SERVICES, INC. (7.92)
FREDONIA CONSTRUCTION SERVICES (0.28)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (0.60)
SOUTHWEST ENVIRONMENT SERIVES, LLC (1.93)
WEST TEXAS ROCK RESOURCES, LLC (0.03)
TEXOP CONSTRUCTION (0.49)
DREWERY BROS TREE SERVICE, INC. (0.01)
MILLER TRANSPORTATION (0.26)
ENGLISH DRILLING, INC. (0.00)
SNOWHILL CONTRACTING LLC (0.09)
RANSOM DRILLING SERVICES, LLC (0.07)
DREWERY & WHEATON, LLC (0.89)
TRUE ROADS CONSTRUCTION, LLC (0.06)
Contract #06193204
Totals37447954.8898715.1937693097.9799.9

page 1 | page 2 | page 3