Monthly State Let Maintenance Report For Houston District As Of Mar 13, 2024 Page 6 Of 7

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayUS0290
FromVARIOUS HIGHWAYS IN THE WEST HARRIS CO.
ToVARIOUS HIGHWAYS IN THE WEST HARRIS CO.
CSJ6445-29-001
Proj IDRMC - 644529001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.0102399332.00471562.2619.6
Work Order00-00-00
Work Began12-01-23
Work Completed
Time Computed12-01-23
Contract Working Days731
Addl Days Granted0
Working Days Charged87
Percent Time Used11
Contractor(s)
T & M LAWN-FENCE SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6445-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09234022
Totals2399332.00166527.51471562.2619.6

CountyWALLER
HighwayUS0290
FromVARIOUS HIGHWAYS IN WALLER COUNTY
ToVARIOUS HIGHWAYS IN WALLER COUNTY
CSJ6448-17-001
Proj IDRMC - 644817001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.010290978.3211604.513.9
Work Order00-00-00
Work Began02-14-24
Work Completed
Time Computed02-14-24
Contract Working Days366
Addl Days Granted0
Working Days Charged12
Percent Time Used3
Contractor(s)
EXPERT MAINTENANCE & CONSTRUCTION SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6448-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234212
Totals290978.3211604.5111604.513.9

CountyMONTGOMERY
HighwayIH0045
FromVARIOUS HIGHWAYS IN MONTGOMERY COUNTY
ToVARIOUS HIGHWAYS IN MONTGOMERY COUNTY
CSJ6449-13-001
Proj IDRMC - 644913001
Work TypeDRAINAGE SYSTEM CLEANING
 
0.0102428750.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-24
Work Began03-01-24
Work Completed
Time Computed03-01-24
Contract Working Days731
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SHALOM SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6449-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234209
Totals2428750.000.000.000.0

CountyWALLER
HighwayUS0290
FromVARIOUS HIGHWAYS IN WALLER COUNTY
ToVARIOUS HIGHWAYS IN WALLER COUNTY
CSJ6449-33-001
Proj IDRMC - 644933001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010385249.0047327.0012.2
Work Order00-00-00
Work Began12-27-23
Work Completed
Time Computed12-11-23
Contract Working Days366
Addl Days Granted0
Working Days Charged79
Percent Time Used21
Contractor(s)
ABOVE ALL CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6449-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234020
Totals385249.0047326.0047327.0012.2

CountyFORT BEND
HighwayUS0059
FromVARIOUS HIGHWAYS IN FORT BEND COUNTY
ToVARIOUS HIGHWAYS IN FORT BEND COUNTY
CSJ6449-37-001
Proj IDRMC - 644937001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010799234.0029273.003.6
Work Order00-00-00
Work Began02-01-24
Work Completed
Time Computed02-01-24
Contract Working Days366
Addl Days Granted0
Working Days Charged25
Percent Time Used6
Contractor(s)
ROSS SA ENTERPRISE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6449-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234213
Totals799234.0029273.0029273.003.6

CountyFORT BEND
HighwayUS0059
FromVARIOUS HIGHWAYS IN FORT BEND COUNTY
ToVARIOUS HIGHWAYS IN FORT BEND COUNTY
CSJ6449-75-001
Proj IDRMC - 644975001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.0101148521.2067017.505.8
Work Order00-00-00
Work Began02-01-24
Work Completed
Time Computed02-01-24
Contract Working Days366
Addl Days Granted0
Working Days Charged25
Percent Time Used6
Contractor(s)
SWEEPING CORPORATION OF AMERICA, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6449-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234020
Totals1148521.2067017.5067017.505.8

CountyMONTGOMERY
HighwayIH0045
FromVARIOUS HIGHWAYS IN MONTGOMERY COUNTY
ToVARIOUS HIGHWAYS IN MONTGOMERY COUNTY
CSJ6450-17-001
Proj IDRMC - 645017001
Work TypeDELINEATOR, OBJ MRK & MAILBOX MAINT
 
0.010653818.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6450-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03244013
Totals653818.000.000.000.0

CountyMONTGOMERY
HighwayIH0045
FromVARIOUS HIGHWAYS IN MONTGOMERY COUNTY
ToVARIOUS HIGHWAYS IN MONTGOMERY COUNTY
CSJ6450-19-001
Proj IDRMC - 645019001
Work TypeASPHALT PAVEMENT REPAIR
 
0.0101525300.0066748.464.3
Work Order02-01-24
Work Began02-01-24
Work Completed
Time Computed02-01-24
Contract Working Days731
Addl Days Granted0
Working Days Charged25
Percent Time Used3
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6450-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11234021
Totals1525300.0066748.4666748.464.3

CountyMONTGOMERY
HighwayIH0045
FromVARIOUS HIGHWAYS IN MONTGOMERY COUNTY
ToVARIOUS HIGHWAYS IN MONTGOMERY COUNTY
CSJ6450-21-001
Proj IDRMC - 645021001
Work TypeSMALL SIGN REPLACEMENT
 
0.0101335530.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-24
Work Began03-01-24
Work Completed
Time Computed03-01-24
Contract Working Days731
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HAZMAT INTERNATIONAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6450-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244021
Totals1335530.000.000.000.0

CountyMONTGOMERY
HighwayIH0045
FromVARIOUS HIGHWAYS IN MONTGOMERY COUNTY
ToVARIOUS HIGHWAYS IN MONTGOMERY COUNTY
CSJ6450-27-001
Proj IDRMC - 645027001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010818950.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-24
Work Began03-01-24
Work Completed
Time Computed03-01-24
Contract Working Days731
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SHALOM SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6450-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234034
Totals818950.000.000.000.0

CountyHARRIS
HighwaySH0249
FromSH 249 ETC VARIOUS LOCATIONS
ToSH 249 ETC VARIOUS LOCATIONS
CSJ6450-37-001
Proj IDRMC - 645037001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.0103156875.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MC2 CIVIL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6450-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244211
Totals3156875.000.000.000.0

CountyHARRIS
HighwayIH0069
FromVARIOUS LOCATIONS IN N. HARRIS COUNTY
ToVARIOUS LOCATIONS IN N. HARRIS COUNTY
CSJ6452-11-001
Proj IDRMC - 645211001
Work TypeTRAFFIC CONTROL SERVICES
 
0.010484669.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-21-24
Work Completed
Time Computed02-21-24
Contract Working Days366
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6452-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234214
Totals484669.000.000.000.0

CountyGALVESTON
HighwayFM1764
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6454-15-001
Proj IDRMC - 645415001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.0101195115.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SWEEPING CORPORATION OF AMERICA, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6454-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03244014
Totals1195115.000.000.000.0

CountyFORT BEND
HighwayUS0059
FromVARIOUS HIGHWAYS IN FORT BEND COUNTY
ToVARIOUS HIGHWAYS IN FORT BEND COUNTY
CSJ6454-76-001
Proj IDRMC - 645476001
Work TypeBRIDGE DECK REPAIR
 
0.010368000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-01-24
Work Completed
Time Computed03-01-24
Contract Working Days366
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6454-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244023
Totals368000.000.000.000.0

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTHEAST HARRIS COUNTY
ToVARIOUS HWYS IN SOUTHEAST HARRIS COUNTY
CSJ6455-75-001
Proj IDRMC - 645575001
Work TypePUMP STATION & DRAINAGE SYSTEM CLEANING
 
0.010292130.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days366
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AIMS COMPANIES
SUBCONTRACTOR(S) FOR CCSJ: 6455-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244024
Totals292130.000.000.000.0

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTHEAST HARRIS COUNTY
ToVARIOUS HWYS IN SOUTHEAST HARRIS COUNTY
CSJ6456-47-001
Proj IDRMC - 645647001
Work TypeREFLECTIVE PAVEMENT MARKINGS (GRAPHICS)
 
0.0101085389.900.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6456-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244212
Totals1085389.900.000.000.0

CountyHARRIS
HighwayIH0069
FromIH 69, ETC. VARIOUS ROADWAYS N. HARRIS
ToIH 69, ETC. VARIOUS ROADWAYS N. HARRIS
CSJ6457-09-001
Proj IDRMC - 645709001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.0101835440.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MBN ENTERPRISES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6457-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244209
Totals1835440.000.000.000.0

CountyMONTGOMERY
HighwayIH0045
FromVARIOUS HIGHWAYS IN MONTGOMERY COUNTY
ToVARIOUS HIGHWAYS IN MONTGOMERY COUNTY
CSJ6457-33-001
Proj IDRMC - 645733001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.0101336286.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days366
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HAZMAT INTERNATIONAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6457-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244015
Totals1336286.000.000.000.0

CountyMONTGOMERY
HighwayIH0045
FromVARIOUS HIGHWAYS IN MONTGOMERY COUNTY
ToVARIOUS HIGHWAYS IN MONTGOMERY COUNTY
CSJ6457-37-001
Proj IDRMC - 645737001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.010659840.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days366
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6457-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244215
Totals659840.000.000.000.0

CountyGALVESTON
HighwayFM0518
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6459-43-001
Proj IDRMC - 645943001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.010394005.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed03-04-24
Contract Working Days366
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6459-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01244213
Totals394005.000.000.000.0