Monthly State Let Construction Report For El Paso District As Of May 10, 2018 Page 1 Of 2

Last Update: Thursday, May 10, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEL PASO
HighwayUS 62
From650 FT W OF EUCALYPTUS ST
ToBARCELONA DR
CSJ0001-04-094
Proj IDNH 1502(154)
Work TypeVEGETATION LANDSCAPE
 
3.618682967.00830133.1899.9
Work Order08-04-15
Work Began04-04-16
Work Completed
Time Computed04-04-16
Contract Working Days60
Addl Days Granted40
Working Days Charged99
Percent Time Used99
Contractor(s)
DOUBLE H CONTRACTING INC.
SUBCONTRACTOR(S) FOR CCSJ: 0001-04-094
APACHE BARRICADE & SIGN (1.53)
BRAVO EL PASO LANDSCAPING AND IRRIGATION (3.66)
SATARAIN CONSTRUCTION, INC. (8.45)
TEXAS CONCRETE AND ASPHALT, INC. (10.24)
TRI STATE ELECTRIC, LTD. (2.63)
Contract #05153020
Totals682967.000.00830133.1899.9

CountyEL PASO
HighwaySH 20
FromPADRES
ToLOOP 375 (AMERICAS AVENUE)
CSJ0002-01-055
Proj IDNH 1602(497)
Work TypeRECON RDWY, INT IMPRVMNTS & REHAB
 
1.8956620004.353586821.0654.1
CountyEL PASO
HighwaySH 20
FromPADRES
ToLOOP 375 (AMERICAS AVENUE)
CSJ0002-01-094
Proj IDROW 2-1-94
Work TypeROW ACQUISITION
 
1.562473499.00238166.3350.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-17
Work Began07-17-17
Work Completed
Time Computed00-00-00
Contract Working Days385
Addl Days Granted0
Working Days Charged206
Percent Time Used53
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0002-01-055
ALLEN CONCRETE, INC. (8.22)
BOWEN INDUSTRIAL CONTRACTORS, INC. (2.12)
LOS FIERRO CONSTRUCTION (6.16)
TRAFFIC BARRICADE SERVICE, INC. (1.69)
TRI STATE ELECTRIC, LTD. (25.65)
FALC ENTERPRISES, LLC (0.26)
Contract #05173017
Totals7093503.35339409.833824987.3953.9

CountyHUDSPETH
HighwayIH 10
From0.81 MI W OF FM 34
ToFM 34
CSJ0002-05-045
Proj IDNH 1702(307)
Work TypeCHANNEL IMPROVEMENTS
 
0.811603661.00565396.7493.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-11-17
Work Began09-11-17
Work Completed
Time Computed00-00-00
Contract Working Days140
Addl Days Granted0
Working Days Charged140
Percent Time Used100
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0002-05-045
MARIL ENTERPRISES LLC (70.41)
Contract #07173250
Totals603661.0050010.45565396.7493.6

CountyEL PASO
HighwayUS 62 ETC
FromAT TROWBRIDGE
To.
CSJ0002-12-023
Proj IDSTP 2017(574)HES
Work TypeIMPROVE TRAFFIC SIGNAL
 
17.3863537952.652383443.0267.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-07-17
Work Began07-10-17
Work Completed
Time Computed00-00-00
Contract Working Days294
Addl Days Granted0
Working Days Charged195
Percent Time Used66
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0002-12-023
HAWK CONSTRUCTION (3.10)
BORDER DRILLING LLC (0.29)
V.C. HUFF, L.L.C. (4.77)
Contract #04173005
Totals3537952.65176494.972383443.0267.3

CountyEL PASO
HighwayUS 62
FromE YANDELL DR
ToMONTANA AVE
CSJ0002-12-025
Proj IDCM 1702(498)
Work TypeOPERATIONAL IMPROVEMENTS
 
0.17186640.00112497.0099.9
CountyEL PASO
HighwayUS 62
FromHAWKINS BLVD
ToRUTHERGLEN ST
CSJ0374-02-108
Proj IDCM 1702(498)
Work TypeOPERATIONAL IMPROVEMENTS
 
0.806638068.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-16-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0002-12-025
HAWK CONSTRUCTION (8.85)
BOWEN INDUSTRIAL CONTRACTORS, INC. (2.83)
HARDY HOLE DRILLING (2.40)
Contract #07173022
Totals724708.700.00112497.0015.5

CountyJEFF DAVIS
HighwayUS 90
FromCULBERSON/JEFF DAVIS COUNTY LINE
To7.653 MI S OF FM 2017
CSJ0020-03-019
Proj IDSTP 1602(498)
Work TypeROADWAY REHABILITATION
 
9.2363507766.374592946.6199.9
CountyJEFF DAVIS
HighwayUS 90
From7.653 MI S OF FM 2017
To7.265 MI N OF RM 505
CSJ0020-04-016
Proj IDSTP 1602(498)
Work TypeROADWAY REHABILITATION
 
8.9044954523.846622392.5699.9
CountyJEFF DAVIS
HighwayUS 90
From7.265 MI N OF RM 505
ToJEFF DAVIS/PRESIDIO COUNTY LINE
CSJ0020-05-015
Proj IDSTP 1602(498)
Work TypeROADWAY REHABILITATION
 
7.7203360797.476865499.6499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-08-16
Work Began11-09-16
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted184
Working Days Charged338
Percent Time Used92
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0020-03-019
BOWEN INDUSTRIAL CONTRACTORS, INC. (1.68)
HENRY TRUJILLO, INC. (0.07)
ENVIRONMENTAL SAFETY SERVICES, INC. (8.67)
X GOMEZ TRANSPORTATION (0.85)
Contract #08163206
Totals11823087.6825307.3018080838.8199.9

CountyPRESIDIO ETC
HighwayUS 90 ETC
FromJEFF DAVIS/PRESIDIO COUNTY LINE
To12.96 MI W OF RM 2810
CSJ0020-06-017
Proj IDNH 2018(338)
Work TypePREVENTATIVE MAINTENANCE
 
177.3737823711.771878700.2924.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-05-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0020-06-017
FLASHER LIMITED (1.23)
VIZCAINO, L.P. (7.86)
Contract #12173009
Totals7823711.77827.901878700.2924.0

CountyBREWSTER
HighwayUS 67
FromJCT US 90
To1.35 MI E OF SH 223
CSJ0021-01-053
Proj IDNH 2017(324)
Work TypeROADWAY REHABILITATION
 
6.3092339737.202577989.9399.9
CountyBREWSTER
HighwayUS 90
From0.298 MI E OF US 67/US 90 INTER
To1.103 MI E OF US 67/US 90 INTER
CSJ0021-01-055
Proj IDNH 2017(324)
Work TypeFY 2016 BRIDGE MAINTENANCE PROGRAM
 
1.4021208740.001632301.9899.9
CountyBREWSTER
HighwayUS 90
FromJCT US 67
To1.63 MI E OF US 67
CSJ0021-01-057
Proj IDNH 2017(324)
Work TypeROADWAY REHABILITATION
 
1.877462080.50741578.4899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-07-17
Work Began03-27-17
Work Completed
Time Computed00-00-00
Contract Working Days140
Addl Days Granted72
Working Days Charged187
Percent Time Used88
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0021-01-053
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.82)
X GOMEZ LOGISTICS, LLC (2.27)
FALC ENTERPRISES, LLC (0.46)
BOWEN INDUSTRIAL CONTRACTORS, INC. (2.21)
Contract #01173025
Totals4010557.7020197.454951870.3999.9

CountyPRESIDIO
HighwayUS 67
FromPUERTO RICO ST
ToINTERNATIONAL DEMARCATION LINE
CSJ0104-10-006
Proj IDNH 1702(686)
Work TypeNEW TWO-LANE TWIN BRIDGE STRUCTURE
 
0.6596854362.50353662.425.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-25-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days260
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0104-10-006
PRIMATE CONSTRUCTION, INC. (0.19)
BOWMAN ENGINEERING & CONSULTING, INC (0.00)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.73)
CONTRACTORS SERVICE COMPANY (0.85)
MICA CORPORATION (6.41)
Contract #08173207
Totals6854362.5056441.28353662.425.1

CountyEL PASO
HighwayUS 54
FromHONDO PASS DRIVE
ToSL 375
CSJ0167-01-095
Proj IDSTP 1702(687)MM
Work TypeWIDEN BY ADDING TWO INSIDE LANES
 
1.99213995966.376389030.1745.6
CountyEL PASO
HighwayUS 54
FromHONDO PASS DRIVE
ToSL 375
CSJ0167-01-098
Proj IDSTP 1702(687)MM
Work TypeOPERATIONAL IMPROVEMENTS
 
1.99219680182.552916348.2114.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-12-17
Work Began11-09-17
Work Completed
Time Computed00-00-00
Contract Working Days460
Addl Days Granted0
Working Days Charged128
Percent Time Used27
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0167-01-095
HARDY HOLE DRILLING (0.15)
TRI STATE ELECTRIC, LTD. (33.92)
A BROTHERS MILLING, LLC (0.15)
ANTIGO CONSTRUCTION, INC. (0.19)
CONCRETE PUMPING, INC. DBA CPI (0.12)
EARTH REINFORCEMENTS LLC (2.53)
PENHALL COMPANY (0.01)
SCOTT DERR PAINTING CO, LLC (0.19)
X GOMEZ LOGISTICS, LLC (1.46)
SATARAIN CONSTRUCTION, INC. (5.68)
NATIONWIDE REBAR, INC. (4.26)
PMI PAVEMENT MARKING, INC. (0.63)
HARDY HOLE DRILLING (1.18)
A BROTHERS MILLING, LLC (0.01)
GREENE CRANE & RIGGING, LLC (0.21)
BORDER DRILLING LLC (0.13)
Contract #08173002
Totals33676148.922156191.879305378.3827.6

CountyCULBERSON ETC
HighwayUS 62 ETC
From9.2 MI E OF SH 54
To3.9 MI W OF RM 652
CSJ0233-01-044
Proj IDSTP 2017(953)HES
Work TypeMODERNIZE BRIDGE RAIL/APR GUARDRAIL
 
49.2123783684.492394285.1363.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-16-17
Work Began07-17-17
Work Completed
Time Computed00-00-00
Contract Working Days200
Addl Days Granted0
Working Days Charged193
Percent Time Used96
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0233-01-044
DOUBLE A CONTRACTING, L.P. (1.00)
Contract #04173211
Totals3783684.49353229.442394285.1363.2

CountyEL PASO
HighwayUS 62
From0.724 MI E OF FM 2316
To1.432 MI W OF RM 2775
CSJ0374-02-106
Proj IDSTP 1702(039)HES
Work TypePROFILE EDGELINE MARKINGS
 
15.188311698.70312156.7899.9
CountyEL PASO
HighwayVA
FromDISTRICTWIDE
To.
CSJ0924-00-082
Proj IDSTP 1702(040)
Work TypeFY 2017 STRIPING PROJECTS
 
1.000504246.74913236.1899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-26-17
Work Began08-07-17
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted20
Working Days Charged140
Percent Time Used100
Contractor(s)
PMI PAVEMENT MARKING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0374-02-106
TRAFFIC CONTROL SPECIALIST SALES & RENTALS (8.20)
SAN BAR CONSTRUCTION CORPORATION (5.35)
Contract #05173213
Totals815945.44275.771225392.9699.9

CountyEL PASO
HighwayUS 62
From9.141 MI E OF FM 659 (ZARAGOZA)
To13.043 MI E OF FM 659 (ZARAGOZA)
CSJ0374-03-028
Proj IDSTP 2018(526)HES
Work TypeTEXTURIZED SHOULDERS
 
3.90237806.720.000.0
CountyEL PASO
HighwayVA
FromDISTRICTWIDE
To.
CSJ0924-00-098
Proj IDSTP 2018(525)
Work TypeFY 2018 STRIPING PROJECT
 
1.000745864.770.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-27-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PMI PAVEMENT MARKING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0374-03-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183026
Totals783671.490.000.000.0

CountyHUDSPETH
HighwayUS 62
From4.387 MI W OF RM 2317
To3.387 MI W OF RM 2317
CSJ0374-05-027
Proj IDBR 2018(524)
Work TypeBOX CULVERT STRUCTURAL REPAIR
 
1.00054568.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-07-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days22
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E. G. L. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0374-05-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183204
Totals54568.000.000.000.0

CountyJEFF DAVIS
HighwaySH 118
From15.219 MI N OF SH 17
ToSH 17
CSJ0415-01-025
Proj IDSTP 2018(878)HES
Work TypeIMPROVE GUARDRAIL TO STANDARDS
 
15.219340160.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0415-01-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183227
Totals340160.000.000.000.0

CountyEL PASO
HighwayVA
FromDISTRICTWIDE
To.
CSJ0924-00-086
Proj IDSTP 2013(863)
Work TypeMETAL BEAM GUARD FENCE/SGT UPGRADES
 
3.2821408923.001193658.4598.8
Work Order10-24-13
Work Began11-14-13
Work Completed
Time Computed11-09-13
Contract Working Days188
Addl Days Granted235
Working Days Charged714
Percent Time Used168
Contractor(s)
SURETEC INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0924-00-086
DAN WILLIAMS COMPANY (0.00)
X GOMEZ LOGISTICS, LLC (0.00)
Contract #07133012
Totals1408923.0010933.661193658.4598.8

CountyEL PASO
HighwayVA
FromAT VARIOUS LOCATION IN EL PASO CO
To.
CSJ0924-06-450
Proj IDSTP 2018(265)
Work TypeCONSTRUCT CURB RAMPS
 
1.0001766126.50402169.3622.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-04-17
Work Began01-15-18
Work Completed
Time Computed00-00-00
Contract Working Days235
Addl Days Granted0
Working Days Charged74
Percent Time Used31
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-450
TRI STATE ELECTRIC, LTD. (20.04)
BOWEN INDUSTRIAL CONTRACTORS, INC. (3.49)
Contract #11173005
Totals1766126.50151015.87402169.3622.7

CountyEL PASO
HighwayCS
FromALBERTON AVE
To200 FT S OF LTV RD
CSJ0924-06-457
Proj IDSTP 2015(455)MM
Work TypeWIDEN ROAD
 
1.2506591274.785255208.1279.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-03-16
Work Began02-01-17
Work Completed
Time Computed00-00-00
Contract Working Days240
Addl Days Granted81
Working Days Charged297
Percent Time Used92
Contractor(s)
J. A. R. CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-457
INTERNATIONAL EAGLE ENTERPRISES, INC. (42.75)
TRI STATE ELECTRIC, LTD. (10.14)
PRIME IRRIGATION & LANDSCAPE, INC. (1.94)
ABRI TRANSPORTATION SERVICES, LLC (0.37)
PMI PAVEMENT MARKING, INC. (0.82)
HENRY TRUJILLO, INC. (0.39)
FALC ENTERPRISES, LLC (0.37)
BORDER DRILLING LLC (0.01)
HARDY HOLE DRILLING (0.05)
NATIONWIDE REBAR INC (0.34)
DUSTROL, INC. (0.38)
Contract #08163204
Totals6591274.78154288.735255208.1279.7

CountyEL PASO
HighwayVA
FromCOUNTY WIDE
To.
CSJ0924-06-533
Proj IDNH 1702(500)
Work TypeVEGETATION LANDSCAPE
 
6.4401330984.071214884.4191.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-23-17
Work Began10-02-17
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted40
Working Days Charged136
Percent Time Used97
Contractor(s)
ALLIED PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-533
ZAYZA IRRIGATION AND LANDSCAPE (37.08)
TRAFFIC BARRICADE SERVICE, INC. (3.00)
FALC ENTERPRISES, LLC (4.16)
Contract #07173223
Totals1330984.0798089.051214884.4191.2

CountyEL PASO
HighwayIH 10
From@ MESA
To.
CSJ2121-01-087
Proj IDSTP 2015(221)HES
Work TypeIMPROVE TRAFFIC SIGNAL
 
0.313458248.263287.080.7
CountyEL PASO
HighwayIH 10
From0.48 MI E OF SUNLAND PARK DR
To0.45 MI E OF EXECUTIVE CENTER
CSJ2121-02-132
Proj IDNH 2015(335)
Work TypeREHABILITATION
 
2.8362487085.0995457.173.8
CountyEL PASO
HighwayIH 10
FromMESA STREET
ToEXECUTIVE CENTER
CSJ2121-02-137
Proj IDCBI 2015(220)
Work TypeCOLLECTOR DISTRIBUTOR LANES
 
5.164151231706.19125342266.5777.6
CountyEL PASO
HighwayIH 10
FromMESA STREET
ToEXECUTIVE CENTER
CSJ2121-02-154
Proj IDROW 2121-2-154
Work TypeACQUISITION AND UTILITIES
 
7.8544601364.664426081.5396.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-19-14
Work Began04-06-15
Work Completed
Time Computed00-00-00
Contract Working Days1,211
Addl Days Granted51
Working Days Charged887
Percent Time Used70
Contractor(s)
TRADECO INFRAESTRUCTURA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2121-01-087
ZTEX CONSTRUCTION, INC. (9.00)
TRAFFIC CONTROL SPECIALIST SALES & RENTALS (0.09)
HARDY HOLE DRILLING (0.69)
TRI STATE ELECTRIC, LTD. (1.25)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.69)
SOUTHWESTERN INDUSTRIAL CONTRACTORS (0.21)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.02)
HENRY TRUJILLO, INC. (0.01)
A BROTHERS (OLD PRIME) (0.13)
SUNDT CONSTRUCTION, INC. (0.00)
TRI STATE ELECTRIC, LTD. (12.29)
HARDY HOLE DRILLING (0.46)
HARDY HOLE DRILLING (3.12)
D"AMBRA CONSTRUCTION CORPORATION (0.10)
PMI PAVEMENT MARKING, INC. (0.36)
DH UNDERGROUND, INC. (0.63)
ANTIGO CONSTRUCTION, INC. (0.04)
ADVANCED CONCRETE SAWING & SEALING, LLC (0.34)
ALLIED PAVING CO. (0.64)
REBAR REINFORCEMENT PLACERS (6.83)
EARTH REINFORCEMENT SPECIALISTS (0.99)
CHOCTAW ERECTORS, INC. (2.49)
SCOTT DERR PAINTING CO, LLC (0.42)
LEEDSMAN CONSTRUCTION, INC. (1.19)
HENRY TRUJILLO, INC. (1.14)
BORDER DRILLING LLC (0.06)
CRANE SERVICES, INC. (0.01)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.84)
CANO STRUCTURES, LLC (0.82)
KEN"S PORTABLE WELDING (0.01)
PENHALL COMPANY (0.25)
HERNANDEZ CONCRETE PUMPING (0.13)
A BROTHERS MILLING, LLC (0.05)
MFH ENVIRONMENTAL CORP. (0.00)
HAWK CONSTRUCTION (0.05)
HDW CONSTRUCTION & DRILLING, LLC. (0.01)
RESONANT MACHINES (0.01)
Contract #10143001
Totals158778404.205489185.44129867092.3576.7

page 1 | page 2