Item No | Description | Units | March 31, 2019 | Twelve-Month-Moving | Usage |
Quantity | Avg Bid | Quantity | Avg Bid |
100 6001 | PREPARING ROW | AC | | | 8.530 | 4,724.50176 | 3 |
100 6002 | PREPARING ROW | STA | | | 1,424.550 | 852.39252 | 10 |
100 6013 | PREP ROW (TREE) (2" TO 12" DIA) | EA | | | 46.000 | 307.39130 | 2 |
104 6001 | REMOVING CONC (PAV) | SY | | | 104,223.000 | 11.77663 | 5 |
104 6009 | REMOVING CONC (RIPRAP) | SY | | | 22,717.000 | 9.78005 | 3 |
104 6010 | REMOVING CONC (RIPRAP) | CY | | | 12.000 | 175.00000 | 1 |
104 6011 | REMOVING CONC (MEDIANS) | SY | | | 10,474.000 | 9.83808 | 3 |
104 6013 | REMOVING CONC (FOUNDATIONS) | SY | | | 9.000 | 34.00000 | 1 |
104 6015 | REMOVING CONC (SIDEWALKS) | SY | | | 4,066.000 | 11.24766 | 3 |
104 6017 | REMOVING CONC (DRIVEWAYS) | SY | | | 10,040.000 | 9.45692 | 2 |
104 6021 | REMOVING CONC (CURB) | LF | | | 16,057.000 | 3.19522 | 2 |
104 6022 | REMOVING CONC (CURB AND GUTTER) | LF | | | 12,180.000 | 5.00000 | 1 |
104 6023 | REMOVING CONC (CTB) | LF | | | 10,881.000 | 14.59350 | 3 |
104 6024 | REMOVING CONC (RETAINING WALLS) | SY | | | 7,610.000 | 12.45030 | 3 |
104 6028 | REMOVING CONC (MISC) | SY | | | 852.000 | 10.00000 | 1 |
104 6029 | REMOVING CONC (CURB OR CURB & GUTTER) | LF | | | 28,970.000 | 4.02485 | 2 |
104 6036 | REMOVING CONC (SIDEWALK OR RAMP) | SY | | | 3,150.000 | 10.51571 | 3 |
104 6040 | REMOVING CONC (PAVERS) | SY | | | 8.000 | 14.00000 | 1 |
104 6044 | REMOVING CONC (FLUME) | SY | | | 58.000 | 45.41276 | 2 |
104 6049 | REMOVE CONCRETE (MSE PANELS) | SF | | | 918.000 | 8.00000 | 1 |
104 6064 | REMOVING CONC (MISC) | CY | | | 42.000 | 71.50000 | 1 |
105 6011 | REMOVING STAB BASE AND ASPH PAV (2"-6" | SY | | | 3,492.000 | 6.00000 | 1 |
105 6016 | REMOVING STAB BASE & ASPH PAV(16") | SY | | | 1,017.000 | 11.50000 | 1 |
105 6019 | REMOVING STAB BASE & ASPH PAV(14") | SY | | | 2,157.000 | 7.00000 | 1 |
105 6033 | REMOVING STB BASE AND ASPH PAV(10-14") | SY | | | 6,420.000 | 5.50000 | 1 |
105 6035 | REMOVING STAB BASE & ASPH PAV (0-2") | SY | | | 712.000 | 10.00000 | 1 |
105 6037 | REMOVING STAB BASE AND ASPH PAV(0"-16" | SY | | | 20,441.000 | 5.55574 | 2 |
105 6043 | REMOVING STAB BASE & ASPH PAV (0-6") | SY | | | 5,728.000 | 4.30000 | 1 |
105 6049 | REMOVING STAB BASE & ASPH PAV (4"-22") | SY | | | 353,180.000 | 5.00010 | 2 |
105 6075 | REMOV STAB BASE AND ASPH PAV (10"-18") | SY | | | 331.000 | 35.00000 | 1 |
105 6089 | REMOVING STAB BASE AND ASP PAV(19"-20" | SY | | | 18,658.000 | 5.00000 | 1 |
110 6001 | EXCAVATION (ROADWAY) | CY | | | 1,624,527.000 | 7.63640 | 9 |
110 6002 | EXCAVATION (CHANNEL) | CY | | | 3,729.000 | 24.55162 | 2 |
110 6003 | EXCAVATION (SPECIAL) | CY | | | 24,766.500 | 25.59036 | 4 |
112 6001 | SUBGRADE WIDENING (ORD COMP) | STA | | | 127.300 | 950.00000 | 1 |
112 6002 | SUBGRADE WIDENING (DENS CONT) | STA | | | 6.000 | 2,500.00000 | 1 |
132 6001 | EMBANKMENT (FINAL)(ORD COMP)(TY A) | CY | | | 2,611.000 | 10.04902 | 2 |
132 6002 | EMBANKMENT (FINAL)(DENS CONT)(TY A) | CY | | | 975,210.000 | 6.58098 | 6 |
132 6003 | EMBANKMENT (FINAL)(ORD COMP)(TY B) | CY | | | 501.000 | 69.52096 | 2 |
132 6006 | EMBANKMENT (FINAL)(DENS CONT)(TY C) | CY | | | 111,259.400 | 23.92690 | 2 |
132 6036 | EMB(FNL)(DC)(TYE)(CSBE)(RWALL FND IMPR | CY | | | 7,582.000 | 39.61000 | 1 |
134 6004 | BACKFILL (TY A OR B) | STA | | | 702.500 | 107.45217 | 3 |
134 6005 | BACKFILL TY A | CY | | | 95,168.700 | 22.32261 | 2 |
150 6002 | BLADING | HR | | | 124.000 | 128.55500 | 2 |
156 6001 | BULLDOZER WORK | HR | | | 40.000 | 85.00000 | 1 |
164 6001 | BROADCAST SEED (PERM) (RURAL) (SANDY) | SY | | | 95.000 | 75.00000 | 1 |
170 6001 | IRRIGATION SYSTEM | LS | | | 4.000 | 148,355.50000 | 4 |
192 6002 | PLANT MATERIAL (1-GAL) | EA | | | 617.000 | 13.00000 | 1 |
192 6004 | PLANT MATERIAL (5-GAL) | EA | | | 2,692.000 | 29.64785 | 3 |
192 6013 | MULCH | SY | | | 656.000 | 8.10000 | 1 |
192 6014 | PLANT SOIL MIX | CY | | | 1,798.000 | 30.98476 | 2 |
192 6015 | LANDSCAPE EDGE | LF | | | 73,097.000 | 5.87195 | 2 |
192 6016 | PLANT BED PREPARATION | SY | | | 2,184.000 | .60000 | 1 |
192 6017 | VEGETATION BARRIER | SY | | | 376,164.000 | 1.14843 | 4 |
192 6023 | PLANT MATERIAL (15 GAL) (TREE) | EA | | | 13.000 | 160.00000 | 1 |
192 6024 | PLANT MATERIAL (30 GAL) (TREE) | EA | | | 132.000 | 322.24091 | 2 |
192 6026 | PLANT MATERIAL (65 GAL) (TREE) | EA | | | 74.000 | 585.00000 | 1 |
192 6030 | PLANT MATERIAL (3 GAL) (SHRUB) | EA | | | 858.000 | 24.00000 | 1 |
192 6031 | PLANT MATERIAL (5 GAL) (SHRUB) | EA | | | 278.000 | 26.40000 | 1 |
192 6044 | PLANT MATERIAL (MIN 2" CAL) (B&B) | EA | | | 680.000 | 324.00000 | 1 |
192 6046 | PLANT MATERIAL (MIN 3" CAL) (B&B) | EA | | | 509.000 | 432.16110 | 2 |
192 6050 | PLANT MATERIAL (MIN 6' TRNK HT) (PALM) | EA | | | 8.000 | 526.40000 | 1 |
192 6055 | PLANT MATERIAL (MIN 4'HT) (BARE ROOT) | EA | | | 44.000 | 40.00000 | 1 |
192 6056 | PLANT MATERIAL (MIN 6'HT) (BARE ROOT) | EA | | | 11.000 | 94.80000 | 1 |
192 6058 | PLANT MATERIAL (20 GAL)(TREE) | EA | | | 315.000 | 289.50000 | 1 |
192 6097 | CONC LNDSCP EDG (12 IN WIDTH) | LF | | | 1,919.000 | 20.00000 | 1 |
192 6100 | VEGETATION BARRIER (TREE ROOT) | SY | | | 24,695.000 | .75000 | 1 |
193 6001 | PLANT MAINTENANCE | MO | | | 48.000 | 794.35000 | 4 |
193 6005 | PLANT REPLACEMENT (5-GAL) | EA | | | 306.000 | 29.72124 | 3 |
193 6007 | IRRIGATION SYSTEM OPER AND MAINT | MO | | | 48.000 | 470.12500 | 4 |
193 6009 | PLANT REPLACEMENT (15 GAL) | EA | | | 4.000 | 175.00000 | 1 |
193 6010 | PLANT REPLACEMENT (30 GAL) | EA | | | 80.000 | 218.95625 | 2 |
193 6016 | PLANT REPLACEMENT (45 GAL) | EA | | | 59.000 | 429.66102 | 2 |
193 6017 | PLANT REPLACEMENT (20 GAL) | EA | | | 32.000 | 379.00000 | 1 |