Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | BRAZOS |
Highway | SH0006 |
From | BRYAN DISTRICT HQ |
To | BRYAN DISTRICT HQ |
CSJ | 6447-62-001 |
Proj ID | SUP - 644762001 |
Work Type | VEGETATION MANAGEMENT |
|
| 0.010 | 127621.76 | | 14654.02 | 11.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 06-12-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 731 |
Addl Days Granted | 0 |
Working Days Charged | 263 |
Percent Time Used | 35 |
Contractor(s) |
WORKQUEST SAUMYA, INC |
SUBCONTRACTOR(S) FOR CCSJ: 6447-62-001 SAUMYA, INC (0.00)
|
Contract # | 06231730 |
| Totals | 127621.76 | 1460.92 | 14654.02 | 11.4 |
|
County | WASHINGTON |
Highway | SH0105 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6451-67-001 |
Proj ID | SUP - 645167001 |
Work Type | PICNIC AREA MAINTENANCE |
|
| 0.010 | 82234.40 | | 22726.18 | 27.6 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 08-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 213 |
Percent Time Used | 29 |
Contractor(s) |
WORKQUEST JUNCTION FIVE-O-FIVE |
SUBCONTRACTOR(S) FOR CCSJ: 6451-67-001 JUNCTION FIVE-O-FIVE (0.00)
|
Contract # | 07231730 |
| Totals | 82234.40 | 3291.62 | 22726.18 | 27.6 |
|
County | WALKER |
Highway | IH0045 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6454-31-001 |
Proj ID | MMC - 645431001 |
Work Type | ROCK/RIPRAP |
|
| 0.010 | 184900.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 12-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 180 |
Working Days Charged | 91 |
Percent Time Used | 25 |
Contractor(s) |
TOUCHSTONE RESOURCES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6454-31-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10231704 |
| Totals | 184900.00 | 0.00 | 0.00 | 0.0 |
|
County | BRAZOS |
Highway | SH0006 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6454-91-001 |
Proj ID | RMC - 645491001 |
Work Type | DEBRIS REMOVAL |
|
| 0.010 | 248160.00 | | 19680.00 | 7.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 01-01-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 60 |
Percent Time Used | 16 |
Contractor(s) |
R&M INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6454-91-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10231701 |
| Totals | 248160.00 | 9480.00 | 19680.00 | 7.9 |
|
County | WALKER |
Highway | IH0045 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6455-57-001 |
Proj ID | MMC - 645557001 |
Work Type | EMULSION |
|
| 0.010 | 167600.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 12-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 180 |
Working Days Charged | 91 |
Percent Time Used | 25 |
Contractor(s) |
CLEVELAND ASPHALT PRODUCTS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6455-57-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10231705 |
| Totals | 167600.00 | 0.00 | 0.00 | 0.0 |
|
County | WASHINGTON |
Highway | SH0036 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6456-05-001 |
Proj ID | RMC - 645605001 |
Work Type | RAISED PAVEMENT MARKERS |
|
| 0.010 | 137285.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 12-06-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 86 |
Percent Time Used | 23 |
Contractor(s) |
BRYDL CONTRACTING, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6456-05-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10231703 |
| Totals | 137285.00 | 0.00 | 0.00 | 0.0 |
|
County | WASHINGTON |
Highway | SH0036 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6456-29-001 |
Proj ID | MMC - 645629001 |
Work Type | CUTBACK |
|
| 0.010 | 149280.00 | | 24274.86 | 16.2 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 12-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 180 |
Working Days Charged | 91 |
Percent Time Used | 25 |
Contractor(s) |
MARTIN RESOURCE MANAGEMENT CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 6456-29-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10231706 |
| Totals | 149280.00 | 0.00 | 24274.86 | 16.2 |
|
County | WASHINGTON |
Highway | SH0036 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6456-31-001 |
Proj ID | MMC - 645631001 |
Work Type | EMULSION |
|
| 0.010 | 193320.00 | | 47506.08 | 24.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 12-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 180 |
Working Days Charged | 91 |
Percent Time Used | 25 |
Contractor(s) |
ERGON ASPHALT & EMULSIONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6456-31-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10231707 |
| Totals | 193320.00 | 29755.52 | 47506.08 | 24.5 |
|
County | FREESTONE |
Highway | IH0045 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6456-33-001 |
Proj ID | MMC - 645633001 |
Work Type | EMULSION |
|
| 0.010 | 163760.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 12-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 180 |
Working Days Charged | 91 |
Percent Time Used | 25 |
Contractor(s) |
ERGON ASPHALT & EMULSIONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6456-33-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10231708 |
| Totals | 163760.00 | 0.00 | 0.00 | 0.0 |
|
County | FREESTONE |
Highway | IH0045 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6456-35-001 |
Proj ID | MMC - 645635001 |
Work Type | ROCK/RIPRAP |
|
| 0.010 | 163600.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 12-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 180 |
Working Days Charged | 91 |
Percent Time Used | 25 |
Contractor(s) |
TOUCHSTONE RESOURCES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6456-35-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10231709 |
| Totals | 163600.00 | 0.00 | 0.00 | 0.0 |
|
County | BRAZOS |
Highway | SH0006 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6457-63-001 |
Proj ID | SUP - 645763001 |
Work Type | JANITORIAL MAINTENANCE |
|
| 0.010 | 140699.36 | | 23067.39 | 16.3 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 10-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 152 |
Percent Time Used | 20 |
Contractor(s) |
WORKQUEST JUNCTION FIVE-O-FIVE |
SUBCONTRACTOR(S) FOR CCSJ: 6457-63-001 JUNCTION FIVE-O-FIVE (0.00)
|
Contract # | 09231730 |
| Totals | 140699.36 | 4068.46 | 23067.39 | 16.3 |
|
County | BRAZOS |
Highway | SH0006 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6459-10-001 |
Proj ID | RMC - 645910001 |
Work Type | TREE REMOVAL |
|
| 0.010 | 395100.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-16-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 14 |
Percent Time Used | 3 |
Contractor(s) |
ICOS MANAGEMENT, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6459-10-001 ORTEGA"S LAWN AND LANDSCAPING, LLC (0.00)
|
Contract # | 12231702 |
| Totals | 395100.00 | 0.00 | 0.00 | 0.0 |
|
County | LEON |
Highway | US0079 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6459-17-001 |
Proj ID | RMC - 645917001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 188790.05 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-16-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 14 |
Percent Time Used | 3 |
Contractor(s) |
AABA MOWING CONTRACTORS, LIMITED LIABILITY COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 6459-17-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12231703 |
| Totals | 188790.05 | 0.00 | 0.00 | 0.0 |
|
County | WALKER |
Highway | FM1374 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6459-23-001 |
Proj ID | RMC - 645923001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 185248.60 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-07-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 23 |
Percent Time Used | 6 |
Contractor(s) |
P-VILLE, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6459-23-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12231704 |
| Totals | 185248.60 | 0.00 | 0.00 | 0.0 |
|
County | ROBERTSON |
Highway | US0079 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6459-27-001 |
Proj ID | RMC - 645927001 |
Work Type | TREE REMOVAL |
|
| 0.010 | 390700.00 | | 75964.00 | 19.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-14-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 16 |
Percent Time Used | 4 |
Contractor(s) |
ICOS MANAGEMENT, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6459-27-001 ORTEGA"S LAWN AND LANDSCAPING, LLC (0.00)
|
Contract # | 12231705 |
| Totals | 390700.00 | 75964.00 | 75964.00 | 19.4 |
|
County | MILAM |
Highway | US0079 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6459-29-001 |
Proj ID | RMC - 645929001 |
Work Type | TREE REMOVAL |
|
| 0.010 | 243100.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
ICOS MANAGEMENT, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6459-29-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02241708 |
| Totals | 243100.00 | 0.00 | 0.00 | 0.0 |
|
County | BRAZOS |
Highway | SH0006 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6460-44-001 |
Proj ID | RMC - 646044001 |
Work Type | SWEEPING AND DEBRIS REMOVAL |
|
| 0.010 | 187997.48 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
EXPERT MAINTENANCE & CONSTRUCTION SERVICES LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6460-44-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12231707 |
| Totals | 187997.48 | 0.00 | 0.00 | 0.0 |
|
County | BRAZOS |
Highway | SH0006 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6460-60-001 |
Proj ID | MMC - 646060001 |
Work Type | AGGREGATE |
|
| 0.010 | 90600.00 | | 27615.36 | 30.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-07-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 180 |
Addl Days Granted | 0 |
Working Days Charged | 23 |
Percent Time Used | 12 |
Contractor(s) |
COLORADO MATERIALS, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6460-60-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12231709 |
| Totals | 90600.00 | 27615.36 | 27615.36 | 30.4 |
|
County | LEON |
Highway | IH0045 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6460-61-001 |
Proj ID | MMC - 646061001 |
Work Type | FLOWABLE FILL |
|
| 0.010 | 165000.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-07-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 23 |
Percent Time Used | 6 |
Contractor(s) |
TOUCHSTONE RESOURCES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6460-61-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12231708 |
| Totals | 165000.00 | 0.00 | 0.00 | 0.0 |
|
County | BURLESON |
Highway | FM0060 |
From | VARIOUS |
To | VARIOUS |
CSJ | 6460-80-001 |
Proj ID | RMC - 646080001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 176623.49 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-28-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 2 |
Percent Time Used | 0 |
Contractor(s) |
ABESCAPE LANDSCAPING, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6460-80-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01241701 |
| Totals | 176623.49 | 0.00 | 0.00 | 0.0 |
|