Monthly State Let Construction Report For Bryan District As Of Apr 10, 2018 Page 3 Of 3

Last Update: Friday, April 20, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMILAM
HighwayFM 908
FromUS 79
ToUS 77
CSJ0858-02-021
Proj IDSTP 2018(029)
Work TypeREHABILITATE EXISTING ROAD
 
1.5431428673.97407552.2128.5
Work Order11-20-17
Work Began02-05-18
Work Completed
Time Computed12-20-17
Contract Working Days87
Addl Days Granted0
Working Days Charged20
Percent Time Used22
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0858-02-021
AREA WIDE PROTECTIVE, INC. (1.95)
FLASHER LIMITED (0.90)
LUZ LERMA CONSTRUCTION, INC. (34.59)
ENVIRONMENTAL SAFETY SERVICES, INC. (4.12)
Contract #09173019
Totals1428673.97182067.91407552.2128.5

CountyBRAZOS
HighwayVA
FromVAR. LOCATIONS IN BRAZOS, WALKER,
ToMADISON, LEON & FREESTONE COUNTIES
CSJ0917-00-042
Proj IDITS 2001(537)
Work TypeFY16 ITS DEVELOPMENT PROGRAM
 
0.001549299.80764782.4199.9
Work Order05-12-16
Work Began07-26-16
Work Completed
Time Computed06-11-16
Contract Working Days85
Addl Days Granted53
Working Days Charged100
Percent Time Used72
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-00-042
BUYER BARRICADES (2.30)
SPECIALTY DRILLING, LTD. (4.73)
Contract #04163239
Totals549299.800.00764782.4199.9

CountyMILAM
HighwayCR
FromON CR 398 - LOCAL CR 440
ToAT BRUSHY CREEK RELIEF
CSJ0917-12-080
Proj IDBR 2012(334)
Work TypeREPLACE AN EXISTING BRIDGE FACILITY
 
0.132447590.00438640.1598.0
Work Order07-11-17
Work Began08-21-17
Work Completed
Time Computed08-21-17
Contract Working Days82
Addl Days Granted0
Working Days Charged68
Percent Time Used82
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0917-12-080
VOGES DRILLING CO. (10.37)
ENVIRONMENTAL SAFETY SERVICES, INC. (3.11)
SAN-ANN-CO., INC. (0.67)
HOUSTON SAWING & DRILLING (0.61)
Contract #06173019
Totals447590.003373.33438640.1598.0

CountyGRIMES
HighwayCR
FromON CR 251 - LOCAL CR 190
ToAT GIBBONS CREEK
CSJ0917-17-065
Proj IDBR 2012(273)
Work TypeREPLACE EXISTING BRIDGE
 
0.192905681.32713416.2478.7
Work Order07-21-17
Work Began10-19-17
Work Completed
Time Computed10-19-17
Contract Working Days196
Addl Days Granted0
Working Days Charged80
Percent Time Used40
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-17-065
LONESTAR TRAFFIC SAFETY, LLC (0.69)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.48)
HEMPHILL WBE PILE DRIVING CO. (3.82)
DIIBS SPECIALISTS (0.34)
MESA ROD BUSTERS, INC. (0.50)
Contract #06173223
Totals905681.3211559.00713416.2478.7

CountyFREESTONE
HighwayPW
FromWITHIN FAIRFIELD STATE PARK IN THE
ToSPRINGFIELD AND POST OAK AREAS
CSJ0917-20-036
Proj IDC 917-20-36
Work TypeRECONSTRUCT ROADS AND CAMPSITES
 
1.0001862429.041422250.5676.9
Work Order03-15-17
Work Began05-01-17
Work Completed
Time Computed04-14-17
Contract Working Days175
Addl Days Granted0
Working Days Charged188
Percent Time Used107
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-20-036
AREA WIDE PROTECTIVE, INC. (0.44)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (3.22)
COLD CREEK CONSTRUCTION, LTD (0.66)
STRIPING TECHNOLOGY, L.P. (0.39)
MOORE PLUMBING REPAIR, LLC (0.89)
Contract #02173215
Totals1862429.04165300.271422250.5676.9

CountyWALKER
HighwayCR
FromON CR 667 - LOCAL BEAR CREEK ROAD
ToAT WHITES CREEK
CSJ0917-27-044
Proj IDBR 2016(317)
Work TypeGRADING, STRUCTURES AND BASE
 
0.104504029.64498058.8798.8
Work Order07-21-17
Work Began10-19-17
Work Completed
Time Computed10-19-17
Contract Working Days99
Addl Days Granted0
Working Days Charged60
Percent Time Used60
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-27-044
LONESTAR TRAFFIC SAFETY, LLC (0.60)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.95)
DIIBS SPECIALISTS (0.62)
BOWMAN ENGINEERING & CONSULTING, INC (0.56)
Contract #06173009
Totals504029.64108779.86498058.8798.8

CountyBRAZOS
HighwayCR
FromON CR 121 - LOCAL DILLY SHAW TAP RD
ToAT CEDAR CREEK
CSJ0917-29-120
Proj IDBR 2016(358)
Work TypeGRADING, STRUCTURE, BASE AND SURF
 
0.189772705.370.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days171
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PROJECT ALLIED RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0917-29-120
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183208
Totals772705.370.000.000.0

CountyBRAZOS
HighwayVA
FromON SH 308 FROM FM 1179
ToINLOW STREET
CSJ0917-29-129
Proj IDSTP 2017(099)TAPS
Work TypePEDESTRIAN AND BICYCLE IMPROVMENTS
 
1.1641803581.23351111.5419.4
Work Order09-25-17
Work Began12-14-17
Work Completed
Time Computed10-25-17
Contract Working Days140
Addl Days Granted0
Working Days Charged73
Percent Time Used52
Contractor(s)
LARRY YOUNG PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0917-29-129
TEXAS ALTERNATIVE GRASSER, INC. (0.37)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (29.08)
CEN TEX HYDROSEED, INC. (1.57)
D. I. J. CONSTRUCTION, INC. (1.84)
SPEEDY PAVING (1.67)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00)
AREA WIDE PROTECTIVE, INC. (0.27)
Contract #08173012
Totals1803581.23139260.46351111.5419.4

CountyGRIMES
HighwayFM 1696
FromFM 39
ToSH 90
CSJ1562-03-018
Proj IDSTP 2017(349)
Work TypeREHABILITATE EXISTING ROADWAY
 
9.1145527215.434365624.2178.9
Work Order04-04-17
Work Began05-03-17
Work Completed
Time Computed05-03-17
Contract Working Days215
Addl Days Granted0
Working Days Charged199
Percent Time Used92
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1562-03-018
ROADSAFE TRAFFIC SYSTEMS, INC. (1.38)
CEN TEX HYDROSEED, INC. (0.56)
COLD CREEK CONSTRUCTION, LTD (1.99)
ODUM SERVICES, L.P. (1.06)
J & M CONTRACTING COMPANY (4.44)
AREA WIDE PROTECTIVE, INC. (1.38)
A. L. HELMCAMP, INC. (0.59)
ANGEL BROTHERS ENTERPRISES, LTD. (9.94)
Contract #01173017
Totals5527215.43347390.104365624.2178.9

page 1 | page 2 | page 3