Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | BASTROP |
Highway | VA |
From | VARIOUS LOCATIONS IN BASTROP COUNTY |
To | . |
CSJ | 0914-18-120 |
Proj ID | F 2B23(129) |
Work Type | PEDESTRIAN, SIDEWALKS & CURB RAMPS |
|
| | 4210981.85 | | 1574334.37 | 37.3 |
Work Order | 09-06-23 |
Work Began | 11-06-23 |
Work Completed | |
Time Computed | 10-06-23 |
Contract Working Days | 279 |
Addl Days Granted | 0 |
Working Days Charged | 73 |
Percent Time Used | 26 |
Contractor(s) |
3LW CIVIL LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0914-18-120 LONE STAR PAVING COMPANY (0.00) ATLAS TRAFFIC MANAGEMENT SYSTEMS LLC (0.00) VACA UNDERGROUND UTILITIES INC (0.00) SAFETY COP, LLC (0.00) INTERSTATE BARRICADES & MARKINGS, INC. (0.00) TRP CONSTRUCTION GROUP, LLC (0.00) AWP SAFETY (0.00)
|
Contract # | 08233015 |
| Totals | 4210981.85 | 236007.17 | 1574334.37 | 37.3 |
|
County | GILLESPIE |
Highway | CR |
From | ON GELLERMAN LN @ PEDERNALES RIVER |
To | STR# 14-087-0-AA01-37-001 |
CSJ | 0914-19-033 |
Proj ID | BR 2B20(089) |
Work Type | BRIDGE REPLACEMENT |
|
| | 1025365.00 | | 113006.89 | 11.0 |
Work Order | 09-07-23 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 10-07-23 |
Contract Working Days | 110 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
DELGADO'S CONTRACTORS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0914-19-033 A K FUQUAY CONSTRUCTION (0.00) BARRICADES UNLIMITED (0.00) KING GEORGE TRAFFIC SOLUTIONS LLC (0.00)
|
Contract # | 08233258 |
| Totals | 1025365.00 | 0.00 | 113006.89 | 11.0 |
|
County | BURNET |
Highway | VA |
From | 1.0 MILES N OF HYLTON BRANCH |
To | 0.4 MILES N OF HYLTON BRANCH |
CSJ | 0914-24-025 |
Proj ID | C 914-24-25 |
Work Type | TEXAS PARK AND WILDLIFE |
|
| | 1637722.85 | | 1012594.70 | 61.8 |
Work Order | 06-07-23 |
Work Began | 09-05-23 |
Work Completed | |
Time Computed | 07-07-23 |
Contract Working Days | 68 |
Addl Days Granted | 30 |
Working Days Charged | 86 |
Percent Time Used | 87 |
Contractor(s) |
ENCINO LANDSCAPE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0914-24-025 D. I. J. CONSTRUCTION, INC. (0.00)
|
Contract # | 05233040 |
| Totals | 1637722.85 | 147291.80 | 1012594.70 | 61.8 |
|
County | HAYS |
Highway | CS |
From | ON COUNTY ROAD 266 (OLD BASTROP HWY) |
To | AT FM 621 |
CSJ | 0914-33-085 |
Proj ID | STP 2021(804)MM |
Work Type | INTERSECTION & OPERATIONAL IMPRV |
|
| | 980747.62 | | 671800.10 | 68.4 |
County | HAYS |
Highway | FM 621 |
From | 0.2 MI N OF OLD BASTROP HWY |
To | 0.2 MI S OF OLD BASTROP HWY |
CSJ | 0987-03-011 |
Proj ID | STP 2021(805)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 0.400 | 683695.24 | | 114597.75 | 16.7 |
County | HAYS |
Highway | FM 621 |
From | 0.1 MILES SE OF PICASSO DR. |
To | 0.2 MI SE OF OLD BASTROP HWY |
CSJ | 0987-03-014 |
Proj ID | STP 2022(343)MM |
Work Type | INTERSECTION & OPERATIONAL IMPRV |
|
| | 1535124.03 | | 747840.82 | 48.7 |
Work Order | 09-28-22 |
Work Began | 08-29-23 |
Work Completed | |
Time Computed | 03-27-23 |
Contract Working Days | 154 |
Addl Days Granted | 0 |
Working Days Charged | 90 |
Percent Time Used | 58 |
Contractor(s) |
JOE BLAND CONSTRUCTION, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0914-33-085 AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (11.45) ENVIRONMENTAL SAFETY SERVICES, INC. (3.01) AREA WIDE PROTECTIVE, INC. (0.89) TRP CONSTRUCTION GROUP, LLC (2.37) TEXAS MATERIALS GROUP, INC. (32.64) WOOLERY CUSTOM FENCE CO. (3.63)
|
Contract # | 08223220 |
| Totals | 3199566.89 | 189034.59 | 1534238.67 | 47.9 |
|
County | HAYS |
Highway | CR |
From | DRIPPING SPRINGS MIDDLE SCHOOL |
To | ROGER HANKS PARKWAY/BROKEN LANCE ROAD |
CSJ | 0914-33-088 |
Proj ID | STP 2022(313)TAPS |
Work Type | PEDESTRIAN, SIDEWALKS & CURB RAMPS |
|
| | 1277863.00 | | 656977.45 | 51.4 |
Work Order | 10-16-23 |
Work Began | 11-15-23 |
Work Completed | |
Time Computed | 11-15-23 |
Contract Working Days | 120 |
Addl Days Granted | 0 |
Working Days Charged | 77 |
Percent Time Used | 64 |
Contractor(s) |
D&S CONCRETE CONTRACTORS LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0914-33-088 THE LEVY COMPANY, INC. (8.97) AWP SAFETY (0.40) FIBERTEL, LLC (0.39)
|
Contract # | 09233025 |
| Totals | 1277863.00 | 126072.35 | 656977.45 | 51.4 |
|
County | HAYS |
Highway | VA |
From | ON RM 1826: LEWIS MOUNTAIN RD, ZYLE, |
To | APPALOOSA, GORMAN SPGS., TOWERING CEDAR |
CSJ | 0914-33-097 |
Proj ID | STP 2024(149)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 3606105.79 | | 3000.00 | 0.0 |
County | HAYS |
Highway | RM 1826 |
From | 0.1 MI E OF WOODLAND DR (E) |
To | 0.1 MI W OF SHELF ROCK RD |
CSJ | 1754-02-030 |
Proj ID | STP 2024(149)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 1109403.80 | | 48170.00 | 4.3 |
Work Order | 11-16-23 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 02-14-24 |
Contract Working Days | 256 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
AARON CONCRETE CONTRACTORS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0914-33-097 TRP CONSTRUCTION GROUP, LLC (2.75) TEXAS MATERIALS GROUP, INC. (39.44) ENVIRONMENTAL SAFETY SERVICES, INC. (10.10)
|
Contract # | 10233015 |
| Totals | 4715509.59 | 0.00 | 51170.00 | 1.0 |
|
County | WILLIAMSON |
Highway | FM 619 |
From | ON FM 619 AT DRAW |
To | STR # 14-246-0-0986-01-007 |
CSJ | 0986-01-046 |
Proj ID | BR 2024(598) |
Work Type | BRIDGE REPLACEMENT |
|
| | 1365940.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 02-21-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 52 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
AUSTIN ENGINEERING CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0986-01-046 ENVIRONMENTAL SAFETY SERVICES, INC. (10.12) A GREATER AUSTIN DEVELOPMENT COMPANY, LLC (29.56) LONE STAR PAVING COMPANY (9.17) BUYERS BARRICADES AUSTIN, LLC (3.16) TRP CONSTRUCTION GROUP, LLC (1.38)
|
Contract # | 01243234 |
| Totals | 1365940.00 | 0.00 | 0.00 | 0.0 |
|
County | CALDWELL |
Highway | FM 671 |
From | AT DRAW |
To | (STR 1060-01-004) |
CSJ | 1060-01-012 |
Proj ID | BR 2023(263) |
Work Type | BRIDGE REPLACEMENT |
|
| | 923086.71 | | 931626.84 | 99.9 |
County | CALDWELL |
Highway | FM 671 |
From | AT DRAW |
To | STR# 14-028-0-1060-01-003 |
CSJ | 1060-01-014 |
Proj ID | BR 2023(263) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.133 | 1165966.60 | | 773251.20 | 66.3 |
Work Order | 03-23-23 |
Work Began | 08-14-23 |
Work Completed | |
Time Computed | 04-22-23 |
Contract Working Days | 160 |
Addl Days Granted | 0 |
Working Days Charged | 151 |
Percent Time Used | 94 |
Contractor(s) |
CROSS PLUS CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 1060-01-012 FLEXICORE OF TEXAS, INC. (0.00) BATTEN DRILLING, INC. (0.00) ODUM SERVICES, LLC (0.00) BLACKSMITH VENTURES LLC (0.00) HOUSTON SAWING & DRILLING (0.00) INTERSTATE BARRICADES & MARKINGS, INC. (0.00)
|
Contract # | 02233244 |
| Totals | 2089053.31 | 330921.03 | 1704878.04 | 82.3 |
|
County | TRAVIS |
Highway | FM 969 |
From | FM 973 |
To | HUNTERS BEND RD. |
CSJ | 1186-01-091 |
Proj ID | PTF 2022(045) |
Work Type | WIDEN NON-FREEWAY |
|
| 1.868 | 8953609.72 | | 10355206.51 | 99.9 |
Work Order | 10-20-21 |
Work Began | 02-07-22 |
Work Completed | |
Time Computed | 11-19-21 |
Contract Working Days | 120 |
Addl Days Granted | 127 |
Working Days Charged | 241 |
Percent Time Used | 97 |
Contractor(s) |
DAN WILLIAMS COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1186-01-091 WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.61) VOGES DRILLING CO. (0.86) THE LEVY COMPANY, INC. (5.43) SCOTT DERR PAINTING CO, LLC (0.09) R K STEPHENS CONSTRUCTION, LLC (4.79) LONE STAR PAVING COMPANY (10.27) GK CONSTRUCTION, LLC (0.88) DIIBS SPECIALISTS, LLC (0.57) D. I. J. CONSTRUCTION, INC. (1.06) STRIPE-IT-UP (0.29) CALAME CONTRACTING, LLC (0.16)
|
Contract # | 09213221 |
| Totals | 8953609.72 | 0.00 | 10355206.51 | 99.9 |
|
County | HAYS |
Highway | RM 150 |
From | 2.098 MI NORTH OF RM 1826 |
To | S OF ELDER HILL ROAD |
CSJ | 1197-01-025 |
Proj ID | C 1197-1-25 |
Work Type | OVERLAY |
|
| | 1083995.67 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 02-02-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 32 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
CLARK CONSTRUCTION OF TEXAS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1197-01-025 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01243034 |
| Totals | 1083995.67 | 0.00 | 0.00 | 0.0 |
|
County | TRAVIS |
Highway | FM 973 |
From | WILCO/TRAVCO LINE |
To | S OF BRITA OLSON |
CSJ | 1200-02-035 |
Proj ID | C 1200-2-35 |
Work Type | OVERLAY |
|
| | 2000249.03 | | 1997771.00 | 99.8 |
Work Order | 04-12-23 |
Work Began | 09-21-23 |
Work Completed | |
Time Computed | 08-01-23 |
Contract Working Days | 39 |
Addl Days Granted | 0 |
Working Days Charged | 17 |
Percent Time Used | 43 |
Contractor(s) |
LONE STAR PAVING COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1200-02-035 TRP CONSTRUCTION GROUP, LLC (0.80) ENVIRONMENTAL SAFETY SERVICES, INC. (0.09) D. I. J. CONSTRUCTION, INC. (4.23) SAN ANTONIO SWEEPING SERVICES, INC. (0.49) STRIPE IT UP, LLC (0.49) TEXAS SITE SERVICES, LLC (0.49)
|
Contract # | 03233224 |
| Totals | 2000249.03 | 0.00 | 1997771.00 | 99.8 |
|
County | TRAVIS |
Highway | FM 973 |
From | 0.069 MI. NE OF FM 969 |
To | 0.1 MI. N OF THYONE DR |
CSJ | 1200-03-060 |
Proj ID | STP 2022(819)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 3.313 | 22834260.66 | | 8528189.13 | 37.3 |
Work Order | 04-12-23 |
Work Began | 10-09-23 |
Work Completed | |
Time Computed | 10-09-23 |
Contract Working Days | 380 |
Addl Days Granted | 0 |
Working Days Charged | 80 |
Percent Time Used | 21 |
Contractor(s) |
DAN WILLIAMS COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1200-03-060 ENVIRONMENTAL SAFETY SERVICES, INC. (3.25) LONE STAR PAVING COMPANY (34.33) THE LEVY COMPANY, INC. (0.20) TRP CONSTRUCTION GROUP, LLC (1.28) R K STEPHENS CONSTRUCTION, LLC (2.80) STRIPE IT UP, LLC (0.30)
|
Contract # | 03233206 |
| Totals | 22834260.66 | 433755.72 | 8528189.13 | 37.3 |
|
County | WILLIAMSON |
Highway | FM 1466 |
From | AT LITTLE DRY BRUSHY CREEK |
To | STR# 14-246-0-1200-04-007 |
CSJ | 1200-04-016 |
Proj ID | BR 2024(026) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.012 | 1755319.54 | | 0.00 | 0.0 |
County | WILLIAMSON |
Highway | FM 1466 |
From | 0.52 MILES EAST OF SH 95 |
To | STR# 14-246-0-1200-04-005 |
CSJ | 1200-04-017 |
Proj ID | BR 2024(026) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.066 | 2874063.76 | | 0.00 | 0.0 |
County | WILLIAMSON |
Highway | FM 1466 |
From | SH 95 |
To | FM 619 |
CSJ | 1200-04-020 |
Proj ID | F 2024(029) |
Work Type | SEAL COAT |
|
| | 916851.70 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 12-06-23 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 154 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
JOE BLAND CONSTRUCTION, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 1200-04-016 D. I. J. CONSTRUCTION, INC. (3.17) LONE STAR PAVING COMPANY (26.49) TEXAS HIGHWAY WALLS (4.95) TRP CONSTRUCTION GROUP, LLC (6.16) WYLIE DRILLING & DRAINAGE, INC. (1.59) BUYERS BARRICADES AUSTIN, LLC (1.29)
|
Contract # | 09233223 |
| Totals | 5546235.00 | 0.00 | 0.00 | 0.0 |
|
County | TRAVIS |
Highway | FM 1100 |
From | US 290 |
To | BASTROP COUNTY LINE |
CSJ | 1234-01-012 |
Proj ID | C 1234-1-12 |
Work Type | OVERLAY |
|
| 6.332 | 2843646.40 | | 745887.56 | 26.2 |
County | TRAVIS |
Highway | FM 1100 |
From | ABRAHAMSON RD |
To | GIESE LN. |
CSJ | 1234-01-013 |
Proj ID | STP 2023(881)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 0.814 | 2109543.80 | | 224638.00 | 10.6 |
Work Order | 07-19-23 |
Work Began | 02-19-24 |
Work Completed | |
Time Computed | 08-18-23 |
Contract Working Days | 48 |
Addl Days Granted | 0 |
Working Days Charged | 21 |
Percent Time Used | 43 |
Contractor(s) |
AARON CONCRETE CONTRACTORS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 1234-01-012 TRP CONSTRUCTION GROUP, LLC (0.66) TEXAS MATERIALS GROUP, INC. (51.19) ROADWAY SPECIALTIES, INC. (1.41) MURRAY CONSTRUCTION (0.21) ENVIRONMENTAL SAFETY SERVICES, INC. (1.43) D. I. J. CONSTRUCTION, INC. (5.22) CAVE TRUCKING, LLC (4.59) GBC GENERAL BARRICADE COMPANY LLC (0.04)
|
Contract # | 06233016 |
| Totals | 4953190.20 | 927525.56 | 970525.56 | 19.5 |
|
County | TRAVIS |
Highway | RM 1431 |
From | 0.103 MI E OF OLD FM 1431 (E) |
To | E REED PARK RD |
CSJ | 1378-01-051 |
Proj ID | STP 2023(989)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 5205668.65 | | 2013241.26 | 38.6 |
Work Order | 07-26-23 |
Work Began | 11-15-23 |
Work Completed | |
Time Computed | 11-15-23 |
Contract Working Days | 232 |
Addl Days Granted | 0 |
Working Days Charged | 57 |
Percent Time Used | 24 |
Contractor(s) |
AUSTIN UNDERGROUND INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 1378-01-051 D. I. J. CONSTRUCTION, INC. (1.30) ENVIRONMENTAL SAFETY SERVICES, INC. (1.52) LONE STAR PAVING COMPANY (24.62) ROADWAY SPECIALTIES, INC. (2.26) STRIPE IT UP, LLC (0.10) AREA WIDE PROTECTIVE, INC. (0.26) TEXAS TRAFFIC AND BARRICADE, LLC (0.39)
|
Contract # | 06233619 |
| Totals | 5205668.65 | 752788.75 | 2013241.26 | 38.6 |
|
County | BURNET |
Highway | RM 1431 |
From | HAMILTON CREEK |
To | TRAVIS COUNTY LINE |
CSJ | 1378-03-039 |
Proj ID | F 2024(362) |
Work Type | SEAL COAT |
|
| | 4898356.85 | | 2476514.76 | 50.5 |
County | BURNET |
Highway | FM 1980 |
From | RM 1431 |
To | END OF STATE MAINTENANCE |
CSJ | 3413-01-007 |
Proj ID | C 3413-1-7 |
Work Type | SEAL COAT |
|
| | 1376701.28 | | 459509.27 | 33.3 |
Work Order | 12-13-23 |
Work Began | 02-12-24 |
Work Completed | |
Time Computed | 02-12-24 |
Contract Working Days | 120 |
Addl Days Granted | 0 |
Working Days Charged | 23 |
Percent Time Used | 19 |
Contractor(s) |
LONE STAR PAVING COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1378-03-039 D. I. J. CONSTRUCTION, INC. (0.00) TRP CONSTRUCTION GROUP, LLC (0.00)
|
Contract # | 11233207 |
| Totals | 6275058.13 | 1007120.73 | 2936024.03 | 46.7 |
|
County | BURNET |
Highway | RM 1431 |
From | LLANO C/L |
To | RM 1980 |
CSJ | 1378-04-056 |
Proj ID | F 2024(500) |
Work Type | OVERLAY |
|
| | 7574977.47 | | 531716.03 | 7.0 |
Work Order | 01-04-24 |
Work Began | 03-18-24 |
Work Completed | |
Time Computed | 03-18-24 |
Contract Working Days | 145 |
Addl Days Granted | 0 |
Working Days Charged | 5 |
Percent Time Used | 3 |
Contractor(s) |
LONE STAR PAVING COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1378-04-056 TRP CONSTRUCTION GROUP, LLC (0.00) D. I. J. CONSTRUCTION, INC. (0.00)
|
Contract # | 12233011 |
| Totals | 7574977.47 | 531716.03 | 531716.03 | 7.0 |
|
County | BLANCO |
Highway | RM 1623 |
From | 1.801 MI EAST OF RM 1888 |
To | US 281 |
CSJ | 1534-01-020 |
Proj ID | F 2023(883) |
Work Type | SEAL COAT |
|
| | 976312.12 | | 657874.95 | 67.3 |
Work Order | 07-19-23 |
Work Began | 09-05-23 |
Work Completed | |
Time Computed | 08-01-23 |
Contract Working Days | 25 |
Addl Days Granted | 0 |
Working Days Charged | 8 |
Percent Time Used | 32 |
Contractor(s) |
CLARK CONSTRUCTION OF TEXAS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1534-01-020 SAN ANTONIO CONCEPTS CONSTRUCTION, LLC (0.17) INTERSTATE BARRICADES & MARKINGS, INC. (12.94) MPB, INC. (0.00)
|
Contract # | 06233033 |
| Totals | 976312.12 | 0.00 | 657874.95 | 67.3 |
|
County | MASON |
Highway | RM 1871 |
From | AT LLANO RIVER |
To | STR# 14-157-0-1753-01-001 |
CSJ | 1753-01-017 |
Proj ID | BR 2021(807) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.357 | 4158807.04 | | 3521290.46 | 89.9 |
County | MASON |
Highway | RM 1871 |
From | AT LLANO RIVER |
To | STR 1753-1-1 |
CSJ | 1753-01-020 |
Proj ID | BR 2021(807) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.005 | 20000.00 | | 20000.00 | 99.9 |
Work Order | 09-29-21 |
Work Began | 01-10-22 |
Work Completed | |
Time Computed | 10-29-21 |
Contract Working Days | 182 |
Addl Days Granted | 23 |
Working Days Charged | 431 |
Percent Time Used | 210 |
Contractor(s) |
RELMCO, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1753-01-017 DIIBS SPECIALISTS, LLC (3.10) TORO BRAVO CONSTRUCTION, LLC (0.72) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.36) HB FARMER FOUNDATION, LLC (7.89) FLASHER EQUIPMENT COMPANY (0.00)
|
Contract # | 08213233 |
| Totals | 4178807.04 | 3854.60 | 3541290.46 | 89.9 |
|
County | WILLIAMSON |
Highway | RM 1869 |
From | HILL TOP |
To | 1.0 MI E OF CR 285 |
CSJ | 1755-01-021 |
Proj ID | STP 2023(737)VRU |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 3631474.28 | | 2171477.04 | 59.7 |
County | WILLIAMSON |
Highway | RM 1869 |
From | HILL TOP |
To | 1.0 MILE EAST OF CR 285 |
CSJ | 1755-01-024 |
Proj ID | C 1755-1-24 |
Work Type | NEW LOCATION NON-FREEWAY |
|
| | 222125.00 | | 207060.00 | 93.2 |
Work Order | 06-21-23 |
Work Began | 09-26-23 |
Work Completed | |
Time Computed | 07-21-23 |
Contract Working Days | 176 |
Addl Days Granted | 0 |
Working Days Charged | 89 |
Percent Time Used | 50 |
Contractor(s) |
AUSTIN UNDERGROUND INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 1755-01-021 AWP SAFETY (0.36) D. I. J. CONSTRUCTION, INC. (1.93) ENVIRONMENTAL SAFETY SERVICES, INC. (4.18) LONE STAR PAVING COMPANY (28.99) TRP CONSTRUCTION GROUP, LLC (0.25) STRIPE IT UP, LLC (0.15)
|
Contract # | 05233024 |
| Totals | 3853599.28 | 406786.03 | 2378537.04 | 61.7 |
|