Monthly State Let Construction Report For Austin District As Of Apr 12, 2024 Page 6 Of 7

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBASTROP
HighwayVA
FromVARIOUS LOCATIONS IN BASTROP COUNTY
To.
CSJ0914-18-120
Proj IDF 2B23(129)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
4210981.851574334.3737.3
Work Order09-06-23
Work Began11-06-23
Work Completed
Time Computed10-06-23
Contract Working Days279
Addl Days Granted0
Working Days Charged73
Percent Time Used26
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-18-120
LONE STAR PAVING COMPANY (0.00)
ATLAS TRAFFIC MANAGEMENT SYSTEMS LLC (0.00)
VACA UNDERGROUND UTILITIES INC (0.00)
SAFETY COP, LLC (0.00)
INTERSTATE BARRICADES & MARKINGS, INC. (0.00)
TRP CONSTRUCTION GROUP, LLC (0.00)
AWP SAFETY (0.00)
Contract #08233015
Totals4210981.85236007.171574334.3737.3

CountyGILLESPIE
HighwayCR
FromON GELLERMAN LN @ PEDERNALES RIVER
ToSTR# 14-087-0-AA01-37-001
CSJ0914-19-033
Proj IDBR 2B20(089)
Work TypeBRIDGE REPLACEMENT
 
1025365.00113006.8911.0
Work Order09-07-23
Work Began00-00-00
Work Completed
Time Computed10-07-23
Contract Working Days110
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DELGADO'S CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-19-033
A K FUQUAY CONSTRUCTION (0.00)
BARRICADES UNLIMITED (0.00)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.00)
Contract #08233258
Totals1025365.000.00113006.8911.0

CountyBURNET
HighwayVA
From1.0 MILES N OF HYLTON BRANCH
To0.4 MILES N OF HYLTON BRANCH
CSJ0914-24-025
Proj IDC 914-24-25
Work TypeTEXAS PARK AND WILDLIFE
 
1637722.851012594.7061.8
Work Order06-07-23
Work Began09-05-23
Work Completed
Time Computed07-07-23
Contract Working Days68
Addl Days Granted30
Working Days Charged86
Percent Time Used87
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-24-025
D. I. J. CONSTRUCTION, INC. (0.00)
Contract #05233040
Totals1637722.85147291.801012594.7061.8

CountyHAYS
HighwayCS
FromON COUNTY ROAD 266 (OLD BASTROP HWY)
ToAT FM 621
CSJ0914-33-085
Proj IDSTP 2021(804)MM
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
980747.62671800.1068.4
CountyHAYS
HighwayFM 621
From0.2 MI N OF OLD BASTROP HWY
To0.2 MI S OF OLD BASTROP HWY
CSJ0987-03-011
Proj IDSTP 2021(805)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.400683695.24114597.7516.7
CountyHAYS
HighwayFM 621
From0.1 MILES SE OF PICASSO DR.
To0.2 MI SE OF OLD BASTROP HWY
CSJ0987-03-014
Proj IDSTP 2022(343)MM
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
1535124.03747840.8248.7
Work Order09-28-22
Work Began08-29-23
Work Completed
Time Computed03-27-23
Contract Working Days154
Addl Days Granted0
Working Days Charged90
Percent Time Used58
Contractor(s)
JOE BLAND CONSTRUCTION, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0914-33-085
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (11.45)
ENVIRONMENTAL SAFETY SERVICES, INC. (3.01)
AREA WIDE PROTECTIVE, INC. (0.89)
TRP CONSTRUCTION GROUP, LLC (2.37)
TEXAS MATERIALS GROUP, INC. (32.64)
WOOLERY CUSTOM FENCE CO. (3.63)
Contract #08223220
Totals3199566.89189034.591534238.6747.9

CountyHAYS
HighwayCR
FromDRIPPING SPRINGS MIDDLE SCHOOL
ToROGER HANKS PARKWAY/BROKEN LANCE ROAD
CSJ0914-33-088
Proj IDSTP 2022(313)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1277863.00656977.4551.4
Work Order10-16-23
Work Began11-15-23
Work Completed
Time Computed11-15-23
Contract Working Days120
Addl Days Granted0
Working Days Charged77
Percent Time Used64
Contractor(s)
D&S CONCRETE CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-33-088
THE LEVY COMPANY, INC. (8.97)
AWP SAFETY (0.40)
FIBERTEL, LLC (0.39)
Contract #09233025
Totals1277863.00126072.35656977.4551.4

CountyHAYS
HighwayVA
FromON RM 1826: LEWIS MOUNTAIN RD, ZYLE,
ToAPPALOOSA, GORMAN SPGS., TOWERING CEDAR
CSJ0914-33-097
Proj IDSTP 2024(149)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3606105.793000.000.0
CountyHAYS
HighwayRM 1826
From0.1 MI E OF WOODLAND DR (E)
To0.1 MI W OF SHELF ROCK RD
CSJ1754-02-030
Proj IDSTP 2024(149)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1109403.8048170.004.3
Work Order11-16-23
Work Began00-00-00
Work Completed
Time Computed02-14-24
Contract Working Days256
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AARON CONCRETE CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-33-097
TRP CONSTRUCTION GROUP, LLC (2.75)
TEXAS MATERIALS GROUP, INC. (39.44)
ENVIRONMENTAL SAFETY SERVICES, INC. (10.10)
Contract #10233015
Totals4715509.590.0051170.001.0

CountyWILLIAMSON
HighwayFM 619
FromON FM 619 AT DRAW
ToSTR # 14-246-0-0986-01-007
CSJ0986-01-046
Proj IDBR 2024(598)
Work TypeBRIDGE REPLACEMENT
 
1365940.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-21-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days52
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN ENGINEERING CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0986-01-046
ENVIRONMENTAL SAFETY SERVICES, INC. (10.12)
A GREATER AUSTIN DEVELOPMENT COMPANY, LLC (29.56)
LONE STAR PAVING COMPANY (9.17)
BUYERS BARRICADES AUSTIN, LLC (3.16)
TRP CONSTRUCTION GROUP, LLC (1.38)
Contract #01243234
Totals1365940.000.000.000.0

CountyCALDWELL
HighwayFM 671
FromAT DRAW
To(STR 1060-01-004)
CSJ1060-01-012
Proj IDBR 2023(263)
Work TypeBRIDGE REPLACEMENT
 
923086.71931626.8499.9
CountyCALDWELL
HighwayFM 671
FromAT DRAW
ToSTR# 14-028-0-1060-01-003
CSJ1060-01-014
Proj IDBR 2023(263)
Work TypeBRIDGE REPLACEMENT
 
0.1331165966.60773251.2066.3
Work Order03-23-23
Work Began08-14-23
Work Completed
Time Computed04-22-23
Contract Working Days160
Addl Days Granted0
Working Days Charged151
Percent Time Used94
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1060-01-012
FLEXICORE OF TEXAS, INC. (0.00)
BATTEN DRILLING, INC. (0.00)
ODUM SERVICES, LLC (0.00)
BLACKSMITH VENTURES LLC (0.00)
HOUSTON SAWING & DRILLING (0.00)
INTERSTATE BARRICADES & MARKINGS, INC. (0.00)
Contract #02233244
Totals2089053.31330921.031704878.0482.3

CountyTRAVIS
HighwayFM 969
FromFM 973
ToHUNTERS BEND RD.
CSJ1186-01-091
Proj IDPTF 2022(045)
Work TypeWIDEN NON-FREEWAY
 
1.8688953609.7210355206.5199.9
Work Order10-20-21
Work Began02-07-22
Work Completed
Time Computed11-19-21
Contract Working Days120
Addl Days Granted127
Working Days Charged241
Percent Time Used97
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1186-01-091
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.61)
VOGES DRILLING CO. (0.86)
THE LEVY COMPANY, INC. (5.43)
SCOTT DERR PAINTING CO, LLC (0.09)
R K STEPHENS CONSTRUCTION, LLC (4.79)
LONE STAR PAVING COMPANY (10.27)
GK CONSTRUCTION, LLC (0.88)
DIIBS SPECIALISTS, LLC (0.57)
D. I. J. CONSTRUCTION, INC. (1.06)
STRIPE-IT-UP (0.29)
CALAME CONTRACTING, LLC (0.16)
Contract #09213221
Totals8953609.720.0010355206.5199.9

CountyHAYS
HighwayRM 150
From2.098 MI NORTH OF RM 1826
ToS OF ELDER HILL ROAD
CSJ1197-01-025
Proj IDC 1197-1-25
Work TypeOVERLAY
 
1083995.670.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-02-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days32
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1197-01-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01243034
Totals1083995.670.000.000.0

CountyTRAVIS
HighwayFM 973
FromWILCO/TRAVCO LINE
ToS OF BRITA OLSON
CSJ1200-02-035
Proj IDC 1200-2-35
Work TypeOVERLAY
 
2000249.031997771.0099.8
Work Order04-12-23
Work Began09-21-23
Work Completed
Time Computed08-01-23
Contract Working Days39
Addl Days Granted0
Working Days Charged17
Percent Time Used43
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1200-02-035
TRP CONSTRUCTION GROUP, LLC (0.80)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.09)
D. I. J. CONSTRUCTION, INC. (4.23)
SAN ANTONIO SWEEPING SERVICES, INC. (0.49)
STRIPE IT UP, LLC (0.49)
TEXAS SITE SERVICES, LLC (0.49)
Contract #03233224
Totals2000249.030.001997771.0099.8

CountyTRAVIS
HighwayFM 973
From0.069 MI. NE OF FM 969
To0.1 MI. N OF THYONE DR
CSJ1200-03-060
Proj IDSTP 2022(819)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.31322834260.668528189.1337.3
Work Order04-12-23
Work Began10-09-23
Work Completed
Time Computed10-09-23
Contract Working Days380
Addl Days Granted0
Working Days Charged80
Percent Time Used21
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1200-03-060
ENVIRONMENTAL SAFETY SERVICES, INC. (3.25)
LONE STAR PAVING COMPANY (34.33)
THE LEVY COMPANY, INC. (0.20)
TRP CONSTRUCTION GROUP, LLC (1.28)
R K STEPHENS CONSTRUCTION, LLC (2.80)
STRIPE IT UP, LLC (0.30)
Contract #03233206
Totals22834260.66433755.728528189.1337.3

CountyWILLIAMSON
HighwayFM 1466
FromAT LITTLE DRY BRUSHY CREEK
ToSTR# 14-246-0-1200-04-007
CSJ1200-04-016
Proj IDBR 2024(026)
Work TypeBRIDGE REPLACEMENT
 
0.0121755319.540.000.0
CountyWILLIAMSON
HighwayFM 1466
From0.52 MILES EAST OF SH 95
ToSTR# 14-246-0-1200-04-005
CSJ1200-04-017
Proj IDBR 2024(026)
Work TypeBRIDGE REPLACEMENT
 
0.0662874063.760.000.0
CountyWILLIAMSON
HighwayFM 1466
FromSH 95
ToFM 619
CSJ1200-04-020
Proj IDF 2024(029)
Work TypeSEAL COAT
 
916851.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-06-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days154
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JOE BLAND CONSTRUCTION, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1200-04-016
D. I. J. CONSTRUCTION, INC. (3.17)
LONE STAR PAVING COMPANY (26.49)
TEXAS HIGHWAY WALLS (4.95)
TRP CONSTRUCTION GROUP, LLC (6.16)
WYLIE DRILLING & DRAINAGE, INC. (1.59)
BUYERS BARRICADES AUSTIN, LLC (1.29)
Contract #09233223
Totals5546235.000.000.000.0

CountyTRAVIS
HighwayFM 1100
FromUS 290
ToBASTROP COUNTY LINE
CSJ1234-01-012
Proj IDC 1234-1-12
Work TypeOVERLAY
 
6.3322843646.40745887.5626.2
CountyTRAVIS
HighwayFM 1100
FromABRAHAMSON RD
ToGIESE LN.
CSJ1234-01-013
Proj IDSTP 2023(881)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.8142109543.80224638.0010.6
Work Order07-19-23
Work Began02-19-24
Work Completed
Time Computed08-18-23
Contract Working Days48
Addl Days Granted0
Working Days Charged21
Percent Time Used43
Contractor(s)
AARON CONCRETE CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1234-01-012
TRP CONSTRUCTION GROUP, LLC (0.66)
TEXAS MATERIALS GROUP, INC. (51.19)
ROADWAY SPECIALTIES, INC. (1.41)
MURRAY CONSTRUCTION (0.21)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.43)
D. I. J. CONSTRUCTION, INC. (5.22)
CAVE TRUCKING, LLC (4.59)
GBC GENERAL BARRICADE COMPANY LLC (0.04)
Contract #06233016
Totals4953190.20927525.56970525.5619.5

CountyTRAVIS
HighwayRM 1431
From0.103 MI E OF OLD FM 1431 (E)
ToE REED PARK RD
CSJ1378-01-051
Proj IDSTP 2023(989)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5205668.652013241.2638.6
Work Order07-26-23
Work Began11-15-23
Work Completed
Time Computed11-15-23
Contract Working Days232
Addl Days Granted0
Working Days Charged57
Percent Time Used24
Contractor(s)
AUSTIN UNDERGROUND INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1378-01-051
D. I. J. CONSTRUCTION, INC. (1.30)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.52)
LONE STAR PAVING COMPANY (24.62)
ROADWAY SPECIALTIES, INC. (2.26)
STRIPE IT UP, LLC (0.10)
AREA WIDE PROTECTIVE, INC. (0.26)
TEXAS TRAFFIC AND BARRICADE, LLC (0.39)
Contract #06233619
Totals5205668.65752788.752013241.2638.6

CountyBURNET
HighwayRM 1431
FromHAMILTON CREEK
ToTRAVIS COUNTY LINE
CSJ1378-03-039
Proj IDF 2024(362)
Work TypeSEAL COAT
 
4898356.852476514.7650.5
CountyBURNET
HighwayFM 1980
FromRM 1431
ToEND OF STATE MAINTENANCE
CSJ3413-01-007
Proj IDC 3413-1-7
Work TypeSEAL COAT
 
1376701.28459509.2733.3
Work Order12-13-23
Work Began02-12-24
Work Completed
Time Computed02-12-24
Contract Working Days120
Addl Days Granted0
Working Days Charged23
Percent Time Used19
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1378-03-039
D. I. J. CONSTRUCTION, INC. (0.00)
TRP CONSTRUCTION GROUP, LLC (0.00)
Contract #11233207
Totals6275058.131007120.732936024.0346.7

CountyBURNET
HighwayRM 1431
FromLLANO C/L
ToRM 1980
CSJ1378-04-056
Proj IDF 2024(500)
Work TypeOVERLAY
 
7574977.47531716.037.0
Work Order01-04-24
Work Began03-18-24
Work Completed
Time Computed03-18-24
Contract Working Days145
Addl Days Granted0
Working Days Charged5
Percent Time Used3
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1378-04-056
TRP CONSTRUCTION GROUP, LLC (0.00)
D. I. J. CONSTRUCTION, INC. (0.00)
Contract #12233011
Totals7574977.47531716.03531716.037.0

CountyBLANCO
HighwayRM 1623
From1.801 MI EAST OF RM 1888
ToUS 281
CSJ1534-01-020
Proj IDF 2023(883)
Work TypeSEAL COAT
 
976312.12657874.9567.3
Work Order07-19-23
Work Began09-05-23
Work Completed
Time Computed08-01-23
Contract Working Days25
Addl Days Granted0
Working Days Charged8
Percent Time Used32
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1534-01-020
SAN ANTONIO CONCEPTS CONSTRUCTION, LLC (0.17)
INTERSTATE BARRICADES & MARKINGS, INC. (12.94)
MPB, INC. (0.00)
Contract #06233033
Totals976312.120.00657874.9567.3

CountyMASON
HighwayRM 1871
FromAT LLANO RIVER
ToSTR# 14-157-0-1753-01-001
CSJ1753-01-017
Proj IDBR 2021(807)
Work TypeBRIDGE REPLACEMENT
 
0.3574158807.043521290.4689.9
CountyMASON
HighwayRM 1871
FromAT LLANO RIVER
ToSTR 1753-1-1
CSJ1753-01-020
Proj IDBR 2021(807)
Work TypeBRIDGE REPLACEMENT
 
0.00520000.0020000.0099.9
Work Order09-29-21
Work Began01-10-22
Work Completed
Time Computed10-29-21
Contract Working Days182
Addl Days Granted23
Working Days Charged431
Percent Time Used210
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1753-01-017
DIIBS SPECIALISTS, LLC (3.10)
TORO BRAVO CONSTRUCTION, LLC (0.72)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.36)
HB FARMER FOUNDATION, LLC (7.89)
FLASHER EQUIPMENT COMPANY (0.00)
Contract #08213233
Totals4178807.043854.603541290.4689.9

CountyWILLIAMSON
HighwayRM 1869
FromHILL TOP
To1.0 MI E OF CR 285
CSJ1755-01-021
Proj IDSTP 2023(737)VRU
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3631474.282171477.0459.7
CountyWILLIAMSON
HighwayRM 1869
FromHILL TOP
To1.0 MILE EAST OF CR 285
CSJ1755-01-024
Proj IDC 1755-1-24
Work TypeNEW LOCATION NON-FREEWAY
 
222125.00207060.0093.2
Work Order06-21-23
Work Began09-26-23
Work Completed
Time Computed07-21-23
Contract Working Days176
Addl Days Granted0
Working Days Charged89
Percent Time Used50
Contractor(s)
AUSTIN UNDERGROUND INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1755-01-021
AWP SAFETY (0.36)
D. I. J. CONSTRUCTION, INC. (1.93)
ENVIRONMENTAL SAFETY SERVICES, INC. (4.18)
LONE STAR PAVING COMPANY (28.99)
TRP CONSTRUCTION GROUP, LLC (0.25)
STRIPE IT UP, LLC (0.15)
Contract #05233024
Totals3853599.28406786.032378537.0461.7

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7