Monthly State Let Construction Report For Austin District As Of Apr 12, 2024 Page 5 Of 7

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTRAVIS
HighwayVA
FromDISTRICTWIDE
To.
CSJ0914-00-459
Proj IDSTP 2024(597)VRU
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1147054.8126145.272.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-02-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days168
Addl Days Granted0
Working Days Charged5
Percent Time Used2
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-459
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01243235
Totals1147054.8118460.0026145.272.2

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS IN TRAVIS COUNTY
ToVARIOUS LOCATIONS IN TRAVIS COUNTY
CSJ0914-00-468
Proj IDC 914-00-468
Work TypeTRAFFIC CONTROL DEVICES
 
2342775.601736316.7674.1
Work Order10-06-22
Work Began07-10-23
Work Completed
Time Computed06-26-23
Contract Working Days300
Addl Days Granted0
Working Days Charged73
Percent Time Used24
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-468
D. I. J. CONSTRUCTION, INC. (1.49)
Contract #09223214
Totals2342775.6020256.001736316.7674.1

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-469
Proj IDC 914-00-469
Work TypeTRAFFIC CONTROL DEVICES
 
827090.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days300
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ELECNOR BELCO ELECTRIC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-469
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243035
Totals827090.000.000.000.0

CountyTRAVIS
HighwayVA
FromLEE, BASTROP, & CALDWELL CO.
To.
CSJ0914-00-470
Proj IDC 914-00-470
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
648422.03311217.1547.9
Work Order08-17-23
Work Began01-30-24
Work Completed
Time Computed09-16-23
Contract Working Days28
Addl Days Granted0
Working Days Charged25
Percent Time Used89
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-470
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01233231
Totals648422.03141552.91311217.1547.9

CountyTRAVIS
HighwayVA
FromFY 24 SITE SPECIFIC BR REPAIRS
ToIN MASON, LLANO AND BURNET COUNTIES
CSJ0914-00-471
Proj IDC 914-00-471
Work TypeBRIDGE MAINTENANCE
 
549976.13978435.7099.9
Work Order04-26-23
Work Began10-23-23
Work Completed
Time Computed05-26-23
Contract Working Days86
Addl Days Granted40
Working Days Charged63
Percent Time Used50
Contractor(s)
AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-471
MACIAS SPECIALTY CONTRACTING LLC (0.00)
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (0.00)
D. I. J. CONSTRUCTION, INC. (0.00)
BUYERS BARRICADES AUSTIN, LLC (0.00)
Contract #03233039
Totals549976.1395492.74978435.7099.9

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS IN
ToBASTROP & LEE COUNTY
CSJ0914-00-476
Proj IDC 914-00-476
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
1519370.001483525.7497.6
Work Order05-08-23
Work Began09-18-23
Work Completed
Time Computed06-07-23
Contract Working Days87
Addl Days Granted55
Working Days Charged94
Percent Time Used66
Contractor(s)
TIGHT LINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-476
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04233028
Totals1519370.00243653.251483525.7497.6

CountyTRAVIS
HighwayVA
FromDISTRICTWIDE
To.
CSJ0914-00-479
Proj IDC 914-00-479
Work TypeTRAFFIC CONTROL DEVICES
 
2491969.221551831.5862.2
Work Order07-12-23
Work Began00-00-00
Work Completed
Time Computed11-09-23
Contract Working Days300
Addl Days Granted0
Working Days Charged41
Percent Time Used13
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-479
FIBERTEL, LLC (6.00)
KING GEORGE TRAFFIC SOLUTIONS LLC (3.54)
SOUTH TEXAS TRAFFIC ALLIANCE INC. (0.00)
LLANO AUGER SERVICE (0.00)
STOCKLIN CO. (0.00)
Contract #06233227
Totals2491969.22231604.541551831.5862.2

CountyTRAVIS
HighwayVA
FromLOCATIONS DISTRICTWIDE
To.
CSJ0914-00-504
Proj IDC 914-00-504
Work TypeTRAFFIC CONTROL DEVICES
 
2626391.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-07-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days300
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-504
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243025
Totals2626391.000.000.000.0

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-512
Proj IDC 914-00-512
Work TypeOVERLAY
 
7676625.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-21-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-512
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243022
Totals7676625.000.000.000.0

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-524
Proj IDF 2024(758)
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
1284795.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-14-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-524
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243225
Totals1284795.000.000.000.0

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE ON LP 1
To.
CSJ0914-00-525
Proj IDF 2024(759)
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
1649750.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-05-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HAZMAT INTERNATIONAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-525
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243030
Totals1649750.000.000.000.0

CountyTRAVIS
HighwayVA
FromAT TPWD STATE HEADQUARTERS COMPLEX
To.
CSJ0914-04-288
Proj IDC 914-4-288
Work TypeTEXAS PARK AND WILDLIFE
 
0.001971504.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-25-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days16
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-288
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09233229
Totals971504.000.000.000.0

CountyTRAVIS
HighwayCS
FromAT METROPOLIS
To.
CSJ0914-04-331
Proj IDSTP 2024(146)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
290491.9443496.2014.9
CountyTRAVIS
HighwayCS
FromAT BLUFF SPRINGS
To.
CSJ0914-04-333
Proj IDSTP 2024(146)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
260178.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-27-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days95
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-331
KING GEORGE TRAFFIC SOLUTIONS LLC (0.00)
SOUTH TEXAS TRAFFIC ALLIANCE INC. (0.00)
FIBERTEL, LLC (0.00)
Contract #10233024
Totals550669.9443496.2043496.207.8

CountyWILLIAMSON
HighwayCR
FromON CR 126 AT MILEHAM BRIDGE
ToSTR# 14-246-0-AA04-87-001
CSJ0914-05-137
Proj IDBR 2020(730)
Work TypeBRIDGE MAINTENANCE
 
0.100125524.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-26-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days37
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ALBECO CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-05-137
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243043
Totals125524.000.000.000.0

CountyWILLIAMSON
HighwayCR
FromCR 118 AT COTTONWOOD CREEK
To.
CSJ0914-05-204
Proj IDBR 2020(733)
Work TypeBRIDGE REPLACEMENT
 
1118680.70424315.5237.9
CountyWILLIAMSON
HighwayCR
From119' E OF CR 119 TO 1,523' E AND;
To1,773' E OF CR 100 TO 2,839' E
CSJ0914-05-220
Proj IDCC 914-5-220
Work TypeNEW LOCATION NON-FREEWAY
 
1459538.29317269.7021.7
Work Order08-03-23
Work Began03-04-24
Work Completed
Time Computed11-01-23
Contract Working Days244
Addl Days Granted0
Working Days Charged11
Percent Time Used4
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-05-204
DIIBS SPECIALISTS, LLC (0.89)
D. I. J. CONSTRUCTION, INC. (0.83)
MURRAY CONSTRUCTION (0.44)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (5.12)
WYLIE DRILLING & DRAINAGE, INC. (1.97)
GK CONSTRUCTION, LLC (0.14)
Contract #06233434
Totals2578218.99554037.17741585.2228.7

CountyWILLIAMSON
HighwayVA
FromVARIOUS ON IH 35, FM 1460 & US 79
ToIN WILLIAMSON COUNTY
CSJ0914-05-209
Proj IDC 914-5-209
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
0.100288957.00304915.3299.9
Work Order05-14-21
Work Began10-04-21
Work Completed
Time Computed08-12-21
Contract Working Days32
Addl Days Granted0
Working Days Charged29
Percent Time Used90
Contractor(s)
TIGHT LINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-05-209
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.60)
HURRICANE INDUSTRIAL SERVICES LLC (1.33)
Contract #04213025
Totals288957.001500.00304915.3299.9

CountyWILLIAMSON
Highway0000000
FromAT CR 234
To.
CSJ0914-05-214
Proj IDSTP 2024(832)HES
Work TypeTRAFFIC CONTROL DEVICES
 
85855.000.000.0
CountyBASTROP
HighwayFM 1209
FromAT FM 969
To.
CSJ2176-01-010
Proj IDC 2176-1-10
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1920972.140.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days103
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0914-05-214
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04243219
Totals2006827.140.000.000.0

CountyWILLIAMSON
HighwayVA
FromVARIOUS LOCATIONS ON IH 35 FROM SH 45
ToSH 195 AT BERRY CREEK
CSJ0914-05-217
Proj IDC 914-5-217
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
1222324.05890046.6172.8
Work Order05-17-23
Work Began09-05-23
Work Completed
Time Computed07-16-23
Contract Working Days96
Addl Days Granted0
Working Days Charged96
Percent Time Used100
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-05-217
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.93)
FLASHER EQUIPMENT COMPANY (1.93)
Contract #04233226
Totals1222324.05164385.65890046.6172.8

CountyWILLIAMSON
HighwayVA
FromVARIOUS LOCATIONS ON FM 971 AND FM 1460
To.
CSJ0914-05-237
Proj IDSTP 2024(499)FRS
Work TypeRAIL HWY CROSSING SIGNALS/STRUCTURES
 
642558.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days106
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-05-237
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243024
Totals642558.000.000.000.0

CountyBASTROP
HighwayCR
FromON OLD MCDADE RD AT BIG SANDY CREEK
ToSTR# 14-011-0-AA01-06-002
CSJ0914-18-107
Proj IDBR 1802(781)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
1478746.421001265.9267.8
Work Order05-17-23
Work Began08-02-23
Work Completed
Time Computed08-02-23
Contract Working Days79
Addl Days Granted0
Working Days Charged81
Percent Time Used102
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-18-107
DIIBS SPECIALISTS, LLC (0.00)
TEXAS SHAFTS, INC. (0.00)
Contract #04233223
Totals1478746.4242378.931001265.9267.8

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7