Monthly Local Let Maintenance Report For Atlanta District As Of Apr 12, 2024 Page 2 Of 3

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCASS
HighwayFM0249
From.
To.
CSJ6439-92-001
Proj IDSUP - 643992001
Work TypeJANITORIAL MAINTENANCE
 
0.01092356.1667357.50100.0
Work Order03-30-23
Work Began04-01-23
Work Completed04-01-24
Time Computed04-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged366
Percent Time Used100
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6439-92-001
A LIFT FOR LIFE OUTREACH CENTER, INC. (100.00)
Contract #03231931
Totals92356.165665.5367357.50100.0

CountyHARRISON
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6442-52-001
Proj IDRMC - 644252001
Work TypeTREE REMOVAL
 
0.010142028.00142205.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-11-23
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged21
Percent Time Used28
Contractor(s)
CEHAND SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6442-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231902
Totals142028.000.00142205.0099.9

CountyPANOLA
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6442-54-001
Proj IDRMC - 644254001
Work TypeTREE REMOVAL
 
0.010142028.00205933.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-31-23
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted24
Working Days Charged42
Percent Time Used42
Contractor(s)
CEHAND SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6442-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231903
Totals142028.000.00205933.5099.9

CountyCASS
HighwaySH0008
From.
To.
CSJ6442-82-001
Proj IDSUP - 644282001
Work TypeJANITORIAL MAINTENANCE
 
0.0108579.906967.9581.2
Work Order04-19-23
Work Began05-01-23
Work Completed
Time Computed05-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged336
Percent Time Used91
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6442-82-001
A LIFT FOR LIFE OUTREACH CENTER, INC. (100.00)
Contract #04231931
Totals8579.90633.456967.9581.2

CountyTITUS
HighwayUS0271
From.
To.
CSJ6442-86-001
Proj IDSUP - 644286001
Work TypeJANITORIAL MAINTENANCE
 
0.01011227.008878.6079.0
Work Order04-19-23
Work Began05-01-23
Work Completed
Time Computed05-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged336
Percent Time Used91
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6442-86-001
A LIFT FOR LIFE OUTREACH CENTER, INC. (100.00)
Contract #04231932
Totals11227.00669.508878.6079.0

CountyBOWIE
HighwayIH0369
From.
To.
CSJ6442-90-001
Proj IDSUP - 644290001
Work TypeJANITORIAL MAINTENANCE
 
0.01020723.6017674.8085.2
Work Order04-19-23
Work Began05-01-23
Work Completed
Time Computed05-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged336
Percent Time Used91
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6442-90-001
A LIFT FOR LIFE OUTREACH CENTER, INC. (100.00)
Contract #04231933
Totals20723.601606.8017674.8085.2

CountyBOWIE
HighwayIH0369
From.
To.
CSJ6443-24-001
Proj IDSUP - 644324001
Work TypeGROUNDS MAINTENANCE
 
0.01015657.0011107.0070.9
Work Order04-19-23
Work Began05-01-23
Work Completed
Time Computed05-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged336
Percent Time Used91
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6443-24-001
A LIFT FOR LIFE OUTREACH CENTER, INC. (100.00)
Contract #04231934
Totals15657.00566.5011107.0070.9

CountyPANOLA
HighwayUS0079
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6453-11-001
Proj IDMMC - 645311001
Work TypeHOT MIX
 
0.010239800.0087344.7236.4
Work Order11-03-23
Work Began12-14-23
Work Completed
Time Computed12-14-23
Contract Working Days120
Addl Days Granted120
Working Days Charged109
Percent Time Used45
Contractor(s)
LONGVIEW ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6453-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231901
Totals239800.0023049.3087344.7236.4

CountyMORRIS
HighwayUS0259
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6453-15-001
Proj IDMMC - 645315001
Work TypeHOT MIX
 
0.010236750.007917.803.3
Work Order11-03-23
Work Began12-14-23
Work Completed
Time Computed12-14-23
Contract Working Days120
Addl Days Granted120
Working Days Charged109
Percent Time Used45
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6453-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231902
Totals236750.007917.807917.803.3

CountyUPSHUR
HighwayUS0271
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6453-17-001
Proj IDMMC - 645317001
Work TypeHOT MIX
 
0.010219750.000.000.0
Work Order11-03-23
Work Began12-14-23
Work Completed
Time Computed12-14-23
Contract Working Days120
Addl Days Granted120
Working Days Charged109
Percent Time Used45
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6453-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231903
Totals219750.000.000.000.0

CountyMARION
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6453-19-001
Proj IDMMC - 645319001
Work TypeHOT MIX
 
0.010239800.0030585.7412.7
Work Order11-03-23
Work Began12-14-23
Work Completed
Time Computed12-14-23
Contract Working Days120
Addl Days Granted120
Working Days Charged110
Percent Time Used45
Contractor(s)
LONGVIEW ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6453-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231904
Totals239800.008248.4730585.7412.7

CountyCASS
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6453-21-001
Proj IDMMC - 645321001
Work TypeHOT MIX
 
0.010262000.0088263.3533.6
Work Order11-03-23
Work Began12-14-23
Work Completed
Time Computed12-14-23
Contract Working Days120
Addl Days Granted120
Working Days Charged109
Percent Time Used45
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6453-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231905
Totals262000.0012361.7288263.3533.6

CountyHARRISON
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6453-23-001
Proj IDMMC - 645323001
Work TypeHOT MIX
 
0.010239800.006973.832.9
Work Order11-03-23
Work Began12-14-23
Work Completed
Time Computed12-14-23
Contract Working Days120
Addl Days Granted120
Working Days Charged109
Percent Time Used45
Contractor(s)
LONGVIEW ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6453-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231906
Totals239800.000.006973.832.9

CountyTITUS
HighwayUS0271
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6453-25-001
Proj IDMMC - 645325001
Work TypeHOT MIX
 
0.010236750.002755.501.1
Work Order11-03-23
Work Began12-14-23
Work Completed
Time Computed12-14-23
Contract Working Days120
Addl Days Granted120
Working Days Charged109
Percent Time Used45
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6453-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231907
Totals236750.002755.502755.501.1

CountyBOWIE
HighwayUS0082
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6453-27-001
Proj IDMMC - 645327001
Work TypeHOT MIX
 
0.010260125.0068379.7826.2
Work Order11-03-23
Work Began12-14-23
Work Completed
Time Computed12-14-23
Contract Working Days120
Addl Days Granted120
Working Days Charged109
Percent Time Used45
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6453-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231908
Totals260125.0035240.6668379.7826.2

CountyBOWIE
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6453-29-001
Proj IDMMC - 645329001
Work TypeHOT MIX
 
0.010252625.0019403.307.6
Work Order11-03-23
Work Began12-14-23
Work Completed
Time Computed12-14-23
Contract Working Days120
Addl Days Granted120
Working Days Charged109
Percent Time Used45
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6453-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231909
Totals252625.005162.2219403.307.6

CountyPANOLA
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6453-72-001
Proj IDRMC - 645372001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010178343.880.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days57
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6453-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01241901
Totals178343.880.000.000.0

CountyMORRIS
HighwayFM0161
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6453-73-001
Proj IDRMC - 645373001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010193596.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days51
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TERRY ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6453-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01241902
Totals193596.000.000.000.0

CountyUPSHUR
HighwayFM0556
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6453-75-001
Proj IDRMC - 645375001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010188016.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days59
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6453-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01241903
Totals188016.000.000.000.0

CountyMARION
HighwaySH0049
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6453-77-001
Proj IDRMC - 645377001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010149206.180.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HX FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6453-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01241904
Totals149206.180.000.000.0

page 1 | page 2 | page 3