Monthly State Let Construction Report For Amarillo District As Of Apr 10, 2018 Page 1 Of 2

Last Update: Friday, April 20, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyOCHILTREE ETC
HighwayUS 83 ETC
FromOKLAHOMA STATE LINE
ToSH 15
CSJ0030-01-033
Proj IDSTP 2018(160)HESG
Work TypeSAFETY IMPROVEMENT PROGRAM (HSIP)
 
159.784810357.03108464.9113.3
Work Order11-13-17
Work Began00-00-00
Work Completed
Time Computed12-13-17
Contract Working Days74
Addl Days Granted0
Working Days Charged40
Percent Time Used54
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0030-01-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173005
Totals810357.0360507.00108464.9113.3

CountyOCHILTREE
HighwayUS 83
FromPEER STREET
ToCOUNTY ROAD K
CSJ0030-02-044
Proj IDSTP 1602(301)
Work TypeREHAB EXISTING ROADWAY
 
1.5132999163.702601937.4586.7
Work Order03-16-17
Work Began05-23-17
Work Completed
Time Computed04-17-17
Contract Working Days131
Addl Days Granted4
Working Days Charged117
Percent Time Used86
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-02-044
ALAMO BROTHERS CONCRETE, INC. (9.73)
BARRICADES UNLIMITED (2.71)
WOLFE CONSTRUCTION GROUP, INC. (0.15)
Contract #02173010
Totals2999163.70263448.062601937.4586.7

CountyOCHILTREE ETC
HighwayUS 83 ETC
FromSH 15
ToPEER STREET (PERRYTON)
CSJ0030-02-047
Proj IDNH 2017(260)
Work TypeSEALCOAT
 
313.26012438153.539533755.4776.6
Work Order12-20-16
Work Began00-00-00
Work Completed
Time Computed04-15-17
Contract Working Days76
Addl Days Granted0
Working Days Charged72
Percent Time Used94
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-02-047
CACTUS ASPHALT, A DIVISION OF CACTUS TRANSPORT, INC. (14.02)
FLAT LINE, INC. (2.47)
Contract #11163003
Totals12438153.530.009533755.4776.6

CountyHEMPHILL ETC
HighwayUS 83 ETC
FromAT SH 33
To.
CSJ0030-06-059
Proj IDSTP 2017(858)HES
Work TypeINSTALL FLASHING BEACON
 
3.781563243.50551527.6997.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-24-17
Work Began00-00-00
Work Completed
Time Computed05-24-17
Contract Working Days54
Addl Days Granted7
Working Days Charged60
Percent Time Used98
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-06-059
BEAN ELECTRICAL, INC. (68.91)
Contract #03173221
Totals563243.500.00551527.6997.9

CountyHEMPHILL ETC
HighwayUS 83 ETC
FromFM 277
ToWHEELER COUNTY LINE
CSJ0030-07-019
Proj IDSTP 2018(282)
Work TypeSEALCOAT
 
290.15014437253.180.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-22-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days98
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-07-019
BARRICADES PLUS, LLC (0.99)
STRIPE-A-ZONE, INC. (8.20)
Contract #11173001
Totals14437253.180.000.000.0

CountyDALLAM ETC
HighwayUS 87 ETC
FromUS 54
ToLINCOLN STREET
CSJ0040-03-059
Proj IDNH 1502(569)
Work TypeUPGRADE TO STANDARDS NON-FREEWAY
 
4.35626321210.0026789840.9899.9
Work Order02-02-16
Work Began03-14-16
Work Completed
Time Computed03-03-16
Contract Working Days443
Addl Days Granted10
Working Days Charged379
Percent Time Used83
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0040-03-059
BARRICADES UNLIMITED (0.31)
A BROTHERS MILLING, LLC (1.02)
TLJ LINING CO. (0.09)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.38)
MCL CONTRACTING, LLC (0.02)
G AND G OPERATORS, LTD. (4.59)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.32)
J. LEE MILLIGAN, INC. (16.97)
PRIMATE CONSTRUCTION, INC. (0.71)
BREDA COMPANY, INC. (0.74)
KLP COMMERCIAL, LLC (4.23)
FARR FOUNDATION, INC. (0.83)
AR DANIEL CONSTRUCTION SERVICES, INC. (0.48)
SIGNAL SERVICES GROUP INC. (2.60)
ACTION CONSTRUCTORS (5.23)
SLATON BROTHERS, INC. (1.98)
FLUHMAN BUILDERS, LLC (0.00)
URBAN INFRACONSTRUCTION, LLC. (0.22)
ABERNATHY FENCE (0.08)
SYNERGY SIGNS & SERVICES, LLC (0.25)
PENHALL COMPANY (0.15)
SCOTT DERR PAINTING CO, LLC (0.05)
Contract #08153216
Totals26321210.00182442.1526789840.9899.9

CountyPOTTER
HighwayUS 87
FromAMARILO CREEK
ToMOORE COUNTY LINE
CSJ0041-05-050
Proj IDNH 2018(435)
Work TypeOVERLAY
 
17.36812042105.820.000.0
CountyPOTTER
HighwayUS 287
FromIH 40
ToCARSON COUNTY LINE
CSJ0042-01-030
Proj IDNH 2018(435)
Work TypeOVERLAY
 
3.8182523248.650.000.0
CountyCARSON
HighwayUS 287
FromCARSON COUNTY LINE
ToARMSTRONG COUNTY LINE
CSJ0042-02-020
Proj IDNH 2018(435)
Work TypeOVERLAY
 
0.510331656.090.000.0
Work Order02-14-18
Work Began00-00-00
Work Completed
Time Computed03-16-18
Contract Working Days146
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0041-05-050
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183203
Totals14897010.560.000.000.0

CountyMOORE
HighwayUS 87
FromDIVIDED 4 LANE SOUTH OF DUMAS
ToPOTTER COUNTY LINE
CSJ0066-05-066
Proj IDC 66-5-66
Work TypeREHAB EXISTING ROADWAY
 
15.50610790483.200.000.0
CountyMOORE
HighwayUS 87
From0.863 MILES SOUTH OF FM 722
ToPOTTER COUNTY LINE
CSJ0066-05-068
Proj IDSTP 2018(776)HES
Work Type2017 FEDERAL HSIP PROGRAM
 
15.478394503.000.000.0
CountyMOORE
HighwayUS 87
From0.863 MILES SOUTH OF FM 722
ToPOTTER COUNTY LINE
CSJ0066-05-069
Proj IDSTP 2018(776)HES
Work Type2017 FEDERAL HSIP PROGRAM
 
15.47858000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0066-05-066
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183214
Totals11242986.200.000.000.0

CountyDEAF SMITH
HighwayIH 40
FromVARIOUS LOCATIONS ON IH 40
To.
CSJ0090-01-032
Proj IDBR 2018(777)
Work Type2018 BMIP PROGRAM
 
0.0107422545.000.000.0
CountyRANDALL
HighwayIH 27
FromVARIOUS LOCATIONS ON IH 27
To.
CSJ0168-09-174
Proj IDBR 2018(777)
Work Type2018 BMIP PROGRAM
 
0.010839417.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days377
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0090-01-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183009
Totals8261962.000.000.000.0

CountyPOTTER
HighwayIH 40
From1274 FT WEST OF FM 2381
To1243 FT EAST OF FM 2381
CSJ0090-05-097
Proj IDNH 2018(284)
Work TypeMISCELLANOUS
 
0.4781206394.0214432.001.1
CountyOLDHAM
HighwayFM 809
From.33 MI N OF DEAF SMITH COUNTY LINE
ToDEAF SMITH COUNTY LINE
CSJ0801-01-013
Proj IDSTP 2018(285)
Work TypeMISCELLANEOUS CONSTRUCTION
 
0.333264435.480.000.0
CountyDEAF SMITH
HighwayFM 809
FromOLDHAM COUNTY LINE
To.27 MI S OF OLDHAM COUNTY LINE
CSJ0801-02-020
Proj IDSTP 2018(285)
Work TypeMISCELLANEOUS CONSTRUCTION
 
0.272300331.330.000.0
Work Order12-08-17
Work Began00-00-00
Work Completed
Time Computed01-07-18
Contract Working Days57
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0090-05-097
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11173013
Totals1771160.830.0014432.000.8

CountyPOTTER
HighwayIH 40
FromWEST BOUND BRIDGE AT RM 2381
To.
CSJ0090-05-099
Proj IDBR 1702(431)
Work TypeBRIDGE REPLACEMENT
 
0.3571333510.551522296.4599.9
Work Order07-20-17
Work Began08-21-17
Work Completed
Time Computed08-19-17
Contract Working Days60
Addl Days Granted2
Working Days Charged50
Percent Time Used80
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0090-05-099
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.63)
BARRICADES UNLIMITED (3.00)
HJC FARMS, INC. (7.52)
HUNTER DEMOLITION & WRECKING CORPORATION (4.97)
PENHALL COMPANY (0.27)
ALAMO BROTHERS CONCRETE, INC. (0.99)
Contract #06173018
Totals1333510.5579580.001522296.4599.9

CountyPOTTER
HighwayBI 40-D
FromVARIOUS LOCATIONS ON BI 40-D
To.
CSJ0090-06-039
Proj IDSTP 1602(188)
Work TypeREHAB TRAFFIC SIGNALS
 
0.293977598.79620227.0463.4
CountyPOTTER
HighwayIH 40
FromON IH 40 AT BELL STREET
To.
CSJ0275-01-187
Proj IDBR 2017(934)
Work TypeBRIDGE MAINT PROGRAM (BMIP)
 
0.1004718575.314216464.7989.3
CountyPOTTER
HighwayIH 40
FromWEST OF BELL STREET
ToEAST OF BELL STREET
CSJ0275-01-189
Proj IDNH 2017(935)
Work TypeMISCELLANEOUS CONSTRUCTION
 
0.3001776055.66737908.1241.5
Work Order05-22-17
Work Began07-20-17
Work Completed
Time Computed06-21-17
Contract Working Days212
Addl Days Granted25
Working Days Charged185
Percent Time Used78
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0090-06-039
QLVS, INC. DBA PHASE 3 ELECTRIC (16.95)
ALAMO BROTHERS CONCRETE, INC. (3.30)
HOLMES CONSTRUCTION CO., L.P. (11.28)
BARRICADES UNLIMITED (1.39)
DIIBS SPECIALISTS (0.46)
FARR FOUNDATION, INC. (1.06)
PENHALL COMPANY (0.08)
SCOTT DERR PAINTING CO, LLC (0.05)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.14)
WOLFE CONSTRUCTION GROUP, INC. (0.00)
BOWMAN ENGINEERING & CONSULTING, INC (0.27)
MCL CONTRACTING, LLC (0.29)
ALAMO BROTHERS CONCRETE, INC. (1.05)
ALL STAR FENCE, LLC (0.17)
DRILL PIER CONSTRUCTION, LLC (0.19)
DAN MONK CONSTRUCTION (1.06)
Contract #04173223
Totals7472229.76359486.875574599.9574.6

CountyRANDALL
HighwayIH 27
FromSUNDOWN LANE
ToBELL STREET
CSJ0168-09-161
Proj IDDMO 2012(757)
Work TypeREHAB EXISTING ROADWAY
 
2.17215278484.991634251.4810.6
CountyRANDALL
HighwaySL 335
FromIH 27
ToBELL STREET
CSJ2635-02-029
Proj IDNH 1702(473)
Work TypeCONVERT NONFREEWAY TO FREEWAY
 
0.4265927968.28748.260.0
CountyRANDALL
HighwaySL 335
FromWEST OF COULTER
ToIH 27
CSJ2635-03-018
Proj IDNH 1702(473)
Work TypeCONVERT NONFREEWAY TO FREEWAY
 
1.07621169039.131918592.529.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-11-17
Work Began01-08-18
Work Completed
Time Computed00-00-00
Contract Working Days720
Addl Days Granted0
Working Days Charged59
Percent Time Used8
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0168-09-161
A BROTHERS MILLING, LLC (0.44)
BARRICADES UNLIMITED (0.88)
BRUNDAGE-BONE (0.07)
DIIBS SPECIALISTS (0.32)
HARDY TREES, INC. (0.27)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.10)
OSCAR ORDUNO, INC. (1.42)
PRIMATE CONSTRUCTION, INC. (0.05)
QLVS, INC. DBA PHASE 3 ELECTRIC (0.81)
S & S BRIDGE PAINTING, INC. (0.02)
UTILITY CONTRACTORS OF AMERICA, LTD (18.08)
WEBBER BARRIER SERVICES, LLC. (1.65)
WILLIS ELECTRIC CO., LP (6.48)
BOWMAN ENGINEERING & CONSULTING, INC (0.07)
H & F TRUCKING (1.82)
AMARILLO UTILITY CONTRACTORS (0.14)
CRANE SERVICES, INC. (5.18)
Contract #07173201
Totals42375492.401073277.403553592.268.3

CountyRANDALL
HighwayIH 27
FromPOTTER COUNTY LINE
ToSOUTH OF 34TH AVENUE
CSJ0168-09-170
Proj IDNH 1702(133)
Work TypeMISCELLANOUS CONSTRUCTION
 
0.4033410133.78745557.5021.8
CountyPOTTER
HighwayIH 27
FromON IH 27 SBL AT 26TH AVE
To.
CSJ0168-10-073
Proj IDBR 1702(132)
Work TypeBRIDGE MAINT PROGRAM (BMIP)
 
0.0763180524.881639281.3251.5
CountyPOTTER
HighwayIH 27
FromNORTH OF 26TH AVENUE
ToRANDALL COUNTY LINE
CSJ0168-10-074
Proj IDNH 1702(133)
Work TypeMISCELLANOUS CONSTRUCTION
 
0.5121958921.59320588.0516.3
CountyPOTTER
HighwayIH 40
FromGEORGIA STREET
ToCROCKETT STREET
CSJ0275-01-194
Proj IDNH 1702(133)
Work TypeMISCELLANEOUS CONSTRUCTION
 
0.4681335451.65121462.669.0
Work Order06-14-17
Work Began10-16-17
Work Completed
Time Computed07-14-17
Contract Working Days201
Addl Days Granted0
Working Days Charged109
Percent Time Used54
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0168-09-170
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.53)
HJC FARMS, INC. (2.29)
FARR FOUNDATION, INC. (2.85)
WOLFE CONSTRUCTION GROUP, INC. (0.11)
SCR CIVIL CONSTRUCTION, LLC (3.90)
BARRICADES UNLIMITED (1.62)
S & S BRIDGE PAINTING, INC. (5.99)
QLVS, INC. DBA PHASE 3 ELECTRIC (2.20)
BOWMAN ENGINEERING & CONSULTING, INC (0.04)
CHOCTAW ERECTORS, INC. (2.93)
Contract #05173229
Totals9885031.90679252.322826889.5328.5

CountyPOTTER
HighwayUS 60
FromON BUCHANAN FROM 11TH TO 6TH
ToON 6TH FROM FILLMORE TO PIERCE
CSJ0168-10-069
Proj IDSTP 2014(103)TE
Work TypeTRANSPORTION ENHANCEMENT
 
0.3632147565.302205509.3799.9
Work Order08-05-16
Work Began02-01-17
Work Completed
Time Computed09-04-16
Contract Working Days95
Addl Days Granted0
Working Days Charged95
Percent Time Used100
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0168-10-069
QLVS, INC. DBA PHASE 3 ELECTRIC (9.34)
PARK MINNESOTA CONSTRUCTION COMPANY (9.63)
BARRICADES UNLIMITED (1.23)
GREEN PLAINS DESIGN (15.70)
SPEEDY PAVING (5.18)
Contract #05163222
Totals2147565.306440.002205509.3799.9

CountyPOTTER
HighwayUS 60
FromLP 335
ToCARSON COUNTY LINE
CSJ0169-02-065
Proj IDNH 2018(357)
Work TypeOVERLAY
 
7.2464344644.610.000.0
CountyPOTTER
HighwayIH 40
FromUS 287 INTERCHANGE
ToCARSON COUNTY LINE
CSJ0275-01-161
Proj IDNH 2018(357)
Work TypeOVERLAY
 
4.5973250751.720.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days59
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0169-02-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183234
Totals7595396.330.000.000.0

CountyCARSON
HighwayUS 60
From0.71 MI W OF SH 207
To3.86 MI EAST OF PANHANDLE CL
CSJ0169-04-036
Proj IDNH 2013(611)
Work TypeREHAB EXISTING ROADWAY
 
5.8385719206.16397239.276.9
CountyCARSON
HighwayUS 60
From3.86 MI EAST OF PAHANDLE CL
ToCR S EAST OF PANHANDLE
CSJ0169-05-043
Proj IDNH 2013(611)
Work TypeREHAB EXISTING ROADWAY
 
0.787763361.829423.321.2
CountyGRAY
HighwayUS 60
FromFM 750 WEST OF PAMPA
ToSH 70
CSJ0169-06-039
Proj IDNH 2013(611)
Work TypeREHAB EXISTING ROADWAY
 
1.388747149.820.000.0
CountyGRAY
HighwayUS 60
FromSH 70
ToSH 152
CSJ0169-07-052
Proj IDNH 2013(611)
Work TypeREHAB EXISTING ROADWAY
 
7.5113828249.630.000.0
Work Order12-14-17
Work Began00-00-00
Work Completed
Time Computed01-13-18
Contract Working Days155
Addl Days Granted0
Working Days Charged11
Percent Time Used7
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0169-04-036
DUSTROL, INC. (0.33)
BARRICADES UNLIMITED (2.22)
WOLFE CONSTRUCTION GROUP, INC. (0.21)
TEX OP CONSTRUCTION, LP (3.44)
SIGNAL SERVICES GROUP INC. (2.05)
DUSTIN ALLEN, INC. (0.81)
DK CONTRACTING, LLC (1.08)
Contract #10173201
Totals11057967.43406662.59406662.593.6

CountyCARSON
HighwayUS 60
FromCR W WEST OF WHITE DEER
ToGRAY COUNTY LINE
CSJ0169-05-042
Proj IDNH 2013(614)
Work TypeREHAB EXISTING ROADWAY
 
8.77310873603.330.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-08-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days125
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0169-05-042
BARRICADES UNLIMITED (1.78)
DUSTROL, INC. (3.59)
DIAMOND SURFACE, INC. (0.15)
HJC FARMS, INC. (2.22)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.18)
Contract #02183238
Totals10873603.330.000.000.0

CountyPOTTER
HighwayIH 40
FromSONCY
ToIH 27 INTERCHANGE
CSJ0275-01-163
Proj IDNH 2017(367)
Work TypeOVERLAY
 
5.2426982390.10795545.7711.3
Work Order03-16-17
Work Began10-24-17
Work Completed
Time Computed04-15-17
Contract Working Days80
Addl Days Granted0
Working Days Charged5
Percent Time Used6
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-163
BARRICADES UNLIMITED (1.36)
HJC FARMS, INC. (7.76)
O. TREVINO CONSTRUCTION, LLC (0.82)
Contract #02173206
Totals6982390.100.00795545.7711.3

CountyPOTTER ETC
HighwayIH 40 ETC
FromHELIUM ROAD
ToEAST OF SL 335
CSJ0275-01-166
Proj IDNH 1502(372)
Work TypeRELOCATE ENTRANCE AND EXIT RAMPS
 
5.17926403959.2526297447.6298.0
Work Order10-06-15
Work Began01-25-16
Work Completed
Time Computed11-02-15
Contract Working Days560
Addl Days Granted12
Working Days Charged488
Percent Time Used85
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-166
ALAMO BROTHERS CONCRETE (4.85)
DUSTIN ALLEN, INC. (0.52)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.47)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.23)
WILLIS ELECTRIC CO., LP (10.58)
MCL CONTRACTING, LLC (0.16)
MICA CORPORATION (3.01)
L. A. FULLER & SONS CONSTRUCTION, LTD. (19.71)
SCOTT DERR PAINTING CO, LLC (0.16)
BREDA COMPANY, INC. (2.66)
BARRICADES UNLIMITED (0.95)
TRUMBLE CRANE & RIGGING (0.23)
A BROTHERS MILLING, LLC (0.23)
WOLFE CONSTRUCTION GROUP, INC. (0.04)
TRI-STATE OILFIELD SERVICES, INC. (0.02)
JOSH FRANKLIN DRILLING, LLC (0.04)
OSCAR ORDUNO, INC. (1.84)
MCL CONTRACTING, LLC (0.01)
ALAMO BROTHERS CONCRETE (0.20)
SLATON BROTHERS, INC. (3.58)
PENHALL COMPANY (0.06)
WEBBER BARRIER SERVICES, LLC. (1.30)
PEREZ SERVICES, INC. (0.08)
Contract #07153253
Totals26403959.25363846.5626297447.6298.0

page 1 | page 2