Monthly State Let Construction Report For Yoakum District As Of Jul 13, 2018 Page 3 Of 7

Last Update: Friday, July 13, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCOLORADO
HighwayFM 155
FromFM 2434
To1 MI S OF FM 532
CSJ0211-10-042
Proj IDSTP 2017(484)HES
Work TypeINCREASE SUPERELEVATION
 
8.540714920.82655107.0894.8
Work Order03-01-17
Work Began06-12-17
Work Completed
Time Computed05-30-17
Contract Working Days40
Addl Days Granted0
Working Days Charged78
Percent Time Used195
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0211-10-042
D. I. J. CONSTRUCTION, INC. (2.63)
DELGADO"S CONSTRUCTION (18.91)
EGGEMEYER LAND CLEARING, LLC (2.73)
ROADWAY SPECIALTIES, INC. (4.16)
AREA WIDE PROTECTIVE, INC. (0.81)
Contract #01173205
Totals714920.820.00655107.0894.8

CountyWHARTON
HighwaySH 60
FromFM 2919
To0.2 MI N OF BU 59-R(W. BERNARD RD)
CSJ0240-03-036
Proj IDSTP 1702(486)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
20.7861947826.26479306.1824.6
Work Order08-08-17
Work Began11-13-17
Work Completed
Time Computed11-06-17
Contract Working Days179
Addl Days Granted0
Working Days Charged51
Percent Time Used28
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 0240-03-036
AREA WIDE PROTECTIVE, INC. (0.64)
DIIBS SPECIALISTS (5.12)
FUQUAY, INC. (2.38)
RUCOBA & MAYA CONSTRUCTION (16.65)
Contract #07173042
Totals1947826.26102157.29479306.1824.6

CountyMATAGORDA
HighwaySH 60
From@ GRACE ST
ToIN BAY CITY
CSJ0241-02-053
Proj IDSTP 2017(319)HES
Work TypeIMPROVE TRAFFIC SIGNAL
 
0.002306857.45246161.8380.7
Work Order02-13-17
Work Began04-02-18
Work Completed
Time Computed05-14-17
Contract Working Days45
Addl Days Granted0
Working Days Charged48
Percent Time Used106
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0241-02-053
STRIPE LINES, INC. (2.02)
SOUTH RANGER CONSTRUCTION, INC. (6.44)
Contract #12163011
Totals306857.4594296.37246161.8380.7

CountyFAYETTE
HighwaySH 71
FromBASTROP C/L
To0.051 MI. WEST OF PRAIRIE VALLEY RD
CSJ0265-07-049
Proj IDNH 1702(642)
Work TypeACP OVERLAY
 
7.5762399994.552551274.4399.9
Work Order10-16-17
Work Began04-02-18
Work Completed
Time Computed11-16-17
Contract Working Days45
Addl Days Granted0
Working Days Charged44
Percent Time Used97
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0265-07-049
TRP CONSTRUCTION GROUP, LLC (0.22)
PENHALL COMPANY (AUSTIN) (0.60)
D. I. J. CONSTRUCTION, INC. (3.20)
UNDER CONSTRUCTION INC. (1.05)
GREEN MILLING GROUP (1.12)
Contract #08173034
Totals2399994.5511021.002551274.4399.9

CountyFAYETTE
HighwaySH 71
FromSH 159
ToCOLORADO C/L
CSJ0266-01-074
Proj IDSTP 2017(256)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
24.367276120.00265875.2696.2
Work Order12-07-16
Work Began03-27-17
Work Completed
Time Computed03-07-17
Contract Working Days30
Addl Days Granted12
Working Days Charged42
Percent Time Used100
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0266-01-074
LONESTAR TRAFFIC SAFETY, LLC (3.20)
ENVIRONMENTAL SAFETY SERVICES, INC. (38.41)
Contract #11163007
Totals276120.000.00265875.2696.2

CountyFAYETTE ETC
HighwaySH 71 ETC
FromAT FM 955
To.
CSJ0266-01-075
Proj IDSTP 2017(486)HES
Work TypeSAFETY LIGHTING AT INTERSECTION
 
2.801681093.20687597.4599.9
Work Order02-15-17
Work Began08-17-17
Work Completed
Time Computed05-16-17
Contract Working Days90
Addl Days Granted1
Working Days Charged83
Percent Time Used91
Contractor(s)
F & W ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0266-01-075
ALTUS TRAFFIC MANAGEMENT LLC (1.46)
Contract #01173251
Totals681093.200.00687597.4599.9

CountyCOLORADO
HighwaySH 71
FromSOUTH OF RATLIFF CREEK
To0.2 MILES N. OF US 90A
CSJ0266-03-029
Proj IDSTP 2016(621)
Work TypeCONSTRUCT SUPER 2 LANES
 
9.8059120997.866191334.8368.7
Work Order03-15-16
Work Began08-25-16
Work Completed
Time Computed06-13-16
Contract Working Days226
Addl Days Granted0
Working Days Charged295
Percent Time Used130
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0266-03-029
ROADSAFE TRAFFIC SYSTEMS, INC. (2.13)
WEST TEXAS RUMBLE STRIP (0.11)
MV HENKE COMPANY, LLC (0.83)
SCMU (5.97)
Contract #01163042
Totals9120997.86133777.016191334.8368.7

CountyCOLORADO
HighwayBS 71-F
FromAT COLORADO RIVER
ToSTR# 0266-08-043
CSJ0266-08-011
Proj IDBR 1702(488)
Work TypeCONSTRUCT NEW BRIDGE AND APPROACHES
 
0.67510459588.754437625.8242.4
Work Order08-23-17
Work Began02-20-18
Work Completed
Time Computed11-21-17
Contract Working Days375
Addl Days Granted0
Working Days Charged75
Percent Time Used20
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0266-08-011
CHOCTAW ERECTORS, INC. (10.44)
HOUSTON SAWING & DRILLING (0.09)
DURWOOD GREENE CONSTRUCTION CO. (6.32)
A-1 EROSION CONTROL, LLC (0.10)
LONESTAR TRAFFIC SAFETY, LLC (0.13)
MESA ROD BUSTERS, INC. (0.77)
MICHAEL"S MAINTENANCE SERVICE, LLC (0.14)
KDR CONTRACTORS, LLC (0.49)
A. H. BECK FOUNDATION CO., INC. (8.87)
HIGHWAY 1 LLC (0.49)
Contract #07173209
Totals10459588.75980772.044437625.8242.4

CountyFAYETTE
HighwayFM 609
From2.2 MI. N. OF FM 2237
ToUS 90
CSJ0267-05-018
Proj IDSTP 2018(749)
Work TypePAVEMENT REPAIR AND RESURFACING
 
11.6497416527.180.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-17-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days300
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0267-05-018
AWP, INC. DBA AREA WIDE PROTECTIVE (0.44)
ROADWAY SPECIALTIES, INC. (0.92)
STRIPE-A-ZONE, INC. (0.46)
TRP CONSTRUCTION GROUP, LLC (2.11)
Contract #04183011
Totals7416527.180.000.000.0

CountyLAVACA
HighwayUS 77
FromFAYETTE C/L
ToUS 90A
CSJ0269-02-065
Proj IDSTP 1802(397)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
22.1911147696.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days133
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0269-02-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07183034
Totals1147696.000.000.000.0

CountyLAVACA
HighwayUS 77A
From0.5 MI S OF FM 340
To1.0 MI S OF FM 340
CSJ0269-03-035
Proj IDSTP 2018(605)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
15.0212082955.470.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-18-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days330
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0269-03-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183207
Totals2082955.470.000.000.0

CountyLAVACA
HighwayFM 531
FromAT YELLOW BANK CREEK
ToSTR # 0269-10-027
CSJ0269-10-023
Proj IDBR 1502(585)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1641574475.261543610.0999.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-10-15
Work Began02-25-16
Work Completed
Time Computed02-07-16
Contract Working Days120
Addl Days Granted0
Working Days Charged145
Percent Time Used120
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 0269-10-023
ALTUS TRAFFIC MANAGEMENT LLC (0.51)
BEAIRD DRILLING (3.78)
ENVIRONMENTAL SAFETY SERVICES, INC. (4.76)
LONE STAR EROSION CONTROL (0.59)
WEBER-BALKE FOUNDATION COMPANY, INC (2.37)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00)
Contract #08153039
Totals1574475.260.001543610.0999.2

CountyAUSTIN
HighwayUS 90
FromAT SH 36 & BNSF RR
ToSTR # 0271-08-419 & 025
CSJ0271-08-012
Proj IDBR 2017(052)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.7359013434.639239107.9999.9
Work Order01-17-17
Work Began02-20-17
Work Completed
Time Computed02-17-17
Contract Working Days190
Addl Days Granted13
Working Days Charged203
Percent Time Used100
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0271-08-012
AREA WIDE PROTECTIVE, INC. (0.13)
FLASHER EQUIPMENT COMPANY (0.35)
JASSO"S SAWING & SEALING (0.02)
J. T. B. SERVICES, INC. (1.15)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.93)
MCL CONTRACTING, LLC (1.14)
PFEIFFER & SON LTD. (0.78)
ROADWAY SPECIALTIES, INC. (0.65)
HOUSTON SAWING & DRILLING (0.05)
D&S TEXAS ICON CONSTRUCTION (0.42)
FOSTER FENCE, LTD. (0.32)
Contract #09163211
Totals9013434.6337063.269239107.9999.9

CountyGONZALES
HighwaySH 80
FromGUADALUPE C/L
To1.3 MI N OF FM 1682
CSJ0287-03-031
Proj IDSTP 2018(750)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
21.3731301576.760.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-14-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days213
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BEAR CREEK CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0287-03-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183215
Totals1301576.760.000.000.0

CountyGONZALES
HighwaySH 80
From2.1 MI NORTH OF SH 97
To0.06 MI NORTH OF US 87
CSJ0287-04-037
Proj IDSTP 2017(321)
Work TypePAVEMENT REPAIR AND RESURFACING
 
10.3363460417.813513188.8799.9
Work Order01-17-17
Work Began03-27-17
Work Completed
Time Computed04-17-17
Contract Working Days60
Addl Days Granted0
Working Days Charged60
Percent Time Used100
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0287-04-037
FLASHER EQUIPMENT COMPANY (0.19)
STRIPE-A-ZONE, INC. (0.81)
FUQUAY, INC. (0.05)
MPB, INC. (0.27)
INTERSTATE BARRICADES & MARKINGS, INC. (2.86)
Contract #12163019
Totals3460417.812391.483513188.8799.9

CountyFAYETTE
HighwaySH 95
FromUS 90 IN FLATONIA
To0.6 MI SOUTH OF US 90
CSJ0324-01-026
Proj IDSTP 2016(131)
Work TypePAVEMENT REPAIR AND SURFACING
 
0.5891046229.461026968.4199.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-13-16
Work Began07-14-16
Work Completed
Time Computed07-12-16
Contract Working Days30
Addl Days Granted0
Working Days Charged54
Percent Time Used180
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0324-01-026
A BROTHERS MILLING, LLC (6.74)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.26)
FLASHER EQUIPMENT COMPANY (1.56)
Contract #10153224
Totals1046229.460.001026968.4199.7

CountyLAVACA
HighwaySH 95
FromFAYETTE COUNTY LINE
To0.020 MI NORTH OF CR298 (CSJ BREAK)
CSJ0324-02-024
Proj IDSTP 2017(174)
Work TypeACP OVERLAY
 
13.2123147885.723359115.6699.9
Work Order11-23-16
Work Began07-31-17
Work Completed
Time Computed02-21-17
Contract Working Days60
Addl Days Granted0
Working Days Charged60
Percent Time Used100
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0324-02-024
PRIMATE CONSTRUCTION, INC. (0.87)
STRIPE-A-ZONE, INC. (0.95)
INTERSTATE BARRICADES & MARKINGS, INC. (3.08)
Contract #10163014
Totals3147885.720.003359115.6699.9

CountyFAYETTE
HighwayFM 154
FromAT A TRIB OF PIN OAK CREEK
ToSTR # 130760033408021
CSJ0334-08-033
Proj IDBR 2017(488)
Work TypeREPLACE BRIDE AND APPROACHES
 
0.132519583.10548642.7499.9
Work Order02-13-17
Work Began06-11-17
Work Completed
Time Computed05-14-17
Contract Working Days45
Addl Days Granted0
Working Days Charged45
Percent Time Used100
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0334-08-033
AREA WIDE PROTECTIVE, INC. (3.09)
FLASHER EQUIPMENT COMPANY (2.40)
Contract #01173220
Totals519583.100.00548642.7499.9

CountyMATAGORDA
HighwayFM 1468
FromSH 71
ToSH 35
CSJ0346-10-021
Proj IDSTP 1402(099)HESG
Work TypeSAFETY TREAT FIXED OBJECTS
 
10.3761128804.521029579.6293.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-20-14
Work Began12-09-14
Work Completed
Time Computed12-09-14
Contract Working Days150
Addl Days Granted25
Working Days Charged213
Percent Time Used121
Contractor(s)
ACE ASPHALT OF ARIZONA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0346-10-021
RICE ENVIRONMENTAL SERVICES (0.82)
BEAR CREEK CONSTRUCTION, LLC (16.97)
ROADWAY SPECIALTIES, INC. (2.89)
Contract #08143039
Totals1128804.520.001029579.6293.5

CountyGONZALES
HighwaySH 97
FromCO RD 112
ToUS 183
CSJ0347-01-028
Proj IDSTP 2015(427)
Work TypeREHABILITATE ROADWAY
 
12.81410157843.7710270586.3599.9
Work Order02-18-15
Work Began04-08-15
Work Completed
Time Computed04-08-15
Contract Working Days300
Addl Days Granted43
Working Days Charged340
Percent Time Used99
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0347-01-028
COWBELL TRAFFIC SERVICE, INC. (0.39)
MURRAY CONSTRUCTION (0.50)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.24)
ROADWAY SPECIALTIES, INC. (1.60)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (0.00)
RAMI MATERIALS TRANSPORT, LLC (0.00)
BILL HALL JR. TRUCKING, LTD. (0.00)
GREEN MILLING GROUP (0.11)
Contract #12143205
Totals10157843.770.0010270586.3599.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7