Monthly Local Let Maintenance Report For Waco District As Of May 10, 2018 Page 1 Of 5

Last Update: Thursday, May 10, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBOSQUE
HighwaySH0006
FromVARIOUS ROADWAYS IN BELL, CORYELL,
ToHAMILTON AND BOSQUE COUNTIES
CSJ6225-66-001
Proj IDRMC - 622566001
Work TypeMULTI-COUNTY PAVEMENT MARKINGS
 
0.010150375.00147830.1098.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-23-11
Work Began10-07-11
Work Completed
Time Computed10-10-11
Contract Working Days84
Addl Days Granted0
Working Days Charged50
Percent Time Used59
Contractor(s)
DEANGELO BROTHERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6225-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07110904
Totals150375.000.00147830.1098.3

CountyHILL
HighwaySH0171
FromSTATE MAINTAINED ROADWAYS
ToHILL COUNTY
CSJ6250-54-001
Proj IDRMC - 625054001
Work TypeMOWING ROW & LITTER PICKUP AND DISPOSAL
 
221.740209531.30214580.6099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-10-13
Work Began06-18-13
Work Completed
Time Computed06-18-13
Contract Working Days124
Addl Days Granted0
Working Days Charged68
Percent Time Used54
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6250-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12120904
Totals209531.300.00214580.6099.9

CountyMCLENNAN
HighwayUS0084
FromBELL, BOSQUE, CORYELL, FALLS,
ToHAMILTON, LIMESTONE & MCLENNAN COUNTIES
CSJ6253-98-001
Proj IDRMC - 625398001
Work TypeMAINTENANCE OF ILLUMINATION SYSTEMS
 
0.01084788.0064980.93100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-04-13
Work Began06-17-13
Work Completed07-22-14
Time Computed06-17-13
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04130901
Totals84788.000.0064980.93100.0

CountyBELL
HighwayUS0190
FromVARIOUS ROADWAYS IN
ToBELL COUNTY
CSJ6288-92-001
Proj IDRMC - 628892001
Work TypeCLEANING AND SWEEPING
 
0.100274795.00297332.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-16-15
Work Began10-26-15
Work Completed
Time Computed10-26-15
Contract Working Days120
Addl Days Granted30
Working Days Charged114
Percent Time Used76
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07150902
Totals274795.000.00297332.5099.9

CountyFALLS
HighwaySH0007
FromVARIOUS ROADWAYS IN FALLS, LIMESTONE &
ToHILL COUNTIES
CSJ6288-93-001
Proj IDRMC - 628893001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.01046527.660.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days77
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
H. T. S. CONSTRUCTION ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07150903
Totals46527.660.000.000.0

CountyHAMILTON
HighwaySH0006
FromVARIOUS ROADWAYS IN BOSQUE, CORYELL,
ToAND HAMILTON COUNTIES
CSJ6288-94-001
Proj IDRMC - 628894001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.01047693.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days89
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
H. T. S. CONSTRUCTION ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07150901
Totals47693.000.000.000.0

CountyMCLENNAN
HighwayUS0084
FromVARIOUS ROADWAYS IN
ToMCLENNAN COUNTY
CSJ6288-95-001
Proj IDRMC - 628895001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.01095866.1173602.29100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-09-15
Work Began09-20-15
Work Completed06-01-17
Time Computed09-20-15
Contract Working Days83
Addl Days Granted70
Working Days Charged148
Percent Time Used96
Contractor(s)
H. T. S. CONSTRUCTION ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07150904
Totals95866.110.0073602.29100.0

CountyBELL
HighwayFM0487
FromVARIOUS LOCATIONS
ToIN BELL COUNTY
CSJ6290-11-001
Proj IDRMC - 629011001
Work TypeTREE TIMMING AND TREE REMOVAL
 
0.100153210.00159205.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-22-16
Work Began01-25-16
Work Completed
Time Computed01-25-16
Contract Working Days168
Addl Days Granted0
Working Days Charged62
Percent Time Used36
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6290-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10150904
Totals153210.000.00159205.0099.9

CountyHILL
HighwayUS0077
FromVARIOUS ROADWAYS IN FALLS, HILL
ToAND LIMESTONE COUNTIES
CSJ6290-14-001
Proj IDRMC - 629014001
Work TypeTREE TRIMMING AND REMOVAL
 
0.010242090.25110988.6445.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-08-16
Work Began02-16-16
Work Completed
Time Computed02-16-16
Contract Working Days180
Addl Days Granted0
Working Days Charged36
Percent Time Used20
Contractor(s)
DRC EMERGENCY SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6290-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10150903
Totals242090.250.00110988.6445.8

CountyFALLS
HighwayUS0077
FromVAR ROADWAYS IN FALLS, BOSQUE, HILL,
ToCORYELL, HAMILTON & LIMESTONE COUNTIES
CSJ6292-57-001
Proj IDRMC - 629257001
Work TypeCLEANING AND SWEEING HIGHWAYS
 
0.010144625.8024753.4917.1
Work Order12-07-15
Work Began12-09-15
Work Completed
Time Computed12-09-15
Contract Working Days220
Addl Days Granted0
Working Days Charged52
Percent Time Used23
Contractor(s)
H. T. S. CONSTRUCTION ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09150902
Totals144625.800.0024753.4917.1

CountyMCLENNAN
HighwayUS0084
FromVARIOUS ROADWAYS IN
ToMCLENNAN COUNTY
CSJ6293-92-001
Proj IDRMC - 629392001
Work TypeGRAFFITI REMOVAL (NON-SITE SPECIFIC)
 
0.01069150.0027950.3940.4
Work Order04-27-16
Work Began09-13-16
Work Completed
Time Computed05-16-16
Contract Working Days40
Addl Days Granted0
Working Days Charged5
Percent Time Used12
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6293-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03160902
Totals69150.000.0027950.3940.4

CountyBELL
HighwaySH0036
FromVARIOUS ROADWAYS
ToIN BELL COUNTY
CSJ6295-41-001
Proj IDRMC - 629541001
Work TypeRURAL MOWING
 
0.100190640.00190130.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-11-16
Work Began06-06-16
Work Completed10-31-16
Time Computed06-01-16
Contract Working Days40
Addl Days Granted0
Working Days Charged23
Percent Time Used57
Contractor(s)
LONESTAR HAWK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150905
Totals190640.000.00190130.00100.0

CountyCORYELL
HighwaySH0036
FromVARIOUS ROADWAYS IN
ToCORYELL COUNTY
CSJ6295-42-001
Proj IDRMC - 629542001
Work TypeMOWING AND LITTER REMOVAL
 
0.100242481.24196626.36100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-27-16
Work Began06-13-16
Work Completed11-22-16
Time Computed06-13-16
Contract Working Days135
Addl Days Granted0
Working Days Charged91
Percent Time Used67
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6295-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150901
Totals242481.240.00196626.36100.0

CountyHAMILTON
HighwaySH0006
FromVARIOUS ROADWAYS
ToIN HAMILTON COUNTY
CSJ6295-43-001
Proj IDRMC - 629543001
Work TypeMOWING AND LITTER
 
0.100156336.95153033.96100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-26-16
Work Began06-01-16
Work Completed12-09-16
Time Computed06-01-16
Contract Working Days73
Addl Days Granted0
Working Days Charged42
Percent Time Used57
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6295-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150902
Totals156336.950.00153033.96100.0

CountyHILL
HighwaySH0022
FromVARIOUS ROADWAYS
ToIN HILL COUNTY
CSJ6295-44-001
Proj IDRMC - 629544001
Work TypeMOWING AND LITTER REMOVAL
 
0.100280922.12280421.05100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-23-16
Work Began06-20-16
Work Completed04-28-17
Time Computed06-01-16
Contract Working Days120
Addl Days Granted0
Working Days Charged78
Percent Time Used65
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150904
Totals280922.120.00280421.05100.0

CountyBELL
HighwaySL0363
FromVARIOUS ROADWAYS IN
ToBELL COUNTY
CSJ6295-50-001
Proj IDRMC - 629550001
Work TypeURBAN MOWING
 
0.100206108.04206108.0499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-11-16
Work Began06-06-16
Work Completed
Time Computed06-01-16
Contract Working Days75
Addl Days Granted0
Working Days Charged38
Percent Time Used50
Contractor(s)
LONESTAR HAWK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150903
Totals206108.040.00206108.0499.9

CountyMCLENNAN
HighwaySH0006
FromVAR RDWYS IN BELL, BOSQUE, FALLS, HIILL,
ToCORYELL, HAMILTON, LIMESTONE, MCLENNAN
CSJ6297-29-001
Proj IDRMC - 629729001
Work TypeLARGE SIGN MAINTENANCE (DISTRICT WIDE)
 
0.010176300.00500324.4299.9
Work Order05-13-16
Work Began10-05-16
Work Completed
Time Computed05-23-16
Contract Working Days365
Addl Days Granted240
Working Days Charged572
Percent Time Used94
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03160903
Totals176300.000.00500324.4299.9

CountyCORYELL
HighwayUS0084
From3502 E. MAIN
ToGATESVILLE, TEXAS 76520
CSJ6297-56-001
Proj IDSUP - 629756001
Work TypeJANITORIAL SERVICES - CORYELL CO.
 
0.1008556.007500.1187.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-18-15
Work Began12-01-15
Work Completed
Time Computed12-01-15
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6297-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11150930
Totals8556.000.007500.1187.6

CountyHILL
HighwayFM0067
FromVARIOUS BRIDGES IN BELL, HILL AND
ToLIMESTONE COUNITES
CSJ6298-15-001
Proj IDBPM - 629815001
Work TypeBRIDGE PREVENTIVE MAINTENANCE
 
0.010231687.00228417.22100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-24-16
Work Began09-06-16
Work Completed11-01-16
Time Computed09-06-16
Contract Working Days70
Addl Days Granted0
Working Days Charged39
Percent Time Used55
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6298-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160901
Totals231687.000.00228417.22100.0

CountyHILL
HighwayFM3370
FromFM 3370
To@ AQUILLA ISD
CSJ6299-28-001
Proj IDRMC - 629928001
Work TypeADD SHOULDER AND WIDEN EXISTING ROADWAY
 
0.100216593.00208312.40100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-13-16
Work Began06-20-16
Work Completed08-01-16
Time Computed06-15-16
Contract Working Days31
Addl Days Granted0
Working Days Charged9
Percent Time Used29
Contractor(s)
BRETT CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6299-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04160901
Totals216593.000.00208312.40100.0

page 1 | page 2 | page 3 | page 4 | page 5