Monthly State Let Construction Report For Waco District As Of Mar 13, 2024 Page 4 Of 4

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBOSQUE
HighwayFM 2114
FromCR 3620
ToBRAZOS RIVER
CSJ2305-01-014
Proj IDSTP 2023(895)VRU
Work TypeREHABILITATION OF EXISTING ROAD
 
4.3408851170.301647571.6418.6
CountyBOSQUE
HighwayFM 2114
FromFM 56
ToCR 3620
CSJ2305-01-017
Proj IDF 2023(896)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.8564259319.622133947.8050.1
Work Order07-19-23
Work Began09-19-23
Work Completed
Time Computed08-18-23
Contract Working Days315
Addl Days Granted0
Working Days Charged95
Percent Time Used30
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2305-01-014
ROADWAY SPECIALTIES, INC. (1.68)
CAP RIVER LLC (2.02)
CHEROKEE SERVICES (0.06)
MURRAY CONSTRUCTION (0.56)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (3.30)
PROFESSIONAL TRAFFIC CONTROL LLC (0.11)
COLD CREEK CONSTRUCTION, LTD (1.28)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.90)
SAN-ANN-CO., INC. (0.29)
TRAFFIC HIGHWAY MAINTENANCE, LLC (1.22)
Contract #06233209
Totals13110489.92254624.003781519.4428.8

CountyMCLENNAN
HighwaySL 340
FromFM 3051
ToUS 84
CSJ2311-01-042
Proj IDF 2024(330)
Work TypeOVERLAY
 
1.8123759444.640.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-04-24
Work Began00-00-00
Work Completed
Time Computed02-03-24
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 2311-01-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11233209
Totals3759444.640.000.000.0

CountyBELL
HighwaySL 121
FromLAKE RD (FM 439)
ToSOUTH OF W AVENUE O
CSJ2502-01-021
Proj IDF 2021(093)
Work TypeWIDEN NON-FREEWAY
 
3.08429180209.0020726284.1671.0
Work Order11-15-21
Work Began01-04-22
Work Completed
Time Computed12-15-21
Contract Working Days480
Addl Days Granted0
Working Days Charged410
Percent Time Used85
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2502-01-021
TOTAL HIGHWAY MAINTENANCE, LLC (0.43)
TRP CONSTRUCTION GROUP, LLC (0.84)
VOGES DRILLING CO. (0.00)
DIIBS SPECIALISTS, LLC (0.41)
TEXAS MATERIALS GROUP, INC. (20.08)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (9.02)
CEN TEX HYDROSEED, INC. (1.46)
EAGLE CONSTRUCTION LLC (1.07)
GEORGE MEEKS LANDPRO, INC. (0.21)
FARR FOUNDATION, INC. (0.86)
R K STEPHENS CONSTRUCTION, LLC (7.11)
CHEROKEE SERVICES (0.18)
J.H. PAINTING COMPANY (0.10)
HERMANOS STEEL, LLC (0.26)
DIAMOND K MATERIALS (0.20)
MILLER SPRINGS MATERIALS, L.L.C. (2.21)
PANTHER CREEK TRANSPORTATION, INC. (0.03)
KELLER NORTH AMERICA, INC. (0.00)
HODGES AND SON CONSTRUCTION COMPANY, INC. (0.62)
HERMANOS STEEL, LLC (0.00)
CENTRAL TEXAS CURB CUTTERS (0.06)
HARD AS A ROCK CONCRETE CONSTRUCTION LLC (3.58)
GORDILLO TRUCKING, INC, (0.10)
Contract #08213207
Totals29180209.00910921.3420726284.1671.0

CountyHILL
HighwayFM 2959
FromSH 81
ToUS 77
CSJ3030-01-010
Proj IDC 3030-1-10
Work TypeSAFETY IMPROVEMENT PROJECTS
 
6.93212787365.870.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-02-24
Work Began00-00-00
Work Completed
Time Computed03-03-24
Contract Working Days202
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3030-01-010
BEAR CREEK CONSTRUCTION, LLC (20.69)
D. I. J. CONSTRUCTION, INC. (0.79)
Contract #01243008
Totals12787365.870.000.000.0

CountyMCLENNAN
HighwayFM 3268
FromFM 185
ToFM 3047
CSJ3448-02-007
Proj IDF 2B23(075)
Work TypeREHABILITATION OF EXISTING ROAD
 
2.3052735685.611314626.3248.0
Work Order09-08-23
Work Began10-19-23
Work Completed
Time Computed10-08-23
Contract Working Days105
Addl Days Granted0
Working Days Charged46
Percent Time Used43
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 3448-02-007
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.81)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.58)
J. H. ODEN CONTRACTING COMPANY (2.44)
MURRAY CONSTRUCTION (0.72)
WEST TEXAS ROCK RESOURCES, LLC (0.25)
BEAR CREEK CONSTRUCTION, LLC (13.95)
D. I. J. CONSTRUCTION, INC. (1.01)
Contract #08233036
Totals2735685.61435489.571314626.3248.0

CountyBELL
HighwaySH 201
FromAIRPORT PLAZA DRIVEWAY
ToSH 195
CSJ3534-02-007
Proj IDF 2024(115)
Work TypeOVERLAY
 
5861341.86221495.253.7
Work Order11-16-23
Work Began02-19-24
Work Completed
Time Computed12-16-23
Contract Working Days120
Addl Days Granted0
Working Days Charged7
Percent Time Used5
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3534-02-007
FORTSON CONTRACTING, INC. (0.94)
MOBILE ENTERPRISES, INC. (0.39)
TRP CONSTRUCTION GROUP, LLC (3.33)
WILKO INDUSTRIAL, L.L.C. (0.83)
TEX OP CONSTRUCTION, LP (3.34)
Contract #10233014
Totals5861341.86221495.25221495.253.7

page 1 | page 2 | page 3 | page 4