Monthly Local Let Maintenance Report For Tyler District As Of May 10, 2018 Page 1 Of 4

Last Update: Thursday, May 10, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHENDERSON
HighwayUS0175
FromVARIOUS ROADWAYS IN THE
ToATHENS MAINTENANCE SECTION
CSJ6272-05-001
Proj IDRMC - 627205001
Work TypePAINT
 
0.01023318.75379608.72100.0
CountyVAN ZANDT
HighwaySH0019
FromVARIOUS ROADWAYS IN
ToTHE CANTON MAINTENANCE SECTION
CSJ6272-05-002
Proj IDRMC - 627205002
Work TypePAINT
 
0.01023318.7559964.01100.0
CountyRUSK
HighwayUS0259
FromVARIOUS ROADWAYS IN THE
ToHENDERSON MAINTENANCE SECTIONN
CSJ6272-05-003
Proj IDRMC - 627205003
Work TypePAINT
 
0.01023318.7560837.79100.0
CountyCHEROKEE
HighwayUS0079
FromVARIOUS ROADWAYS IN THE
ToJACKSONVILLE MAINTENANCE SECTION
CSJ6272-05-004
Proj IDRMC - 627205004
Work TypePAINT
 
0.01012009.3866767.05100.0
CountyGREGG
HighwaySH0031
FromVARIOUS ROADWAYS IN THE
ToLONGVIEW MAINTENANCE SECTION
CSJ6272-05-005
Proj IDRMC - 627205005
Work TypePAINT
 
0.01023318.7549248.01100.0
CountyWOOD
HighwayUS0080
FromVARIOUS ROADWAYS IN THE
ToMINEOLA MAINTENACE SECTION
CSJ6272-05-006
Proj IDRMC - 627205006
Work TypePAINT
 
0.01023318.7535210.94100.0
CountyANDERSON
HighwayUS0287
FromVARIOUS ROADWAYS IN THE
ToPALESINE MAINTENANCE SECTION
CSJ6272-05-007
Proj IDRMC - 627205007
Work TypePAINT
 
0.01023318.758365.21100.0
CountySMITH
HighwaySH0110
FromVARIOUS ROADWAYS IN THE
ToTYLER MAINTENANCE SECTION
CSJ6272-05-008
Proj IDRMC - 627205008
Work TypePAINT
 
0.01023318.7548327.90100.0
CountyCHEROKEE
HighwayUS0069
FromVARIOUS ROADWAYS IN THE
ToRUSK MAINTENANCE SECTION
CSJ6272-05-009
Proj IDRMC - 627205009
Work TypePAINT
 
0.01012009.3834335.47100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-14-14
Work Began09-25-14
Work Completed09-15-16
Time Computed09-01-14
Contract Working Days255
Addl Days Granted255
Working Days Charged509
Percent Time Used99
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6272-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06141001
Totals187250.010.00742665.10100.0

CountySMITH
HighwayUS0069
FromVARIOUS LOCATIONS IN THE
ToTYLER AND JACKSONVILLE SECTIONS
CSJ6285-92-001
Proj IDRMC - 628592001
Work TypeGUARDRAIL REPAIR
 
0.010105963.00453562.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed09-12-17
Time Computed00-00-00
Contract Working Days255
Addl Days Granted255
Working Days Charged509
Percent Time Used99
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06151004
Totals105963.000.00453562.00100.0

CountyRUSK
HighwayUS0079
FromVARIOUS ROADWAYS IN
ToRUSK AND CHEROKEE COUNTIES
CSJ6290-48-001
Proj IDEMC - 629048001
Work TypeEMERGENCY DEBRIS & TREE REMOVAL
 
0.010435655.003070764.75100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-26-15
Work Completed08-11-15
Time Computed00-00-00
Contract Working Days52
Addl Days Granted0
Working Days Charged33
Percent Time Used63
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6290-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06151044
Totals435655.000.003070764.75100.0

CountyGREGG
HighwaySH0031
FromVARIOUS ROADWAYS IN
ToGREGG COUNTY
CSJ6294-86-001
Proj IDRMC - 629486001
Work TypeTREE REMOVAL
 
0.001159225.00318470.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-16-16
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted255
Working Days Charged500
Percent Time Used98
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6294-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11151001
Totals159225.0012470.00318470.0099.9

CountyHENDERSON
HighwaySH0019
FromVARIOUS ROADWAYS IN
ToTHE TYLER DISTRICT
CSJ6300-22-001
Proj IDRMC - 630022001
Work TypePAINT
 
0.001239245.00828631.4399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-22-16
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted255
Working Days Charged412
Percent Time Used80
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6300-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161003
Totals239245.0042388.71828631.4399.9

CountySMITH
HighwaySL0323
FromSL 323 IN
ToSMITH COUNTY
CSJ6303-40-001
Proj IDRMC - 630340001
Work TypeSLOPE FAILURE
 
0.100182290.00461048.79100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-05-16
Work Completed10-02-17
Time Computed00-00-00
Contract Working Days40
Addl Days Granted3
Working Days Charged41
Percent Time Used95
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6303-40-001
NEWSTAR DRILLING, INC (2.22)
Contract #08161001
Totals182290.000.00461048.79100.0

CountyHENDERSON
HighwaySH0031
FromATHENS MTCE. SECTION
ToHENDERSON CO.
CSJ6303-70-001
Proj IDSUP - 630370001
Work TypeLANDSCAPE ROW MTCE.
 
0.01014898.0013752.0092.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged607
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6303-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161030
Totals14898.001146.0013752.0092.3

CountyHENDERSON
HighwaySH0031
FromATHENS MTCE. OFFICE
ToHENDERSON CO
CSJ6303-71-001
Proj IDSUP - 630371001
Work TypeLAWN MTCE.
 
0.01016782.0010661.5063.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged607
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6303-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161031
Totals16782.001079.5010661.5063.5

CountyGREGG
HighwaySL0281
FromLONGVIEW MTCE. OFFICE
ToGREGG CO
CSJ6303-72-001
Proj IDSUP - 630372001
Work TypeLAWN MTCE
 
0.01031110.0022230.0071.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged607
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6303-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161032
Totals31110.001230.0022230.0071.4

CountySMITH
HighwayIH0020
FromIH 20 EAST & WEST DERRICK PARK
ToSH 31 @ FM 2661
CSJ6303-73-001
Proj IDSUP - 630373001
Work TypePICNIC AREA MTCE.
 
0.010124980.00104656.0083.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged607
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6303-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161033
Totals124980.006046.00104656.0083.7

CountySMITH
HighwayIH0020
FromIH 20 @ US 69 &
ToIH 20 @ US 271
CSJ6303-74-001
Proj IDSUP - 630374001
Work TypeTRAFFIC ISLAND LANDSCAPE MTCE
 
0.01029450.0024505.5083.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged607
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161034
Totals29450.002325.0024505.5083.2

CountyWOOD
HighwayUS0080
FromUS 80(2), US 69, FM 2088
ToSH 37(2)
CSJ6303-75-001
Proj IDSUP - 630375001
Work TypePICNIC AREA MTCE
 
0.010122429.0497752.8279.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged607
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6303-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161035
Totals122429.044440.7797752.8279.8

CountyWOOD
HighwaySL0564
FromMINEOLA AO & MTCE OFFICE
ToSL 564, WOOD CO
CSJ6303-76-001
Proj IDSUP - 630376001
Work TypeLAWN MTCE
 
0.01026367.0020515.7677.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged607
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6303-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161036
Totals26367.001459.2820515.7677.8

CountySMITH
HighwaySH0155
FromTYLER AO & MTCE OFFICE
ToSH 155 S IN NOONDAY
CSJ6303-78-001
Proj IDSUP - 630378001
Work TypeJANITORIAL MTCE
 
0.00143605.0435582.7881.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged607
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161037
Totals43605.041439.5035582.7881.6

CountyANDERSON
HighwaySH0019
FromPALESTINE MTCE OFFICE
ToANDERSON CO
CSJ6303-79-001
Proj IDSUP - 630379001
Work TypeJANITORIAL MTCE
 
0.01022127.0418128.4681.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged607
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161038
Totals22127.04766.5918128.4681.9

CountyCHEROKEE
HighwaySL0456
FromJACKSONVILLE MTCE OFFICE
ToSL 456
CSJ6303-80-001
Proj IDSUP - 630380001
Work TypeLAWN MTCE
 
0.01012060.007317.5060.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged607
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161039
Totals12060.00627.507317.5060.6

CountyCHEROKEE
HighwayUS0069
FromRUSK MTCE OFFICE
ToUS 69
CSJ6303-81-001
Proj IDSUP - 630381001
Work TypeLAWN MTCE
 
0.01014160.008225.0058.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged607
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161040
Totals14160.00380.008225.0058.0

CountyCHEROKEE
HighwayUS0069
FromJVILLE/RUSK MTCE SECTIONS
ToCHEROKEE CO
CSJ6303-82-001
Proj IDSUP - 630382001
Work TypeLANDSCAPE ISLAND MTCE
 
0.01018052.669501.4052.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged607
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161041
Totals18052.66475.079501.4052.6

CountyRUSK
HighwaySH0064
FromHENDERSON MTCE. SECTION
ToRUSK CO.
CSJ6303-86-001
Proj IDSUP - 630386001
Work TypeLITTER PICK UP
 
0.001373499.73183098.5849.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days1,095
Addl Days Granted0
Working Days Charged607
Percent Time Used55
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161045
Totals373499.730.00183098.5849.0

CountyCHEROKEE
HighwayUS0069
FromCROSS STRUCTURE TRM 398+1.551 US 69
ToCROSS STRUCTURE TRM 322+1.041 FM 59
CSJ6305-76-001
Proj IDRMC - 630576001
Work TypeCULVERT REPAIR
 
0.00160270.0053650.0090.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-19-17
Work Completed
Time Computed00-00-00
Contract Working Days38
Addl Days Granted0
Working Days Charged40
Percent Time Used105
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6305-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07171001
Totals60270.000.0053650.0090.9

page 1 | page 2 | page 3 | page 4