Monthly State Let Construction Report For Tyler District As Of Jul 13, 2018 Page 1 Of 3

Last Update: Friday, July 13, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyVAN ZANDT ETC
HighwayUS 80 ETC
FromGR SALINE WCL, 1.5 MI W OF SH110, E
ToFM 857
CSJ0095-07-059
Proj IDSTP 2018(257)
Work TypeSEAL COAT AND PAVEMENT MARKINGS
 
143.10910067448.296616814.1465.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-12-18
Work Began05-15-18
Work Completed
Time Computed00-00-00
Contract Working Days91
Addl Days Granted0
Working Days Charged40
Percent Time Used43
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0095-07-059
STRIPING TECHNOLOGY, L.P. (18.98)
BRYDL CONTRACTING, INC. (1.40)
INNOVATIVE ROADWAY, LLC (2.16)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (2.75)
Contract #12173205
Totals10067448.29949768.296616814.1465.7

CountyGREGG
HighwayUS 80
FromSL 485, E 1.15 MI
ToLOCKERPLANT RD IN GLADEWATER
CSJ0096-04-066
Proj IDNH 2017(893)
Work TypeGR,BS,HMAC SURF,STRM SWR,C&G,SIGNS
 
0.8373538933.212032165.4757.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-16-17
Work Began06-20-17
Work Completed
Time Computed00-00-00
Contract Working Days190
Addl Days Granted99
Working Days Charged209
Percent Time Used72
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0096-04-066
ISAACS CONSTRUCTION SERVICES, LLC. (1.24)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.93)
PANOLA SIGN & BARRICADE, INC. (0.39)
MAC TRANSPORTATION, LTD, L.L.P. (1.97)
STRIPING TECHNOLOGY, L.P. (0.76)
TEXOP CONSTRUCTION (1.84)
SOUTHWEST ENVIRONMENT SERIVES, LLC (2.04)
Contract #04173030
Totals3538933.21104760.292032165.4757.4

CountyHENDERSON
HighwaySH 19
FromFM 1615, SOUTH 3.8 MI
To0.3 MI S OF COON CREEK BRIDGE
CSJ0108-04-037
Proj IDSTP 1702(091)
Work TypeGR,STRS,ACP SURF,FLEX BS,CAM,OCST
 
3.8364949012.531949131.9639.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-17
Work Began08-08-17
Work Completed
Time Computed00-00-00
Contract Working Days295
Addl Days Granted0
Working Days Charged185
Percent Time Used62
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0108-04-037
COLD CREEK CONSTRUCTION, LTD (1.34)
J & M CONTRACTING, COMPANY (13.03)
TOTAL HIGHWAY MAINTENANCE, LLC (0.74)
SAN-ANN-CO., INC. (0.51)
FORTSON CONTRACTING, INC. (0.15)
AREA WIDE PROTECTIVE, INC. (0.29)
NIXON ENGINEERING, L.L.C. (0.09)
WACO DRILLING CO., INC. (0.02)
BIG CREEK CONSTRUCTION, LTD. (33.03)
Contract #05173028
Totals4949012.53122965.291949131.9639.3

CountyANDERSON
HighwaySH 19
From3.6 MI N OF FM 837(HENDERSON C/L),S
To0.4 MI N OF FM 321 AT MONTALBA
CSJ0108-06-051
Proj IDSTP 2013(637)
Work TypeGR,STRS,HMA BS & SURF,OCST,LVL-UP
 
11.81312487715.8713226800.1899.9
Work Order07-10-14
Work Began09-02-14
Work Completed
Time Computed07-26-14
Contract Working Days453
Addl Days Granted140
Working Days Charged516
Percent Time Used87
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0108-06-051
COLD CREEK CONSTRUCTION, LTD (0.82)
FORTSON CONTRACTING, INC. (0.45)
HIGHWAY 19 CONSTRUCTION, LLC (10.97)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.35)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.15)
STRIPING TECHNOLOGY, L.P. (1.23)
FARR FOUNDATION, INC. (0.64)
SAN-ANN-CO., INC. (0.04)
MURRAY CONSTRUCTION (0.49)
Contract #05143205
Totals12487715.87348069.1513226800.1899.9

CountyANDERSON
HighwayUS 287
From0.154 MI S OF SH 294 IN ELKHART, S
ToHOUSTON C/L (3 MI N OF BU 287V)
CSJ0109-02-026
Proj IDSTP 2018(809)
Work TypePLNG,ACP,OCST,PFC,PVT MRKG
 
4.9673987345.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-11-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days73
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0109-02-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183256
Totals3987345.300.000.000.0

CountyANDERSON ETC
HighwayUS 287 ETC
FromFREESTONE C/L SE
To1.7 MI SE OF FM 488 (FREESTONE CL),
CSJ0122-04-038
Proj IDSTP 2017(355)
Work TypeSEAL COAT & PAVEMENT MARKINGS
 
216.06311487064.259556630.7283.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-13-17
Work Began08-08-17
Work Completed
Time Computed00-00-00
Contract Working Days110
Addl Days Granted22
Working Days Charged131
Percent Time Used99
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0122-04-038
STRIPING TECHNOLOGY, L.P. (16.08)
BRYDL CONTRACTING, INC. (1.55)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (0.35)
Contract #01173005
Totals11487064.25819255.579556630.7283.1

CountyCHEROKEE
HighwayUS 84
FromUS 69 IN RUSK, N & E
To.46 MI E OF SH 110, NEAR PR50
CSJ0123-03-021
Proj IDC 123-3-21
Work TypeMILL & INLAY, SURF, PVT MRKG
 
1.3382742753.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-11-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0123-03-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183012
Totals2742753.500.000.000.0

CountyRUSK
HighwayUS 259
FromUS 79 IN HENDERSON, S
ToJARRELL CREEK, 2.8 MI N OF FM 1798
CSJ0138-04-046
Proj IDC 138-4-46
Work TypePLNG,ACP OVRLY,OCST,PFC,PVT MRKG
 
7.6225220900.060.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-11-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days71
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0138-04-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183246
Totals5220900.060.000.000.0

CountyHENDERSON
HighwayBS 31H
FromBS 19 IN ATHENS, NE
To0.1 MI E OF US175/SL7 (PVMNT JOINT)
CSJ0164-01-071
Proj IDC 164-1-71
Work TypePFC SURF,BRG RAIL,MBGF,PVT MRKG
 
3.2011161999.490.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0164-01-071
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07183222
Totals1161999.490.000.000.0

CountyHENDERSON
HighwaySH 31
FromFM 3204(E), E
To0.5 MI W OF FM 315(C&G) IN CHANDLER
CSJ0164-03-053
Proj IDNH 2018(514)
Work TypeBS RPR,PLNG,SUPRPVE,OCST,PFC,MBGF
 
2.3062687805.15442097.9416.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-14-18
Work Began06-18-18
Work Completed
Time Computed00-00-00
Contract Working Days95
Addl Days Granted0
Working Days Charged23
Percent Time Used24
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0164-03-053
CHEROKEE SERVICES (1.69)
DIIBS SPECIALISTS (4.76)
PANOLA SIGN & BARRICADE, INC. (0.28)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.32)
STRIPING TECHNOLOGY, L.P. (1.40)
WEST TEXAS RUMBLE STRIP (0.14)
WOLFE CONSTRUCTION GROUP, INC. (0.44)
Contract #02183210
Totals2687805.15442097.94442097.9416.4

CountySMITH
HighwaySH 31
FromSW SL 323 IN TYLER, E
To0.35 MI E OF US271, BROADWAY AVE
CSJ0164-04-160
Proj IDC 164-4-160
Work TypePLNG,PVMT RPR,OCST,PVMT MRKG
 
2.4193587845.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days58
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0164-04-160
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07183246
Totals3587845.300.000.000.0

CountySMITH
HighwayUS 69
From0.37 MI S OF FM 346, S
ToCHEROKEE C/L
CSJ0191-01-085
Proj IDNH 1702(418)
Work TypePLNG,BS RPR,OCST,PFC,SUPERPAVE,MBGF
 
4.6573628777.001813339.2949.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-09-18
Work Began05-30-18
Work Completed
Time Computed00-00-00
Contract Working Days62
Addl Days Granted0
Working Days Charged17
Percent Time Used27
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0191-01-085
PANOLA SIGN & BARRICADE, INC. (0.40)
STRIPE-A-ZONE, INC. (0.37)
TEX OP CONSTRUCTION, LP (1.97)
MORRIS COUNTY CONTRACTORS, LLC (0.21)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.02)
STRIPING TECHNOLOGY, L.P. (2.55)
FREDONIA CONSTRUCTION SERVICES (0.00)
Contract #03183024
Totals3628777.001737115.021813339.2949.9

CountySMITH
HighwayFM 2493
FromFM 2813 IN GRESHAM, S
ToFM 346 IN FLINT
CSJ0191-03-081
Proj IDSTP 2013(215)
Work TypeGR,FLX BS,ACP,CULV EXT&RPLCMT,SIGNS
 
2.24114458790.480.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days506
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0191-03-081
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07183036
Totals14458790.480.000.000.0

CountyHENDERSON
HighwayUS 175
From0.1 MI SE OF FM 804, SE
ToCR 4712 (END OF C-S)
CSJ0198-01-023
Proj IDNH 1402(195)
Work TypeRECONSTR GR, STRS, BS, SURF & PAV M
 
6.69539261003.8939825228.5499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-21-14
Work Began04-06-15
Work Completed
Time Computed00-00-00
Contract Working Days605
Addl Days Granted30
Working Days Charged599
Percent Time Used94
Contractor(s)
A. L. HELMCAMP, INC.
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0198-01-023
DUSTIN ALLEN, INC. (0.36)
MURRAY CONSTRUCTION (0.22)
STRIPING TECHNOLOGY, L.P. (0.31)
SAN-ANN-CO., INC. (0.21)
KLP COMMERCIAL, LLC (4.91)
KENSAR LLC DBA S & S TRUCKING (1.88)
BIG CREEK CONSTRUCTION, LTD. (0.00)
ENVIRODREDGE (0.20)
TEXAS ORGANIC ENTERPRISES, LTD (0.07)
A. L. CONSTRUCTION, LLC (0.03)
NIXON ENGINEERING, L.L.C. (0.00)
Contract #08143055
Totals39261003.891009672.9239825228.5499.9

CountyHENDERSON
HighwayUS 175
From1.1 MI E OF LP 60E @ LARUE, SE
To0.85 MI E OF FM 315, IN POYNOR
CSJ0198-02-027
Proj IDNH 2015(423)
Work TypeRECONSTR GR, STRS, BS, SURF & PAV M
 
4.73137849155.3141536158.0099.9
Work Order06-30-15
Work Began10-06-15
Work Completed
Time Computed07-16-15
Contract Working Days654
Addl Days Granted4
Working Days Charged528
Percent Time Used80
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0198-02-027
N-LINE TRAFFIC MAINTENANCE, L.P. (0.20)
WOLFE CONSTRUCTION GROUP, INC. (0.83)
K & S UTILITY CONTRACTORS, INC. (4.02)
OTTO TRUCKING, INC. (3.31)
APAC-TEXAS, INC. (19.01)
BREDA COMPANY, INC. (2.68)
ANTIGO CONSTRUCTION, INC. (0.02)
LAYFIELD CONSTRUCTION, INC (0.40)
A BROTHERS MILLING, LLC (0.18)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.18)
STRIPING TECHNOLOGY, L.P. (0.54)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.00)
MCL CONTRACTING, LLC (0.04)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (1.51)
PRIMATE CONSTRUCTION, INC. (0.00)
CARTHAGE DRILLING, INC. (0.01)
Contract #04153201
Totals37849155.31135611.6941536158.0099.9

CountyHENDERSON
HighwayUS 175
From0.85 MI E OF FM 315, IN POYNOR
ToANDERSON C/L
CSJ0198-02-035
Proj IDC 198-2-35
Work TypeGR,SUB BS,BS,HMAC,DRAIN STRS,SIGNS
 
0.9237052578.984147873.9858.8
CountyANDERSON
HighwayUS 175
From1.9 MI S OF FM 315 (HENDERSON C/L)
To0.5 MI NW OF SH 155 AT FRANKSTON
CSJ0198-03-027
Proj IDNH 1502(561)
Work TypeGR,SUB BS,BS,HMAC,DRAIN STRS,SIGNS
 
3.80420312971.6612888040.3663.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-17-16
Work Began05-04-16
Work Completed
Time Computed00-00-00
Contract Working Days571
Addl Days Granted37
Working Days Charged377
Percent Time Used62
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0198-02-035
STRIPING TECHNOLOGY, L.P. (0.36)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.16)
MARCOM"S MOWING SERVICE, LLC (0.21)
FORTSON CONTRACTING, INC. (0.04)
STRIPING SYSTEMS, INC. (0.00)
FARR FOUNDATION, INC. (0.32)
BIG CREEK CONSTRUCTION, LTD. (27.92)
NIXON ENGINEERING (0.03)
A. L. CONSTRUCTION, LLC (0.25)
Contract #12153202
Totals27365550.64277076.4217035914.3462.2

CountyCHEROKEE
HighwayUS 69
From2.0 MI N OF FM 1247,NEAR WELLS,S
To0.9 MI S OF FM 1247 (ANGELINA C/L)
CSJ0199-03-028
Proj IDHP 2013(803)
Work TypeGRDG,STRS,BASE,OCST,SURF,PVT MRKG
 
2.89617687832.877772230.1643.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-05-16
Work Began01-23-17
Work Completed
Time Computed00-00-00
Contract Working Days350
Addl Days Granted54
Working Days Charged190
Percent Time Used47
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0199-03-028
AMERICAN REMEDIATION OPTIONS, INC. (2.08)
STRIPING TECHNOLOGY, L.P. (0.52)
STRIPING SYSTEMS, INC. (0.00)
TEX OP CONSTRUCTION, LP (1.05)
LUDCO, INC. (1.00)
FLEX SUPPLY, LLC (0.15)
Contract #06163005
Totals17687832.871260114.367772230.1643.9

CountyANDERSON
HighwayUS 79
From1.6 MI SW OF LP 256 IN PALESTINE, S
To0.4 MI SW OF FM 645
CSJ0205-07-043
Proj IDNH 2008(510)
Work TypeGR,BS,ASPH PVT, SIGS, ILLUM,SIGNS
 
8.60141986850.1945275432.5099.9
Work Order10-24-12
Work Began11-12-12
Work Completed
Time Computed11-09-12
Contract Working Days880
Addl Days Granted147
Working Days Charged1,001
Percent Time Used97
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0205-07-043
HIGHWAY TECHNOLOGIES, INC. (0.10)
STRIPING TECHNOLOGY, L.P. (1.65)
MAC TRANSPORTATION, LTD, L.L.P. (3.12)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.39)
AMERICAN REMEDIATION OPTIONS, INC. (0.53)
DANRIDGE CONSTRUCTION, LLC. (0.30)
DUSTROL, INC. (0.20)
WEST TEXAS RUMBLE STRIP (0.05)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.68)
NORTH TEXAS REBAR, LLC (0.02)
TOTAL HIGHWAY MAINTENANCE, LLC (0.23)
P.R. PARKER COMPANY, INC. (0.00)
TEX OP CONSTRUCTION, LP (0.01)
DIRECTIONAL DRILLING (0.01)
DFW REBAR, INC. (0.01)
ROYAL REBAR (0.03)
Contract #09123003
Totals41986850.1990056.6745275432.5099.9

CountyANDERSON
HighwayUS 79
From1.5 MI EAST OF FM 2574
ToSTR#100010020601032 OVER UPRR
CSJ0206-01-049
Proj IDBR 1702(753)
Work TypeCLN/PNT GIRD,RPL RAIL,CONC DCK OVLY
 
0.6721646254.33910904.7555.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-10-17
Work Began04-02-18
Work Completed
Time Computed00-00-00
Contract Working Days136
Addl Days Granted0
Working Days Charged35
Percent Time Used25
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0206-01-049
DIAMOND SURFACE, INC. (0.52)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.31)
MORRIS COUNTY CONTRACTORS, LLC (4.76)
HOUSTON SAWING & DRILLING (0.19)
AGGREGATE TECHNOLOGIES, INC. (3.23)
GIBSON & ASSOCIATES, INC. (14.88)
PANOLA SIGN & BARRICADE, INC. (0.72)
S & S BRIDGE PAINTING, INC. (9.03)
STRIPING TECHNOLOGY, L.P. (1.94)
FREDONIA CONSTRUCTION SERVICES (0.60)
TEXOP CONSTRUCTION (1.38)
GARY A. CRAIN, INC. (0.29)
Contract #08173017
Totals1646254.3371795.00910904.7555.3

CountyCHEROKEE
HighwayUS 79
FromANDERSON C/L AT NECHES RIVER, NE
To1.2 MI NE OF FM 747, J VILLE CL
CSJ0206-03-061
Proj IDNH 1802(198)
Work TypeRECONSTR BS & SURF, WDN STR, PAV MR
 
9.6878257306.230.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days224
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0206-03-061
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183218
Totals8257306.230.000.000.0

page 1 | page 2 | page 3