Monthly State Let Maintenance Report For San Antonio District As Of Jun 08, 2018 Page 2 Of 2

Last Update: Tuesday, June 12, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyATASCOSA
HighwayIH0037
FromVARIOUS LOCATIONS IN
ToATASCOSA COUNTY
CSJ6325-77-001
Proj IDRMC - 632577001
Work TypeMOWING AND LITTER REMOVAL
 
0.001356910.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days192
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6325-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184015
Totals356910.000.000.000.0

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS IN FRIO, ATASCOSA
ToAND LASALLE COUNTIES
CSJ6325-79-001
Proj IDRMC - 632579001
Work TypeMOWING AND LITTER REMOVAL
 
0.001420886.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-05-18
Work Began00-00-00
Work Completed
Time Computed06-25-18
Contract Working Days184
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6325-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184016
Totals420886.400.000.000.0

CountyBEXAR
HighwayIH0010
FromVARIOUS LOCATIONS IN
ToSAN ANTONIO DISTRICT
CSJ6325-85-001
Proj IDRMC - 632585001
Work TypePAVEMENT REPAIR
 
0.0015251020.501731618.6032.9
Work Order02-22-18
Work Began03-02-18
Work Completed
Time Computed03-02-18
Contract Working Days365
Addl Days Granted0
Working Days Charged90
Percent Time Used24
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6325-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184213
Totals5251020.501007255.671731618.6032.9

CountyATASCOSA
HighwayFM1332
FromSH 16
ToEND OF MAINTENANCE
CSJ6325-94-001
Proj IDRMC - 632594001
Work TypeSEAL COAT
 
0.0011644676.151471775.9389.4
Work Order02-09-18
Work Began04-23-18
Work Completed
Time Computed04-02-18
Contract Working Days75
Addl Days Granted0
Working Days Charged30
Percent Time Used40
Contractor(s)
NEWMAN & KENG PAVING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6325-94-001
D. I. J. CONSTRUCTION, INC. (20.00)
BRYDL CONTRACTING, INC. (1.17)
Contract #01184214
Totals1644676.15614317.291471775.9389.4

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS IN THE
ToSAN ANTONIO DISTRICT
CSJ6326-45-001
Proj IDRMC - 632645001
Work TypePAV MARKINGS & MRKRS CENTERLINE TEXTURE
 
0.0011813510.70482048.0126.5
Work Order04-05-18
Work Began04-06-18
Work Completed
Time Computed04-06-18
Contract Working Days365
Addl Days Granted0
Working Days Charged56
Percent Time Used15
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6326-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02184208
Totals1813510.7046207.20482048.0126.5

CountyBEXAR
HighwaySH0016
FromSH 16 AT
ToELM CREEK
CSJ6327-01-001
Proj IDBPM - 632701001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.001427360.000.000.0
Work Order05-15-18
Work Began00-00-00
Work Completed
Time Computed05-28-18
Contract Working Days60
Addl Days Granted0
Working Days Charged3
Percent Time Used5
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6327-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03184213
Totals427360.000.000.000.0

CountyBANDERA
HighwaySH0016
FromVARIOUS LOCATIONS IN
ToTHE SAN ANTONIO DISTRICT
CSJ6329-34-001
Proj IDRMC - 632934001
Work TypeGUARDRAIL REPAIR
 
0.0011235997.050.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6329-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04184021
Totals1235997.050.000.000.0

page 1 | page 2