Monthly Local Let Maintenance Report For Pharr District As Of May 10, 2021 Page 4 Of 5

Last Update: Monday, May 10, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCAMERON
HighwayIH0069E
FromSAN BENITO AREA OFFICE
ToSAN BENITO MAINTENANCE OFFICE
CSJ6343-13-001
Proj IDSUP - 634313001
Work TypeTECHNICAL ASSISTANCE
 
0.01056617.6044940.2279.3
Work Order07-23-19
Work Began09-03-19
Work Completed
Time Computed09-01-19
Contract Working Days731
Addl Days Granted0
Working Days Charged607
Percent Time Used83
Contractor(s)
WORKQUEST
GOODWILL INDUSTRIES OF SOUTH TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6343-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08192133
Totals56617.602354.5344940.2279.3

CountyHIDALGO
HighwayIH0002
FromPHARR DISTRICT COMPLEX
ToPHARR AREA/MAINTENANCE OFFICE
CSJ6343-14-001
Proj IDSUP - 634314001
Work TypeGROUNDS MAINTENANCE
 
0.01061812.0046338.0074.9
Work Order07-25-19
Work Began09-11-19
Work Completed
Time Computed09-01-19
Contract Working Days731
Addl Days Granted0
Working Days Charged608
Percent Time Used83
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6343-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08192134
Totals61812.002079.0046338.0074.9

CountyCAMERON
HighwayIH0069E
FromDISTRICT WIDE
ToVARIOUS ROADWAYS
CSJ6343-15-001
Proj IDSUP - 634315001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010415015.18398682.5196.0
Work Order08-18-19
Work Began09-05-19
Work Completed
Time Computed09-01-19
Contract Working Days731
Addl Days Granted0
Working Days Charged604
Percent Time Used82
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6343-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08192135
Totals415015.1821777.00398682.5196.0

CountySTARR
HighwayUS0083
FromROMA AREA AND MAINTENANCE OFFICE
ToHEBBRONVILLE MAINTENANCE OFFICE
CSJ6343-16-001
Proj IDSUP - 634316001
Work TypeJANITORIAL MAINTENANCE
 
0.01084791.9466157.3878.0
Work Order08-08-19
Work Began09-03-19
Work Completed
Time Computed09-01-19
Contract Working Days731
Addl Days Granted0
Working Days Charged608
Percent Time Used83
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6343-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08192136
Totals84791.942977.2666157.3878.0

CountyCAMERON
HighwayIH0069E
FromCAMERON, WILLACY AND KENEDY COUNTY
ToSAN BENITO, BROWNSVILLE AND RAYMONDVILLE
CSJ6343-17-001
Proj IDSUP - 634317001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010987929.00563377.0057.0
Work Order08-29-19
Work Began09-05-19
Work Completed
Time Computed09-01-19
Contract Working Days366
Addl Days Granted0
Working Days Charged361
Percent Time Used98
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6343-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08192137
Totals987929.0064041.00563377.0057.0

CountySTARR
HighwayUS0083
FromSTARR, ZAPATA, JIM HOGG, BROOKS COUNTY
ToROMA, HEBBRONVILLE MAINTENANCE
CSJ6343-19-001
Proj IDSUP - 634319001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010693558.00287174.7541.4
Work Order08-29-19
Work Began09-05-19
Work Completed
Time Computed09-01-19
Contract Working Days366
Addl Days Granted0
Working Days Charged365
Percent Time Used99
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6343-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08192139
Totals693558.008873.00287174.7541.4

CountyWILLACY
HighwaySH0186
FromWILLACY COUNTY
ToVARIOUS LOCATIONS
CSJ6354-90-001
Proj IDRMC - 635490001
Work TypeINSTALLATION OF CONCRETE PIPE & RIPRAP
 
0.010337395.19294195.0887.1
Work Order11-13-20
Work Began01-11-21
Work Completed
Time Computed01-06-21
Contract Working Days50
Addl Days Granted2
Working Days Charged48
Percent Time Used92
Contractor(s)
B & MS CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6354-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09202101
Totals337395.190.00294195.0887.1

CountyCAMERON
HighwayIH0069E
FromI-69E/I-2 INTERCHANGE
ToCAMERON COUNTY
CSJ6357-50-001
Proj IDSUP - 635750001
Work TypeLANDSCAPE MAINTENANCE
 
0.010318456.6079469.8224.9
Work Order09-25-20
Work Began11-03-20
Work Completed
Time Computed11-01-20
Contract Working Days731
Addl Days Granted0
Working Days Charged179
Percent Time Used24
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6357-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09202130
Totals318456.6013244.9779469.8224.9

CountyCAMERON
HighwayIH0069E
FromHIDALGO COUNTY
ToBROWNSVILLE, HIDALGO, & SAN BENITO
CSJ6357-51-001
Proj IDSUP - 635751001
Work TypeMAINTENANCE OF TBSIF
 
0.01031623.3610541.1233.3
Work Order08-11-20
Work Began09-04-20
Work Completed
Time Computed09-01-20
Contract Working Days730
Addl Days Granted0
Working Days Charged242
Percent Time Used33
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6357-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08202131
Totals31623.361317.6410541.1233.3

CountyHIDALGO
HighwayIH0002
FromDISTRICT WIDE
ToVARIOUS LOCATIONS
CSJ6357-52-001
Proj IDSUP - 635752001
Work TypeDRAIN INLET CLEANING
 
0.010576300.0082455.0014.3
Work Order08-17-20
Work Began10-01-20
Work Completed
Time Computed09-01-20
Contract Working Days730
Addl Days Granted0
Working Days Charged212
Percent Time Used29
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6357-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08202132
Totals576300.0059920.0082455.0014.3

CountyHIDALGO
HighwayIH0002
FromIH 2, IH 69E, IH 69C, US 281
ToHIDALGO AND CAMERON COUNTY
CSJ6357-53-001
Proj IDSUP - 635753001
Work TypeDEBRIS REMOVAL
 
0.010491070.59148229.9130.1
Work Order08-12-20
Work Began09-17-20
Work Completed
Time Computed09-17-20
Contract Working Days731
Addl Days Granted0
Working Days Charged226
Percent Time Used30
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6357-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08202133
Totals491070.5918528.74148229.9130.1

CountyHIDALGO
HighwaySH0107
FromBROWNSVILLE MNT / RAYMONDVILLE MNT
ToEDCOUCH MNT / MISSION MNT
CSJ6357-54-001
Proj IDSUP - 635754001
Work TypeJANITORIAL MAINTENANCE
 
0.01073048.5020359.9527.8
Work Order08-17-20
Work Began09-01-20
Work Completed
Time Computed09-01-20
Contract Working Days730
Addl Days Granted0
Working Days Charged242
Percent Time Used33
Contractor(s)
WORKQUEST
GOODWILL INDUSTRIES OF SOUTH TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6357-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08202134
Totals73048.501946.7220359.9527.8

CountyHIDALGO
HighwayIH0002
FromPHARR DISTRICT COMPLEX
ToPHARR AREA/MAINTENANCE OFFICE
CSJ6357-55-001
Proj IDSUP - 635755001
Work TypeJANITORIAL MNT AND ON-SITE JANITOR
 
0.010245898.6074111.0730.1
Work Order08-10-20
Work Began09-01-20
Work Completed
Time Computed09-01-20
Contract Working Days731
Addl Days Granted0
Working Days Charged242
Percent Time Used33
Contractor(s)
WORKQUEST
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6357-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08202135
Totals245898.609418.8274111.0730.1

CountyCAMERON
HighwayUS0077
FromSAN BENITO MAINTENANCE
ToSAN BENITO AREA OFFICE
CSJ6357-56-001
Proj IDSUP - 635756001
Work TypeJANITORIAL MAINTENANCE
 
0.01039384.9612223.9231.0
Work Order08-13-20
Work Began09-02-20
Work Completed
Time Computed09-01-20
Contract Working Days730
Addl Days Granted0
Working Days Charged242
Percent Time Used33
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6357-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08202136
Totals39384.961829.6912223.9231.0

CountyJIM HOGG
HighwayFM1017
FromHEBBRONVILLE AND ROMA MAINTENANCE
ToVARIOUS ROADWAYS
CSJ6357-57-001
Proj IDSUP - 635757001
Work TypeROADSIDE MOWING & LITTER REMOVAL
 
0.010773506.55291922.6537.7
Work Order08-18-20
Work Began09-01-20
Work Completed
Time Computed09-01-20
Contract Working Days365
Addl Days Granted0
Working Days Charged242
Percent Time Used66
Contractor(s)
WORKQUEST
UPPER VALLEY HELPSOURCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6357-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08202137
Totals773506.550.00291922.6537.7

CountyCAMERON
HighwayIH0069E
FromCAMERON, WILLACY AND KENEDY COUNTY
ToSAN BENITO, BROWNSVILLE AND RAYMONDVILLE
CSJ6357-58-001
Proj IDSUP - 635758001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010949144.00329500.0034.7
Work Order08-18-20
Work Began09-03-20
Work Completed
Time Computed09-01-20
Contract Working Days365
Addl Days Granted0
Working Days Charged242
Percent Time Used66
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6357-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08202138
Totals949144.0022359.00329500.0034.7

CountyHIDALGO
HighwayIH0069C
FromPHARR, EDCOUCH, MISSION
ToVARIOUS ROADWAYS
CSJ6357-59-001
Proj IDSUP - 635759001
Work TypeMETAL BEAM GUARD FENCE
 
0.010983687.00278485.7028.3
Work Order08-17-20
Work Began09-02-20
Work Completed
Time Computed09-02-20
Contract Working Days365
Addl Days Granted0
Working Days Charged241
Percent Time Used66
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6357-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08202139
Totals983687.0025142.40278485.7028.3

CountySTARR
HighwayUS0083
FromVARIOUS ROADWAYS
ToROMA AND HEBBRONVILLE MAINTENANCE
CSJ6357-60-001
Proj IDSUP - 635760001
Work TypeMBGF REPAIR
 
0.010771448.15210431.2527.2
Work Order08-12-20
Work Began09-08-20
Work Completed
Time Computed09-08-20
Contract Working Days365
Addl Days Granted0
Working Days Charged235
Percent Time Used64
Contractor(s)
WORKQUEST
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6357-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08202140
Totals771448.155957.00210431.2527.2

CountyCAMERON
HighwayIH0069E
FromCITY OF BROWNSVILLE
ToVARIOUS LOCATIONS
CSJ6361-18-001
Proj IDMMA - 636118001
Work TypeMAINTENANCE OF TRAFFIC SIGNALS
 
0.01084240.0028080.0033.3
Work Order08-12-20
Work Began09-01-20
Work Completed
Time Computed09-01-20
Contract Working Days730
Addl Days Granted0
Working Days Charged242
Percent Time Used33
Contractor(s)
CITY OF BROWNSVILLE
SUBCONTRACTOR(S) FOR CCSJ: 6361-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08202102
Totals84240.003510.0028080.0033.3

CountyCAMERON
HighwayIH0069E
FromCITY OF HARLINGEN
ToVARIOUS ROADWAYS
CSJ6361-19-001
Proj IDMMA - 636119001
Work TypeMAINTENANCE OF TRAFFIC SIGNALS
 
0.01099600.0033200.0033.3
Work Order07-31-20
Work Began09-01-20
Work Completed
Time Computed09-01-20
Contract Working Days730
Addl Days Granted0
Working Days Charged242
Percent Time Used33
Contractor(s)
CITY OF HARLINGEN
SUBCONTRACTOR(S) FOR CCSJ: 6361-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06202130
Totals99600.004150.0033200.0033.3