Monthly State Let Maintenance Report For Paris District As Of Jul 13, 2018 Page 1 Of 2

Last Update: Friday, July 13, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLAMAR
HighwayUS0082
FromUS 82 W
ToUS 271 N
CSJ6203-38-001
Proj IDRMC - 620338001
Work TypeSEAL COAT SHOULDERS/CLEAN & SEAL JOINTS
 
3.560372768.260.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6203-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05104002
Totals372768.260.000.000.0

CountyGRAYSON
HighwaySH0091
FromVARIOUS LOCATIONS IN GRAYSON, FANNIN,
ToRED RIVER AND RAINS COUNTIES
CSJ6291-12-001
Proj IDBPM - 629112001
Work TypeENCASEMENT AND WINGWALL REPAIR/REPLACE
 
0.001476292.00432790.20100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-04-16
Work Began04-25-16
Work Completed01-02-18
Time Computed04-25-16
Contract Working Days75
Addl Days Granted10
Working Days Charged176
Percent Time Used207
Contractor(s)
REVEGETATION SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6291-12-001
ROSS TREE SERVICE (1.07)
S&S BRIDGE PAINTING (4.22)
Contract #01164201
Totals476292.000.00432790.20100.0

CountyHUNT
HighwayIH0030
FromVARIOUS LOCATIONS IN HUNT, RAINS,
ToHOPKINS AND FRANKLIN COUNTIES
CSJ6292-44-001
Proj IDRMC - 629244001
Work TypeON CALL TY II STRIPING
 
0.001427700.00286643.5867.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-13-16
Work Began01-15-16
Work Completed
Time Computed01-15-16
Contract Working Days365
Addl Days Granted365
Working Days Charged729
Percent Time Used99
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6292-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11154001
Totals427700.000.00286643.5867.0

CountyLAMAR
HighwayUS0082
FromPARIS DISTRICT
ToALL LOCATIONS
CSJ6292-45-001
Proj IDRMC - 629245001
Work TypeON CALL RPM'S
 
0.001294594.00574222.4299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-07-16
Work Began01-15-16
Work Completed
Time Computed01-15-16
Contract Working Days365
Addl Days Granted365
Working Days Charged727
Percent Time Used99
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11154202
Totals294594.000.00574222.4299.9

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS THROUGHOUT ENTIRE
ToPARIS DISTRICT
CSJ6301-86-001
Proj IDRMC - 630186001
Work TypeON CALL TRAFFIC CONTROL SERVICES
 
0.0012302678.753975842.0199.9
Work Order10-10-16
Work Began00-00-00
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted365
Working Days Charged607
Percent Time Used83
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164201
Totals2302678.75226882.123975842.0199.9

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS THROUGHOUT
ToPARIS DISTRICT
CSJ6308-45-001
Proj IDRMC - 630845001
Work TypeON CALL MILL AND INLAY
 
0.0014370668.548221336.7999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-22-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged494
Percent Time Used67
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6308-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164001
Totals4370668.540.008221336.7999.9

CountyHUNT
HighwayIH0030
FromIH 30 THROUGH HUNT, HOPKINS,
ToFRANKLIN COUNTIES
CSJ6313-72-001
Proj IDRMC - 631372001
Work TypeDEBRIS REMOVAL
 
0.001328038.00375415.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-17
Work Completed
Time Computed00-00-00
Contract Working Days254
Addl Days Granted365
Working Days Charged295
Percent Time Used47
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174001
Totals328038.0031357.00375415.0099.9

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS THROUGHOUT
ToENTIRE PARIS DISTRICT
CSJ6314-23-001
Proj IDRMC - 631423001
Work TypeILLUMINATION MAINTENANCE
 
0.001387411.00193315.0049.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-10-17
Work Completed
Time Computed00-00-00
Contract Working Days261
Addl Days Granted0
Working Days Charged232
Percent Time Used88
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6314-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174003
Totals387411.0011470.00193315.0049.8

CountyLAMAR
HighwayUS0082
FromVARIOUS ROADWAYS IN LAMAR, DELTA,
ToAND RED RIVER COUNTIES
CSJ6314-93-001
Proj IDRMC - 631493001
Work TypeON CALL TY I & SPECIALTY STRIPING
 
0.001642955.00621573.0896.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-08-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged358
Percent Time Used98
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6314-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174202
Totals642955.000.00621573.0896.6

CountyGRAYSON
HighwayUS0075
FromVARIOUS ROADWAYS IN GRAYSON AND
ToFANNIN COUNTIES
CSJ6314-95-001
Proj IDRMC - 631495001
Work TypeON CALL TY I & SPECIALTY STRIPING
 
0.001667264.00257248.8838.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-22-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged344
Percent Time Used94
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6314-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174004
Totals667264.000.00257248.8838.5

CountyHUNT
HighwayIH0030
FromVARIOUS ROADWAYS IN HUNT, RAINS,
ToHOPKINS, AND FRANKLIN COUNTIES
CSJ6314-97-001
Proj IDRMC - 631497001
Work TypeON CALL TY I & SPECIALTY STRIPING
 
0.001860464.50264825.1730.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-08-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged358
Percent Time Used98
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6314-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174203
Totals860464.500.00264825.1730.7

CountyGRAYSON
HighwayUS0075
FromGRAYSON CO
ToUS 75
CSJ6317-53-001
Proj IDRMC - 631753001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.001598650.00634704.0599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged50
Percent Time Used83
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174201
Totals598650.000.00634704.0599.9

CountyGRAYSON
HighwayFM0084
FromFM 84 AT THE
ToUNION PACIFIC RAILROAD
CSJ6318-62-001
Proj IDBPM - 631862001
Work TypeEROSION REPAIR-INSTALL RETAINING WALL
 
0.001629000.0031928.095.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6318-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04184001
Totals629000.0031928.0931928.095.0

CountyHOPKINS
HighwayIH0030
FromVARIOUS LOCATIONS THROUGHOUT
ToPARIS DISTRICT
CSJ6321-64-001
Proj IDRMC - 632164001
Work TypeON CALL FULL DEPTH CONCRETE REPAIR
 
0.0011573245.001227449.1778.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged150
Percent Time Used41
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10174201
Totals1573245.00354771.991227449.1778.0

CountyFANNIN
HighwaySH0056
FromVARIOUS ROADWAYS IN
ToFANNIN COUNTY
CSJ6323-50-001
Proj IDRMC - 632350001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001292651.1070963.4524.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days76
Addl Days Granted0
Working Days Charged29
Percent Time Used38
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174001
Totals292651.1070963.4570963.4524.2

CountyHOPKINS
HighwayIH0030
FromIH 30 IN HOPKINS, FRANKLIN,
ToAND HUNT COUNTY
CSJ6323-51-001
Proj IDRMC - 632351001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001302564.00105563.0034.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days54
Addl Days Granted0
Working Days Charged19
Percent Time Used35
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6323-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174201
Totals302564.00105563.00105563.0034.8

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS IN
ToPARIS DISTRICT
CSJ6323-58-001
Proj IDRMC - 632358001
Work TypeON CALL RAISED PAVEMENT MARKERS
 
0.001334862.0051340.3515.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-07-18
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged144
Percent Time Used39
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174002
Totals334862.000.0051340.3515.3

CountyHUNT
HighwayIH0030
FromVARIOUS LOCATIONS IN HUNT, RAINS,
ToHOPKINS AND FRANKLIN COUNTY
CSJ6323-93-001
Proj IDRMC - 632393001
Work TypeON CALL METAL BEAM GUARD FENCE REPAIR
 
0.001249815.00133675.0053.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-05-18
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged146
Percent Time Used40
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174202
Totals249815.0029202.00133675.0053.5

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATION THROUGHOUT
ToENTIRE PARIS DISTRICT
CSJ6324-93-001
Proj IDRMC - 632493001
Work TypeON CALL MILL & INLAY
 
0.0014350178.001949495.6344.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-10-18
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged82
Percent Time Used22
Contractor(s)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6324-93-001
A.E. MOORE CONSTRUCTION, INC. DBA (0.17)
TEX OP CONSTRUCTION, LP (4.10)
WEST TEXAS RUMBLE STRIP (0.21)
STRIPING TECHNOLOGY, L.P. (3.90)
Contract #02184001
Totals4350178.001006087.371949495.6344.8

CountyHUNT
HighwayIH0030
FromVARIOUS LOCATION IN
ToPARIS DISTRICT
CSJ6325-66-001
Proj IDRMC - 632566001
Work TypeSITE SPECIFIC TY I STRIPING
 
0.0011259149.01935010.0374.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-18
Work Completed
Time Computed00-00-00
Contract Working Days66
Addl Days Granted0
Working Days Charged25
Percent Time Used37
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6325-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02184002
Totals1259149.01198101.29935010.0374.2

page 1 | page 2