Monthly State Let Construction Report For Paris District As Of Jun 08, 2018 Page 2 Of 3

Last Update: Tuesday, June 12, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDELTA
HighwaySH 19
From@ NORTH SULPHUR RIVER
To.
CSJ0136-04-035
Proj IDBR 1702(379)
Work TypeBRIDGE REPLACEMENT
 
0.1181665295.931519515.0291.2
Work Order07-14-17
Work Began08-25-17
Work Completed
Time Computed08-14-17
Contract Working Days180
Addl Days Granted0
Working Days Charged141
Percent Time Used78
Contractor(s)
L & N BRIDGE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0136-04-035
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (8.86)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.11)
TEXOP CONSTRUCTION (0.54)
STRIPING TECHNOLOGY, L.P. (0.90)
GARY A. CRAIN, INC. (0.17)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.42)
WOLFE CONSTRUCTION GROUP, INC. (1.16)
ALTUS TRAFFIC MANAGEMENT LLC (0.87)
SOUTHWEST ENVIRONMENT SERIVES, LLC (3.23)
BOWMAN ENGINEERING & CONSULTING, INC (0.22)
Contract #06173037
Totals1665295.9393537.171519515.0291.2

CountyHUNT
HighwaySH 34
FromSH 276
ToKAUFMAN COUNTY LINE
CSJ0173-06-043
Proj IDSTP 2018(770)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
5.677611916.350.000.0
CountyHUNT
HighwayFM 816
FromFANNIN COUNTY LINE
ToSH 34
CSJ1097-01-017
Proj IDSTP 2018(770)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
6.108688586.540.000.0
CountyFANNIN
HighwayFM 816
FromSH 78
ToHUNT COUNTY LINE
CSJ1097-02-008
Proj IDSTP 2018(770)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
4.421231703.430.000.0
CountyFANNIN
HighwayRR 3
FromFM 273
To2.02 MI E OF FM 273
CSJ3310-01-005
Proj IDSTP 2018(770)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
2.020251822.900.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-17-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days224
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0173-06-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183219
Totals1784029.220.000.000.0

CountyHUNT
HighwaySH 34
FromAT NE CORNER OF SH 34 AND SH 276 W
To.
CSJ0173-06-048
Proj IDSTP 2018(423)
Work TypeLANDSCAPE AND SCENIC ENHANCEMENT
 
1.53261367.3038957.9163.4
Work Order02-14-18
Work Began03-21-18
Work Completed
Time Computed03-16-18
Contract Working Days60
Addl Days Granted0
Working Days Charged46
Percent Time Used76
Contractor(s)
CENTRAL NORTH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0173-06-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183225
Totals61367.3010492.8938957.9163.4

CountyHUNT
HighwaySH 34 ETC
From0.19 MI. SOUTH OF IH30
ToBU 69-D
CSJ0173-07-055
Proj IDNH 2017(926)
Work TypeOVERLAY
 
6.4201683587.851550266.1392.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-18-17
Work Began06-15-17
Work Completed
Time Computed06-19-17
Contract Working Days102
Addl Days Granted0
Working Days Charged89
Percent Time Used87
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0173-07-055
ALTUS TRAFFIC MANAGEMENT LLC (0.82)
SOUTHWEST ENVIRONMENT SERVICES LLC (5.09)
TOTAL HIGHWAY MAINTENANCE, LLC (3.04)
Contract #04173014
Totals1683587.850.001550266.1392.0

CountyRED RIVER
HighwaySH 37
FromOKLAHOMA STATE LINE
To0.453 MI S FROM STATE LINE
CSJ0189-01-011
Proj IDSTP 2018(979)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
38.9532961890.310.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days240
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0189-01-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183040
Totals2961890.310.000.000.0

CountyFRANKLIN
HighwaySH 37
FromFM 21
ToWOOD C/L
CSJ0190-01-021
Proj IDNH 1502(556)
Work TypeRECONST & ADD 10' SHLDRS
 
13.25820387243.9814125316.6869.2
Work Order03-08-16
Work Began03-23-16
Work Completed
Time Computed06-06-16
Contract Working Days457
Addl Days Granted72
Working Days Charged447
Percent Time Used84
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0190-01-021
N-LINE TRAFFIC MAINTENANCE, L.P. (0.18)
BAHENA CONSTRUCTION CO.,INC. (1.65)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.99)
MORRIS COUNTY CONTRACTORS, LLC (1.94)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.74)
STRIPING TECHNOLOGY, L.P. (1.18)
TX TINMAN ENTERPRISES, LLC. (1.85)
WOLFE CONSTRUCTION GROUP, INC. (0.57)
KLP COMMERCIAL, LLC (0.00)
MESA ROD BUSTERS, INC. (0.04)
DFW REBAR, INC. (0.02)
ISAACS CONSTRUCTION SERVICES, LLC. (1.65)
Contract #01163001
Totals20387243.98415313.7914125316.6869.2

CountyFANNIN ETC
HighwayUS 69
FromFM 151
ToHUNT COUNTY LINE
CSJ0202-03-041
Proj IDSTP 2017(739)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
39.0843186550.002325337.6374.4
Work Order03-15-17
Work Began04-10-17
Work Completed
Time Computed04-14-17
Contract Working Days180
Addl Days Granted0
Working Days Charged228
Percent Time Used126
Contractor(s)
GHB EQUIPMENT COMPANY, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0202-03-041
AREA WIDE PROTECTIVE, INC. (0.84)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.02)
EAGLE BARRICADE,LLC. (1.12)
STRIPING TECHNOLOGY, L.P. (0.41)
SHALOM SERVICES CORPORATION (4.39)
ODUM SERVICES, L.P. (10.47)
Contract #02173020
Totals3186550.0083060.002325337.6374.4

CountyGRAYSON
HighwaySH 289
FromMEADOWBROOK DR
ToFOUNTAIN CREEK BLVD
CSJ0202-08-063
Proj IDSTP 2018(609)
Work TypeREPLACE CULVERTS AND IMPROVE DRAINA
 
0.131201885.960.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-18-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0202-08-063
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183014
Totals201885.960.000.000.0

CountyLAMAR
HighwayUS 271
FromSL 286
ToRED RIVER COUNTY LINE
CSJ0221-01-074
Proj IDNH 2018(127)
Work TypeWIDEN NON-FREEWAY
 
14.1237030934.901586634.0822.5
CountyLAMAR
HighwayUS 271
FromSL 286
ToRED RIVER COUNTY LINE
CSJ0221-01-075
Proj IDSTP 2018(128)HESG
Work TypeHAZARD ELIMINATION & SAFETY
 
14.123450552.700.000.0
CountyRED RIVER
HighwayUS 271
FromLAMAR COUNTY LINE
ToSH 37
CSJ0221-02-025
Proj IDSTP 2018(129)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
6.1221434199.040.000.0
Work Order11-10-17
Work Began04-16-18
Work Completed
Time Computed12-11-17
Contract Working Days197
Addl Days Granted101
Working Days Charged25
Percent Time Used26
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0221-01-074
A.E. MOORE CONSTRUCTION, INC. DBA (0.78)
BAHENA CONSTRUCTION CO.,INC. (3.33)
DUSTIN ALLEN, INC. (3.00)
LYON BARRICADE AND CONSTRUCTION CO. (0.20)
D. I. J. CONSTRUCTION, INC. (0.17)
TOTAL HIGHWAY MAINTENANCE, LLC (1.46)
WEST TEXAS RUMBLE STRIP (0.24)
WITHERS CONSTRUCTION, LLC (1.17)
DUSTROL, INC. (1.61)
Contract #10173010
Totals8915686.641024993.231586634.0817.7

CountyRED RIVER
HighwayUS 271
FromFM 410
ToSH 37
CSJ0221-02-026
Proj IDSTP 2018(610)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
3.180141416.000.000.0
CountyRED RIVER
HighwayUS 271
FromSH 37
ToFRANKLIN COUNTY LINE
CSJ0221-03-065
Proj IDSTP 2018(610)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
7.940575967.200.000.0
CountyRED RIVER
HighwayUS 271
FromSH 37
ToFRANKLIN COUNTY LINE
CSJ0221-03-068
Proj IDSTP 2018(610)HES
Work TypeBRIDGE MAINTENANCE
 
7.94078300.000.000.0
CountyFRANKLIN
HighwayUS 271
FromRED RIVER COUNTY LINE
ToTITUS COUNTY LINE
CSJ0221-04-024
Proj IDSTP 2018(610)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
0.48845345.000.000.0
Work Order04-24-18
Work Began00-00-00
Work Completed
Time Computed05-24-18
Contract Working Days93
Addl Days Granted0
Working Days Charged6
Percent Time Used6
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0221-02-026
AREA WIDE PROTECTIVE, INC. (1.42)
A. E. MOORE CONSTRUCTION, INC. (2.38)
MORRIS COUNTY CONTRACTORS, LLC (25.51)
Contract #03183208
Totals841028.200.000.000.0

CountyFANNIN
HighwaySH 78
FromSH 11
To0.68 MI S OF SH 56
CSJ0279-03-035
Proj IDSTP 2017(188)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
23.8702675061.252322589.4187.8
Work Order12-06-16
Work Began01-09-17
Work Completed
Time Computed02-01-17
Contract Working Days159
Addl Days Granted24
Working Days Charged218
Percent Time Used119
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0279-03-035
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.84)
WITHERS CONSTRUCTION, LLC (1.32)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION, LTD. (0.38)
MORRIS COUNTY CONTRACTORS, LLC (13.35)
Contract #10163212
Totals2675061.2587077.062322589.4187.8

CountyRED RIVER
HighwayFM 44
FromFM 412
ToFM 911
CSJ0427-01-037
Proj IDSTP 2016(363)
Work TypeREHABILITATION OF EXISTING ROAD
 
10.3634617291.244456156.1096.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-15-16
Work Began04-25-16
Work Completed
Time Computed05-16-16
Contract Working Days222
Addl Days Granted4
Working Days Charged244
Percent Time Used107
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0427-01-037
HIGHWAY 19 CONSTRUCTION, LLC (1.62)
LYON BARRICADE AND CONSTRUCTION CO. (0.52)
WITHERS CONSTRUCTION, LLC (2.23)
A. E. MOORE CONSTRUCTION, INC. (2.98)
SAMMY SMALLWOOD COMPANY (2.37)
BAHENA CONSTRUCTION CO.,INC. (11.37)
TEX OP CONSTRUCTION, LP (0.15)
STRIPING TECHNOLOGY, L.P. (1.84)
STRIPING SYSTEMS, INC. (0.02)
A. E. MOORE CONSTRUCTION, INC. (2.98)
SOUTHERN CROSS CONTRACTORS, LLC (0.19)
Contract #02163241
Totals4617291.240.004456156.1096.8

CountyRED RIVER
HighwayFM 1158
FromFM 114
ToEND OF STATE MAINTENANCE
CSJ0427-02-009
Proj IDSTP 2018(279)
Work TypeREHABILITATION OF EXISTING ROAD
 
3.8042040371.541109420.2754.3
Work Order12-19-17
Work Began01-23-18
Work Completed
Time Computed01-18-18
Contract Working Days110
Addl Days Granted0
Working Days Charged53
Percent Time Used48
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0427-02-009
ISAACS CONSTRUCTION SERVICES, LLC. (0.80)
BAHENA CONSTRUCTION CO.,INC. (10.16)
TEXANA LAND & ASPHALT, INC. (0.20)
TOTAL HIGHWAY MAINTENANCE, LLC (1.77)
WOLFE CONSTRUCTION GROUP, INC. (1.10)
PANOLA SIGN & BARRICADE, INC. (0.75)
WITHERS CONSTRUCTION, LLC (2.41)
Contract #11173216
Totals2040371.54302739.971109420.2754.3

CountyLAMAR
HighwayFM 38
FromUS 82
ToFM 1509
CSJ0435-01-073
Proj IDSTP 2018(511)
Work TypeREHABILITATION OF EXISTING ROAD
 
2.5161588245.34142367.508.9
CountyDELTA
HighwayFM 38
FromLAMAR COUNTY LINE
ToFM 128
CSJ0749-03-014
Proj IDSTP 2018(511)
Work TypeREHABILITATION OF EXISTING ROAD
 
1.671859679.22490570.6157.0
Work Order03-08-18
Work Began04-06-18
Work Completed
Time Computed04-09-18
Contract Working Days128
Addl Days Granted0
Working Days Charged31
Percent Time Used24
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0435-01-073
LYON BARRICADE AND CONSTRUCTION CO. (0.76)
BAHENA CONSTRUCTION CO.,INC. (2.75)
WITHERS CONSTRUCTION, LLC (1.60)
A. E. MOORE CONSTRUCTION, INC. (2.53)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (27.80)
MARCOM"S MOWING SERVICE, LLC (0.37)
DUSTIN ALLEN, INC. (1.85)
TOTAL HIGHWAY MAINTENANCE, LLC (2.56)
TEX OP CONSTRUCTION, LP (3.61)
Contract #02183008
Totals2447924.56292690.19632938.1125.8

CountyGRAYSON
HighwayFM 902
FromUS 377
ToSH 289
CSJ0510-01-026
Proj IDSTP 2015(309)
Work TypeREHABILITATION OF EXISTING ROAD
 
14.4277337375.526598558.9290.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-02-15
Work Began09-28-15
Work Completed
Time Computed04-02-15
Contract Working Days304
Addl Days Granted0
Working Days Charged342
Percent Time Used112
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0510-01-026
TEXOP CONSTRUCTION (0.05)
CATOCON, INC. (1.83)
FARR FOUNDATION, INC. (4.74)
LYON BARRICADE AND CONSTRUCTION CO. (0.46)
MURRAY CONSTRUCTION (1.26)
SAMMY G. SMALLWOOD (1.75)
STRIPING TECHNOLOGY, L.P. (1.54)
TEXANA LAND & ASPHALT, INC. (2.35)
BAHENA CONSTRUCTION CO.,INC. (14.62)
A. E. MOORE CONSTRUCTION, INC. (1.15)
Contract #11143220
Totals7337375.520.006598558.9290.5

CountyDELTA ETC
HighwaySH 19 ETC
From@ BRUSHY CREEK
To.
CSJ0525-01-020
Proj IDBR 1502(141)
Work TypeBRIDGE REPLACEMENT
 
0.6784018602.904039013.8999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-30-15
Work Began09-22-15
Work Completed
Time Computed08-30-15
Contract Working Days348
Addl Days Granted0
Working Days Charged364
Percent Time Used104
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0525-01-020
PANOLA SIGN & BARRICADE, INC. (0.71)
A. E. MOORE CONSTRUCTION, INC. (1.43)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (4.08)
DUSTIN ALLEN, INC. (3.15)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.02)
STRIPING TECHNOLOGY, L.P. (1.08)
PENHALL COMPANY (0.23)
TEX OP CONSTRUCTION, LP (0.62)
WITHERS CONSTRUCTION, LLC (0.79)
MCL CONTRACTING, LLC (0.30)
STRIPING SYSTEMS, INC. (0.00)
Contract #05153217
Totals4018602.900.004039013.8999.9

CountyFRANKLIN
HighwayFM 21
FromFM 2723
ToCR 4140
CSJ0633-01-021
Proj IDSTP 1702(748)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
6.4981216614.351203151.0098.8
CountyFRANKLIN
HighwayFM 3357
FromFM 115
ToSH 37
CSJ3354-01-015
Proj IDC 3354-1-15
Work TypeSEAL COAT
 
5.324323324.00274702.5584.9
Work Order10-25-17
Work Began11-29-17
Work Completed
Time Computed11-24-17
Contract Working Days95
Addl Days Granted0
Working Days Charged62
Percent Time Used65
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0633-01-021
FLEX SUPPLY, LLC (0.24)
A.E. MOORE CONSTRUCTION, INC. DBA (3.50)
TEX OP CONSTRUCTION, LP (2.97)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (36.69)
TOTAL HIGHWAY MAINTENANCE, LLC (2.92)
MORRIS COUNTY CONTRACTORS, LLC (2.94)
Contract #09173026
Totals1539938.35367080.281477853.5595.9

CountyLAMAR
HighwayFM 196
FromUS 271
ToFM 1501
CSJ0680-01-015
Proj IDSTP 2017(086)
Work TypeREHABILITATION OF EXISTING ROAD
 
4.8062490743.372361397.8295.8
Work Order11-15-16
Work Began01-03-17
Work Completed
Time Computed12-15-16
Contract Working Days144
Addl Days Granted0
Working Days Charged178
Percent Time Used123
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0680-01-015
CATACON, INC. (1.92)
A. E. MOORE CONSTRUCTION, INC. (2.36)
SCOTT PAVING, INC. (17.51)
TOTAL HIGHWAY MAINTENANCE, LLC (1.83)
SOUTHERN CROSS CONTRACTORS, LLC (2.24)
DUSTIN ALLEN, INC. (0.48)
Contract #09163221
Totals2490743.3717500.002361397.8295.8

CountyRAINS
HighwayFM 275
FromFM 514
ToFM 514
CSJ0725-02-019
Proj IDSTP 1702(751)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
1.405614717.76569493.0092.6
CountyRAINS
HighwayFM 275
FromFM 514
ToFM 514
CSJ0725-02-020
Proj IDSTP 1702(752)
Work TypeSEAL COAT
 
1.40570822.7554368.0076.7
Work Order09-14-17
Work Began10-23-17
Work Completed
Time Computed10-16-17
Contract Working Days120
Addl Days Granted0
Working Days Charged102
Percent Time Used85
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0725-02-019
SOUTHWEST ENVIRONMENT SERIVES, LLC (4.31)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (2.03)
MAC TRANSPORTATION, LTD, L.L.P. (0.90)
TOTAL HIGHWAY MAINTENANCE, LLC (2.64)
Contract #08173036
Totals685540.51115339.50623861.0091.0

CountyGRAYSON
HighwayFM 121
FromSH 289
To1200 FT WEST OF FM 3356
CSJ0729-01-037
Proj IDSTP 1502(559)HES
Work TypeHAZARD ELIMINATION & SAFETY
 
6.9584609064.064428400.0796.0
Work Order01-29-16
Work Began03-16-16
Work Completed
Time Computed04-28-16
Contract Working Days272
Addl Days Granted0
Working Days Charged272
Percent Time Used100
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0729-01-037
TOTAL HIGHWAY MAINTENANCE, LLC (0.49)
STRIPING TECHNOLOGY, L.P. (2.18)
CATACON, INC. (1.41)
A. E. MOORE CONSTRUCTION, INC. (1.88)
LONE STAR BARRIER SERVICES, LLC (4.24)
BAHENA CONSTRUCTION CO.,INC. (15.72)
DUSTIN ALLEN, INC. (3.33)
MARCOM"S MOWING SERVICE, LLC (0.88)
STRIPING SYSTEMS, INC. (0.00)
Contract #10153228
Totals4609064.066050.004428400.0796.0

page 1 | page 2 | page 3