Monthly Local Let Maintenance Report For Odessa District As Of Mar 13, 2024 Page 3 Of 5

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyREEVES
HighwayUS0285
FromVARIOUS
ToVARIOUS
CSJ6433-44-001
Proj IDRMC - 643344001
Work TypeCULVERT CLEANING
 
0.0100.00232122.000.0
Work Order03-20-23
Work Began03-20-23
Work Completed
Time Computed03-20-23
Contract Working Days60
Addl Days Granted0
Working Days Charged17
Percent Time Used28
Contractor(s)
TALBRAN ENTERPRISES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6433-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02230601
Totals0.000.00232122.000.0

CountyPECOS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6434-14-001
Proj IDRMC - 643414001
Work TypeREFLECTIVE PAVEMENT MARKINGS (LONG LINE)
 
0.010247300.000.000.0
Work Order04-01-23
Work Began00-00-00
Work Completed
Time Computed04-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged335
Percent Time Used91
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6434-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02230602
Totals247300.000.000.000.0

CountyPECOS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6434-32-001
Proj IDRMC - 643432001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010282986.0470746.5125.0
Work Order10-01-23
Work Began11-10-23
Work Completed
Time Computed10-01-23
Contract Working Days731
Addl Days Granted0
Working Days Charged152
Percent Time Used20
Contractor(s)
LIGHT & FOLIAGE SUPPLY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6434-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05230601
Totals282986.040.0070746.5125.0

CountyECTOR
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6434-40-001
Proj IDMMC - 643440001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.01065000.00124120.3099.9
Work Order06-22-23
Work Began07-13-23
Work Completed
Time Computed07-01-23
Contract Working Days120
Addl Days Granted240
Working Days Charged253
Percent Time Used70
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6434-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03230601
Totals65000.0023807.30124120.3099.9

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6434-42-001
Proj IDMMC - 643442001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.01074000.00247318.50100.0
Work Order05-24-23
Work Began07-12-23
Work Completed01-26-24
Time Computed06-01-23
Contract Working Days120
Addl Days Granted120
Working Days Charged214
Percent Time Used89
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6434-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03230602
Totals74000.000.00247318.50100.0

CountyPECOS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6434-44-001
Proj IDMMC - 643444001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.010104000.000.000.0
Work Order06-23-23
Work Began00-00-00
Work Completed
Time Computed07-03-23
Contract Working Days120
Addl Days Granted240
Working Days Charged244
Percent Time Used67
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6434-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03230603
Totals104000.000.000.000.0

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6434-48-001
Proj IDMMC - 643448001
Work TypeAGGREGATE
 
0.01079500.0086491.5099.9
Work Order07-01-23
Work Began09-15-23
Work Completed
Time Computed07-01-23
Contract Working Days120
Addl Days Granted120
Working Days Charged215
Percent Time Used89
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6434-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04230602
Totals79500.000.0086491.5099.9

CountyPECOS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6434-56-001
Proj IDMMC - 643456001
Work TypeAGGREGATE
 
0.01052500.000.000.0
Work Order07-01-23
Work Began00-00-00
Work Completed
Time Computed07-01-23
Contract Working Days120
Addl Days Granted120
Working Days Charged244
Percent Time Used101
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6434-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04230603
Totals52500.000.000.000.0

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6434-58-001
Proj IDMMC - 643458001
Work TypeSAND
 
0.01017750.000.000.0
Work Order05-25-23
Work Began00-00-00
Work Completed
Time Computed06-01-23
Contract Working Days120
Addl Days Granted240
Working Days Charged274
Percent Time Used76
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6434-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03230604
Totals17750.000.000.000.0

CountyECTOR
HighwaySL0338
FromVARIOUS
ToVARIOUS
CSJ6434-60-001
Proj IDMMC - 643460001
Work TypeFLEXIBLE BASE
 
0.01033000.00102087.9099.9
Work Order06-06-23
Work Began06-06-23
Work Completed
Time Computed06-06-23
Contract Working Days120
Addl Days Granted240
Working Days Charged271
Percent Time Used75
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6434-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04230604
Totals33000.0021174.00102087.9099.9

CountyPECOS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6434-62-001
Proj IDMMC - 643462001
Work TypeFLEXIBLE BASE
 
0.01049000.0062782.3099.9
Work Order07-01-23
Work Began07-13-23
Work Completed
Time Computed07-01-23
Contract Working Days120
Addl Days Granted120
Working Days Charged215
Percent Time Used89
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6434-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04230605
Totals49000.000.0062782.3099.9

CountyPECOS
HighwayBI0010G
FromVARIOUS
ToVARIOUS
CSJ6440-26-001
Proj IDMMC - 644026001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010123499.50202703.1199.9
Work Order08-24-23
Work Began08-29-23
Work Completed
Time Computed08-25-23
Contract Working Days120
Addl Days Granted120
Working Days Charged184
Percent Time Used76
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6440-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06230601
Totals123499.5033674.03202703.1199.9

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6440-28-001
Proj IDMMC - 644028001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010226164.00191495.5684.6
Work Order08-02-23
Work Began08-09-23
Work Completed
Time Computed08-02-23
Contract Working Days120
Addl Days Granted120
Working Days Charged213
Percent Time Used88
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6440-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06230602
Totals226164.0063302.98191495.5684.6

CountyECTOR
HighwaySL0338
FromVARIOUS
ToVARIOUS
CSJ6440-30-001
Proj IDMMC - 644030001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010184331.5092378.9950.1
Work Order07-21-23
Work Began08-15-23
Work Completed
Time Computed08-01-23
Contract Working Days120
Addl Days Granted240
Working Days Charged213
Percent Time Used59
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6440-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06230603
Totals184331.5025742.7592378.9950.1

CountyWINKLER
HighwaySH0302
FromKERMIT MAINTENANCE OFFICE/YARD
ToKERMIT MAINTENANCE OFFICE/YARD
CSJ6442-26-001
Proj IDSUP - 644226001
Work TypeJANITORIAL, GROUNDS AND/OR LANDSCAPE SE
 
0.01021835.344168.3920.3
Work Order06-12-23
Work Began07-05-23
Work Completed
Time Computed07-01-23
Contract Working Days730
Addl Days Granted0
Working Days Charged244
Percent Time Used33
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6442-26-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #04230631
Totals21835.34346.714168.3920.3

CountyECTOR
HighwayBI0020E
FromDISTRICT COMPLEX
ToDISTRICT COMPLEX
CSJ6443-32-001
Proj IDSUP - 644332001
Work TypeJANITORIAL MAINTENANCE
 
0.010121814.0438196.5831.3
Work Order07-19-23
Work Began08-01-23
Work Completed
Time Computed08-01-23
Contract Working Days730
Addl Days Granted0
Working Days Charged213
Percent Time Used29
Contractor(s)
WORKQUEST
PERMIAN BASIN COMMUNITY CENTERS
SUBCONTRACTOR(S) FOR CCSJ: 6443-32-001
PERMIAN BASIN COMMUNITY CENTERS (0.00)
Contract #05230632
Totals121814.044040.0738196.5831.3

CountyPECOS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6444-78-001
Proj IDSUP - 644478001
Work TypeLITTER REMOVAL
 
0.010141270.8015782.8511.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-02-24
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
WORKQUEST
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6444-78-001
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED (0.00)
Contract #05230631
Totals141270.800.0015782.8511.1

CountyMIDLAND
HighwayIH0020
FromMIDLAND MAINTENANCE/AREA OFFICE/YARD
ToMIDLAND MAINTENANCE/AREA OFFICE/YARD
CSJ6444-80-001
Proj IDSUP - 644480001
Work TypeJANITORIAL, GROUNDS AND/OR LANDSCAPE SE
 
0.01039492.009160.0023.1
Work Order07-25-23
Work Began08-01-23
Work Completed
Time Computed08-01-23
Contract Working Days730
Addl Days Granted0
Working Days Charged211
Percent Time Used28
Contractor(s)
WORKQUEST
PERMIAN BASIN COMMUNITY CENTERS
SUBCONTRACTOR(S) FOR CCSJ: 6444-80-001
PERMIAN BASIN COMMUNITY CENTERS (0.00)
Contract #06230631
Totals39492.00750.009160.0023.1

CountyECTOR
HighwaySL0338
FromODESSA MAINTENANCE OFFICE/YARD
ToODESSA MAINTENANCE OFFICE/YARD
CSJ6444-82-001
Proj IDSUP - 644482001
Work TypeJANITORIAL, GROUNDS AND/OR LANDSCAPE SE
 
0.01026860.004135.0015.3
Work Order07-19-23
Work Began08-01-23
Work Completed
Time Computed08-01-23
Contract Working Days730
Addl Days Granted0
Working Days Charged213
Percent Time Used29
Contractor(s)
WORKQUEST
PERMIAN BASIN COMMUNITY CENTERS
SUBCONTRACTOR(S) FOR CCSJ: 6444-82-001
PERMIAN BASIN COMMUNITY CENTERS (0.00)
Contract #05230634
Totals26860.00525.004135.0015.3

CountyCRANE
HighwayUS0385
FromVARIOUS
ToVARIOUS
CSJ6445-63-001
Proj IDSUP - 644563001
Work TypeLITTER REMOVAL
 
0.010244318.0066250.7227.1
Work Order08-31-23
Work Began09-07-23
Work Completed
Time Computed09-01-23
Contract Working Days730
Addl Days Granted0
Working Days Charged182
Percent Time Used24
Contractor(s)
WORKQUEST
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6445-63-001
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED (0.00)
Contract #05230633
Totals244318.0031947.3666250.7227.1

page 1 | page 2 | page 3 | page 4 | page 5