Monthly Local Let Maintenance Report For Odessa District As Of Apr 12, 2024 Page 1 Of 5

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyECTOR
HighwayLP0338
FromODESSA MAINTENANCE OFFICE
ToODESSA MAINTENANCE OFFICE
CSJ6173-64-001
Proj IDSUP - 617364001
Work TypeGROUNDS MAINTENANCE
 
0.0017717.506615.0085.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-26-08
Work Began03-11-08
Work Completed
Time Computed03-01-08
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
PERMIAN BASIN COMMUNITY CENTERS
SUBCONTRACTOR(S) FOR CCSJ: 6173-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01080631
Totals7717.500.006615.0085.7

CountyMARTIN
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6197-11-001
Proj IDRMC - 619711001
Work TypeROADSIDE MOWING
 
234.30083691.9668030.0781.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-03-10
Work Began06-09-10
Work Completed
Time Computed06-09-10
Contract Working Days56
Addl Days Granted0
Working Days Charged19
Percent Time Used33
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6197-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01100606
Totals83691.960.0068030.0781.2

CountyWINKLER
HighwaySH0302
FromVARIOUS
ToVARIOUS
CSJ6234-97-001
Proj IDRMC - 623497001
Work TypeROADSIDE MOWING
 
0.00146995.260.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days26
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KRAFT WERKS
SUBCONTRACTOR(S) FOR CCSJ: 6234-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05120601
Totals46995.260.000.000.0

CountyWARD
HighwayBI0020D
FromVARIOUS
ToVARIOUS
CSJ6297-63-001
Proj IDRMC - 629763001
Work TypeRETROREFLECTIVITY MEASUREMENT
 
0.00121323.8721323.88100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-16-16
Work Began05-16-16
Work Completed01-31-17
Time Computed05-16-16
Contract Working Days60
Addl Days Granted0
Working Days Charged59
Percent Time Used98
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03160602
Totals21323.870.0021323.88100.0

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6315-92-001
Proj IDRMC - 631592001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.010203137.502520.001.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DELGADO'S CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6315-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10230601
Totals203137.500.002520.001.2

CountyPECOS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6344-43-001
Proj IDRMC - 634443001
Work TypeROADSIDE MOWING
 
0.001249496.00485258.00100.0
Work Order06-25-19
Work Began07-31-19
Work Completed11-30-23
Time Computed07-17-19
Contract Working Days731
Addl Days Granted731
Working Days Charged1,462
Percent Time Used100
Contractor(s)
ABESCAPE LANDSCAPING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6344-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04190601
Totals249496.000.00485258.00100.0

CountyREEVES
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6376-84-001
Proj IDRMC - 637684001
Work TypePICNIC AREA MAINTENANCE
 
0.01062540.0086140.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-03-21
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted731
Working Days Charged1,035
Percent Time Used70
Contractor(s)
LUKEDA SANDBLASTING & SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6376-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04210601
Totals62540.002655.0086140.0099.9

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6380-14-001
Proj IDRMC - 638014001
Work TypeRAISED PAVEMENT MARKINGS
 
0.010111510.00130264.10100.0
Work Order02-22-22
Work Began06-03-22
Work Completed02-27-24
Time Computed03-01-22
Contract Working Days366
Addl Days Granted366
Working Days Charged731
Percent Time Used99
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6380-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05210603
Totals111510.000.00130264.10100.0

CountyANDREWS
HighwayUS0385
FromVARIOUS
ToVARIOUS
CSJ6383-52-001
Proj IDRMC - 638352001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010298824.72279304.7294.5
Work Order02-28-22
Work Began06-20-22
Work Completed
Time Computed03-01-22
Contract Working Days731
Addl Days Granted731
Working Days Charged762
Percent Time Used52
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6383-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12210603
Totals298824.720.00279304.7294.5

CountyANDREWS
HighwaySH0176
FromVARIOUS
ToVARIOUS
CSJ6388-86-001
Proj IDRMC - 638886001
Work TypeLANDSCAPE MAINTENANCE
 
0.01051200.0032000.0062.5
Work Order12-16-21
Work Began12-27-21
Work Completed
Time Computed12-16-21
Contract Working Days731
Addl Days Granted731
Working Days Charged837
Percent Time Used57
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6388-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10210603
Totals51200.001280.0032000.0062.5

CountyUPTON
HighwayUS0067
FromVARIOUS
ToVARIOUS
CSJ6388-90-001
Proj IDSUP - 638890001
Work TypePICNIC AREA MAINTENANCE
 
0.010146680.00176060.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-21
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted730
Working Days Charged881
Percent Time Used60
Contractor(s)
WORKQUEST
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6388-90-001
FRESH START OF MONROE INC. (0.00)
Contract #09210631
Totals146680.006300.00176060.0099.9

CountyREEVES
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6390-16-001
Proj IDRMC - 639016001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010296947.20293369.1298.7
Work Order02-28-22
Work Began06-27-22
Work Completed
Time Computed03-01-22
Contract Working Days731
Addl Days Granted731
Working Days Charged762
Percent Time Used52
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6390-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12210602
Totals296947.200.00293369.1298.7

CountyMARTIN
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6390-17-001
Proj IDRMC - 639017001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010358168.00350968.0097.9
Work Order02-22-22
Work Began07-14-22
Work Completed
Time Computed03-01-22
Contract Working Days731
Addl Days Granted731
Working Days Charged762
Percent Time Used52
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6390-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12210601
Totals358168.000.00350968.0097.9

CountyWARD
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6390-18-001
Proj IDRMC - 639018001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010266080.62289112.8599.9
Work Order02-17-22
Work Began06-13-22
Work Completed
Time Computed03-01-22
Contract Working Days731
Addl Days Granted731
Working Days Charged762
Percent Time Used52
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6390-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01220602
Totals266080.620.00289112.8599.9

CountyTERRELL
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6390-89-001
Proj IDRMC - 639089001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010191701.44191701.4499.9
Work Order06-27-22
Work Began07-01-22
Work Completed
Time Computed07-01-22
Contract Working Days731
Addl Days Granted0
Working Days Charged640
Percent Time Used87
Contractor(s)
MARLANE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6390-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01220603
Totals191701.440.00191701.4499.9

CountyWINKLER
HighwaySH0302
FromVARIOUS
ToVARIOUS
CSJ6394-52-001
Proj IDRMC - 639452001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010245453.60191161.0577.8
Work Order03-23-22
Work Began05-23-22
Work Completed
Time Computed04-01-22
Contract Working Days731
Addl Days Granted731
Working Days Charged731
Percent Time Used50
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6394-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01220606
Totals245453.600.00191161.0577.8

CountyECTOR
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6395-38-001
Proj IDRMC - 639538001
Work TypeSMALL SIGN REPLACEMENT
 
0.010203950.00184889.77100.0
Work Order09-01-22
Work Began09-01-22
Work Completed02-05-24
Time Computed09-01-22
Contract Working Days366
Addl Days Granted120
Working Days Charged486
Percent Time Used100
Contractor(s)
SAFETY FIRST TRAFFIC SOLUTIONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6395-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02220603
Totals203950.000.00184889.77100.0

CountyWINKLER
HighwaySH0302
FromVARIOUS
ToVARIOUS
CSJ6398-49-001
Proj IDSUP - 639849001
Work TypeLITTER REMOVAL
 
0.010153741.15236216.2899.9
Work Order04-27-22
Work Began05-02-22
Work Completed
Time Computed05-01-22
Contract Working Days365
Addl Days Granted365
Working Days Charged701
Percent Time Used96
Contractor(s)
WORKQUEST
WORK SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6398-49-001
WORK SERVICES CORPORATION (0.00)
Contract #02220633
Totals153741.158053.86236216.2899.9

CountyPECOS
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6399-41-001
Proj IDSUP - 639941001
Work TypePICNIC AREA MAINTENANCE
 
0.01059998.0856662.00100.0
Work Order03-23-22
Work Began04-01-22
Work Completed03-31-24
Time Computed04-01-22
Contract Working Days731
Addl Days Granted0
Working Days Charged700
Percent Time Used95
Contractor(s)
WORKQUEST
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6399-41-001
FRESH START OF MONROE INC. (0.00)
Contract #02220636
Totals59998.082266.0856662.00100.0

CountyMIDLAND
HighwayBI0020E
FromVARIOUS
ToVARIOUS
CSJ6399-50-001
Proj IDRMC - 639950001
Work TypePUMP STATION & DRAINAGE SYSTEM CLEANING
 
0.010236560.00243409.7099.9
Work Order08-12-22
Work Began10-03-22
Work Completed
Time Computed09-01-22
Contract Working Days731
Addl Days Granted0
Working Days Charged577
Percent Time Used78
Contractor(s)
E.V.G. ENTERPRISE
SUBCONTRACTOR(S) FOR CCSJ: 6399-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04220602
Totals236560.000.00243409.7099.9

page 1 | page 2 | page 3 | page 4 | page 5