Monthly State Let Construction Report For Laredo District As Of Jul 13, 2018 Page 1 Of 2

Last Update: Friday, July 13, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLASALLE
HighwayIH 35
From@ FM 468
To.
CSJ0017-08-102
Proj IDSTP 2017(581)HES
Work TypeINSTALL TRAFFIC SIGNAL
 
0.800541921.20331733.8861.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-16-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days82
Addl Days Granted0
Working Days Charged58
Percent Time Used70
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-08-102
FLASHER LIMITED (4.02)
TRIPLE H FIELD SERVICES, LLC (2.99)
Contract #02173021
Totals541921.2066221.96331733.8861.2

CountyLASALLE
HighwayIH 35
From0.09 MI N OF IH35 UPRR UNDERPASS
To0.188 MI N OF FM 3408
CSJ0018-01-091
Proj IDNH 2018(779)
Work TypeBASE,ACP,GRAD,STR,PAV MRK
 
7.78111655295.270.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-14-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days465
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0018-01-091
PENHALL COMPANY (0.10)
FLASHER LIMITED (0.40)
AREA WIDE PROTECTIVE, INC. (0.45)
AARON CONCRETE CONTRACTORS, L.P. (0.52)
ROADWAY SPECIALTIES, INC. (0.58)
DIAMOND M FIELD SERVICES LLC (1.24)
PAVEMENT MARKINGS INC. (1.27)
TRAF-TEX, INC. (4.13)
BEAVER CONTRACTORS, LLC (29.91)
Contract #04183017
Totals11655295.270.000.000.0

CountyLASALLE
HighwayIH 35
FromFM 133
To1.031 MI S OF BI 35C (SOUTH INT)
CSJ0018-01-097
Proj IDC 18-1-97
Work TypePLANING, ACP, PAV MRK
 
10.7085687629.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days107
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0018-01-097
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07183037
Totals5687629.000.000.000.0

CountyLASALLE
HighwayIH 35
FromWEBB COUNTY LINE
ToFM 133
CSJ0018-02-085
Proj IDBR 1802(408)
Work TypeBRIDGE RAIL,SET,MBGF,SGT
 
17.743567072.610.000.0
CountyWEBB
HighwayVA
FromDISTRICTWIDE
To.
CSJ0922-00-064
Proj IDSTP 1802(313)
Work TypeBRIDGE RAIL,SET,MBGF,SGT
 
0.1001464381.240.000.0
CountyMAVERICK
HighwayFM 1021
FromFM 3443
To0.383 MI NORTH OF FM 2644
CSJ1229-01-066
Proj IDBR 1802(314)
Work TypeBRIDGE RAIL,SET,MBGF,SGT
 
15.896450736.140.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days308
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0018-02-085
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07183231
Totals2482189.990.000.000.0

CountyWEBB
HighwayIH 35
FromBI-35B OVERPASS
ToWEBB/LASALLE COUNTY LINE
CSJ0018-03-049
Proj IDNH 2018(729)
Work TypeBASE,ACP,GRADE,STR,SIGN,PAVMRK
 
1.1321521454.71189939.9512.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-24-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days74
Addl Days Granted0
Working Days Charged15
Percent Time Used20
Contractor(s)
REIM CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0018-03-049
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.96)
SOIL-TECH, INC (1.92)
Contract #03183031
Totals1521454.71189939.95189939.9512.4

CountyWEBB
HighwayIH 35
From0.945 MI N OF CALLAGHAN INT (EFR)
ToWEBB/LA SALLE COUNTY LINE
CSJ0018-03-056
Proj IDNH 2018(105)
Work TypeSEALCOAT & PAV MRKS
 
33.6471393636.951427412.8499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-16-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days97
Addl Days Granted0
Working Days Charged53
Percent Time Used54
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0018-03-056
PAVEMENT MARKINGS INC. (8.22)
ANGEL BROTHERS ENTERPRISES, LTD. (26.57)
Contract #09173005
Totals1393636.95171974.191427412.8499.9

CountyVAL VERDE
HighwayUS 90
From200 FT NORTHWEST OF PECOS BRIDGE
To200 FT SOUTHEAST OF PECOS BRIDGE
CSJ0022-06-051
Proj IDC 22-6-51
Work TypeAPCH SLAB, BASE, ACP, SURF, PAV MRK
 
0.325476631.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0022-06-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183257
Totals476631.600.000.000.0

CountyVAL VERDE
HighwayUS 90 ETC
FromAT 2ND ST
To.
CSJ0022-10-064
Proj IDSTP 1702(310)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
1.400419937.40391586.0093.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days110
Addl Days Granted8
Working Days Charged118
Percent Time Used100
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0022-10-064
G & E ESCOBEDO CONSTRUCTION, INC. (4.36)
Contract #06173034
Totals419937.4096251.16391586.0093.2

CountyKINNEY ETC
HighwayUS 90 ETC
From0.375 MI EAST OF SH 131
ToKINNEY/UVALDE COUNTY LINE
CSJ0023-04-065
Proj IDNH 2017(587)
Work TypeACP OVERLAY, PAV MRKS
 
47.10310014131.2210141279.8199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days300
Addl Days Granted0
Working Days Charged191
Percent Time Used63
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0023-04-065
FLASHER LIMITED (2.82)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.67)
PRIMATE CONSTRUCTION, INC. (1.37)
STRIPE-A-ZONE, INC. (0.73)
D&S TEXAS ICON CONSTRUCTION (0.19)
CLARK CONSTRUCTION OF TEXAS, INC. (3.22)
PENHALL COMPANY (0.00)
Contract #04173202
Totals10014131.221655486.1110141279.8199.9

CountyDIMMIT ETC
HighwayUS 83 ETC
FromAT FM 790
To.
CSJ0037-05-051
Proj IDSTP 1702(317)HES
Work TypeINSTALL INTERSECTION FLASHING BEACO
 
1.600452670.20322861.0071.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-17
Work Began02-01-18
Work Completed
Time Computed00-00-00
Contract Working Days133
Addl Days Granted0
Working Days Charged121
Percent Time Used90
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0037-05-051
PAVEMENT MARKINGS INC. (7.98)
Contract #06173213
Totals452670.2037613.10322861.0071.3

CountyWEBB
HighwaySH 359 ETC
FromJUDITH GUTIERREZ PARKWAY
To8.892 MILES EAST OF SL 20
CSJ0086-01-091
Proj IDSTP 1802(248)HES
Work TypePROFILE EDGE MRK, PROFILE CL MRK
 
79.01128248453.660.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days371
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0086-01-091
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183256
Totals28248453.660.000.000.0

CountyWEBB
HighwaySL 20
From0.457 MI S OF SS 400 (KCS RR OVP)
To0.450 MI N OF US 59 (STA. 140+00)
CSJ0086-14-046
Proj IDCBI 2013(281)
Work TypeGRAD, WID STRS, BASE AND PAV
 
1.75133883949.2032383823.3095.5
CountyWEBB
HighwaySL 20
From0.457 MI S OF SS 400 (KCS RR OVP)
To0.450 MI N OF US 59 (STA. 140+00)
CSJ0086-14-056
Proj IDROW 86-14-56
Work TypeACQUISITION & UTILITY ADJUSTMENTS
 
1.7511993938.701949054.9097.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-03-14
Work Began07-27-15
Work Completed
Time Computed00-00-00
Contract Working Days535
Addl Days Granted26
Working Days Charged560
Percent Time Used99
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0086-14-046
ANGEL BROTHERS ENTERPRISES, LTD. (19.52)
CABCOS CONTRACTORS LLC (3.32)
HIGHWAY BARRICADES AND SERVICES, LLC (0.80)
LAREDO STRIPING INC. (0.78)
SOIL-TECH, INC. (0.55)
STAR OPERATIONS, INC. (3.77)
VOGES DRILLING CO. (0.61)
WEBBER BARRIER SERVICES, LLC. (0.72)
SAN ANTONIO TELEPHONE COMPANY INC. (0.07)
REIM CONSTRUCTION, INC. (0.78)
AARON CONCRETE CONTRACTORS, L.P. (2.09)
FRANK JR REINFORCEMENT LLC (0.03)
RAMOS MASONRY (0.11)
V.C. HUFF, L.L.C. (2.37)
IVY ROSALVA CRUZ DBA IVY"S TRUCKING (0.09)
SOUTH TEXAS PAINTING COMPANY (0.18)
SCOTT DERR PAINTING CO, LLC (0.29)
E&E GROUP INC., DBA LIGHT IT UP ELECTRIC (0.07)
GILMAR CONSTRUCTION, LTD. (0.07)
Contract #08143002
Totals35877887.900.0034332878.2095.6

CountyWEBB
HighwaySL 20
FromSH 359
ToSPUR 400
CSJ0086-14-061
Proj IDSTP 1502(617)MM
Work TypeGRADING, BASE, STRUCTURES & SURFACE
 
2.40525541056.4016992631.9166.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-04-15
Work Began03-07-16
Work Completed
Time Computed00-00-00
Contract Working Days596
Addl Days Granted0
Working Days Charged534
Percent Time Used89
Contractor(s)
OSCAR RENDA CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0086-14-061
ANGEL BROTHERS ENTERPRISES, LTD. (11.40)
HIGHWAY BARRICADES AND SERVICES, LLC (1.53)
LAREDO STRIPING INC. (2.36)
S & S BRIDGE PAINTING, INC. (0.19)
SOIL-TECH, INC. (1.05)
W. W. FOUNDATION DRILLING, LTD. (2.97)
TEXAS STEEL (1.85)
CANTU ELECTRIC CO., INC. (2.46)
RRR SEALCOAT & STRIPING, LLC (0.05)
Contract #08153003
Totals25541056.40570660.5616992631.9166.5

CountyWEBB
HighwaySL 20
From0.330 MILES WEST OF IH 35
To0.160 MILES WEST OF MCPHERSON
CSJ0086-14-065
Proj IDCBI 1602(504)
Work TypeFLEX BASE,SURF,BRIDGE AND PAV MRK
 
4.38025596044.497529842.1129.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-01-17
Work Began01-02-18
Work Completed
Time Computed00-00-00
Contract Working Days724
Addl Days Granted0
Working Days Charged178
Percent Time Used24
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0086-14-065
ANGEL BROTHERS HOLDINGS CORP. (3.51)
CANTU ELECTRIC CO., INC. (5.77)
HIGHWAY BARRICADES AND SERVICES, LLC (0.57)
ATS DRILLING, INC. (3.31)
DEPENDABLE ENTERPRISES, INC. (0.59)
MONTALVO BRIDGE SYSTEMS, LLC (1.93)
BOWMAN ENGINEERING & CONSULTING, INC (0.24)
E&E GROUP INC., DBA LIGHT IT UP ELECTRIC (0.07)
Contract #07173004
Totals25596044.49976569.237529842.1129.4

CountyWEBB
HighwaySL 20
From0.45 MI EAST OF INTERNATIONAL BLVD
To0.25 MI WEST OF MCPHERSON ROAD
CSJ0086-14-066
Proj IDNH 2016(400)
Work TypeFLEX BSE, SURF, BRIDGE, PAV MRK ETC
 
1.41721976081.1521596972.6598.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-16-16
Work Began05-23-16
Work Completed
Time Computed00-00-00
Contract Working Days387
Addl Days Granted107
Working Days Charged494
Percent Time Used100
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0086-14-066
AARON CONCRETE CONTRACTORS, L.P. (0.75)
ALTUS TRAFFIC MANAGEMENT LLC (0.15)
ATS DRILLING, INC. (0.82)
D&S TEXAS ICON CONSTRUCTION (1.25)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.19)
FLASHER EQUIPMENT COMPANY (0.35)
FOREMOST PAVING, INC. (9.45)
FUQUAY, INC. (0.25)
PENHALL COMPANY (0.05)
PRIMATE CONSTRUCTION, INC. (0.06)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.14)
SOUTH TEXAS PAINTING COMPANY (0.12)
THE LEVY COMPANY, L.P. (4.89)
CUATRO T CONSTRUCTION, INC. (3.59)
INDUS CONSTRUCTION, L.P. (0.06)
Contract #12153003
Totals21976081.1514055.0021596972.6598.2

CountyVAL VERDE ETC
HighwayUS 277 ETC
From7.953 MI SOUTH OF EDWARDS CL
To12.336 MI SOUTH OF EDWARDS CL
CSJ0160-04-049
Proj IDNH 2018(088)
Work TypeSEALCOAT & PAV MRKS
 
54.3902245195.912239189.4999.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-16-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days153
Addl Days Granted0
Working Days Charged64
Percent Time Used41
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0160-04-049
CHEROKEE SERVICES (1.82)
INTERSTATE BARRICADES & MARKINGS, INC. (17.32)
Contract #09173014
Totals2245195.9129826.502239189.4999.7

CountyWEBB
HighwaySH 44
FromLOS OLMOS CREEK
ToIN WEBB COUNTY
CSJ0237-03-030
Proj IDBR 1602(506)
Work TypeREPLACEMENT OF AN EXISTING BRIDGE
 
0.3023538171.863510797.5599.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-20-16
Work Began03-27-17
Work Completed
Time Computed00-00-00
Contract Working Days256
Addl Days Granted0
Working Days Charged253
Percent Time Used98
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0237-03-030
RIO GRANDE REBAR PLACING, LTD. (2.26)
D&S TEXAS ICON CONSTRUCTION (0.43)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (3.13)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.36)
FLASHER EQUIPMENT COMPANY (1.22)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.25)
MUNOZ FOUNDATION DRILLING, INC. (0.71)
SCOTT DERR PAINTING CO, LLC (0.01)
ANDERSON COLUMBIA CO., INC. (7.19)
Contract #08163016
Totals3538171.8615714.403510797.5599.2

CountyDIMMIT
HighwayFM 133
FromUS 83
To5.0 MILES EAST OF US 83
CSJ0237-07-013
Proj IDSTP 1702(496)
Work TypeBASE,GRADE,ACP,PAV MARK
 
18.7309690620.286849394.6970.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-16-17
Work Began02-05-18
Work Completed
Time Computed00-00-00
Contract Working Days185
Addl Days Granted0
Working Days Charged100
Percent Time Used54
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0237-07-013
APEX HIGHWAY SERVICES LLC (0.21)
PRIMATE CONSTRUCTION, INC. (0.39)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.47)
PENHALL COMPANY (0.48)
FLASHER LIMITED (0.54)
(USE 06621)D. I. J. CONSTRUCTION, INC. (0.55)
D&S TEXAS ICON CONSTRUCTION (3.01)
ANDALE CONSTRUCTION INC (5.30)
RELMCO, INC. (15.24)
CMT ENGINEERING, INC. (0.06)
PHIL LYNE SERVICES, LLC (0.40)
Contract #07173208
Totals9690620.281093866.596849394.6970.6

CountyMAVERICK ETC
HighwayUS 277
FromKINNEY/MAVERICK COUNTY LINE
To0.273 MI S OF FM 1665 SOUTHERN INT
CSJ0299-03-050
Proj IDNH 1702(691)
Work TypeBASE,WIDEN,GRAD,SURF,PAVMRK&SIGN
 
92.75320795394.701330644.516.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-21-17
Work Began01-23-18
Work Completed
Time Computed00-00-00
Contract Working Days575
Addl Days Granted0
Working Days Charged109
Percent Time Used18
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0299-03-050
A BROTHERS MILLING, LLC (1.33)
RELMCO, INC. (9.89)
D&S TEXAS ICON CONSTRUCTION (3.03)
CHEROKEE SERVICES (0.24)
CLARK CONSTRUCTION OF TEXAS, INC. (0.00)
INDUSTRIAL FABRICS, INC. (2.80)
PENHALL COMPANY (0.76)
RVP CONSTRUCTION, INC. (2.97)
WEST TEXAS RUMBLE STRIP (0.28)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.56)
FLASHER LIMITED (2.93)
J. CARROLL WEAVER, INC. (4.64)
Contract #08173203
Totals20795394.70456350.501330644.516.3

CountyMAVERICK ETC
HighwayUS 277 ETC
From0.501 M SOUTH OF BU 277(N CEYLON)
ToUS 57
CSJ0299-04-068
Proj IDNH 2017(794)
Work TypeACP OVERLAY AND PAV MRKS
 
14.7256593233.706249675.7494.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-24-17
Work Began07-17-17
Work Completed
Time Computed00-00-00
Contract Working Days97
Addl Days Granted22
Working Days Charged117
Percent Time Used98
Contractor(s)
H. L. ZUMWALT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0299-04-068
DELGADO"S CONSTRUCTION (4.71)
FLASHER EQUIPMENT COMPANY (2.28)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (6.90)
Contract #03173217
Totals6593233.7017458.776249675.7494.7

page 1 | page 2