Monthly State Let Maintenance Report For Houston District As Of Jun 08, 2018 Page 9 Of 11

Last Update: Tuesday, June 12, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWALLER
HighwayUS0290
FromVARIOUS HWYS IN WALLER COUNTY
ToVARIOUS HWYS IN WALLER COUNTY
CSJ6317-09-001
Proj IDRMC - 631709001
Work TypeREFLECTIVE PAVEMNT MARKINGS
 
0.001415063.770.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-14-18
Work Began00-00-00
Work Completed
Time Computed05-14-18
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6317-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02184007
Totals415063.770.000.000.0

CountyGALVESTON
HighwayFM0517
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6317-23-001
Proj IDRMC - 631723001
Work TypeDITCH CLEANING AND RESHAPING
 
0.001279200.00346483.7599.9
Work Order00-00-00
Work Began12-05-17
Work Completed
Time Computed12-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged176
Percent Time Used48
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6317-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10174003
Totals279200.000.00346483.7599.9

CountyWALLER
HighwayUS0290
FromVARIOUS ROADWAYS IN WALLER COUNTY
ToVARIOUS ROADWAYS IN WALLER COUNTY
CSJ6317-64-001
Proj IDRMC - 631764001
Work TypeBRIDGE DECK REPAIR
 
0.001423690.000.000.0
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed12-11-17
Contract Working Days365
Addl Days Granted0
Working Days Charged137
Percent Time Used37
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6317-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09174003
Totals423690.000.000.000.0

CountyHARRIS
HighwayIH0045
FromIH45 SB OVER US59&MISC STRS.,IH45 NB
ToOVER SP 5, SS548 TO IH610 NL
CSJ6318-48-001
Proj IDBPM - 631848001
Work TypeREPLACE/RESET BEARING PADS,ETC
 
0.001325600.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02184205
Totals325600.000.000.000.0

CountyFORT BEND
HighwayUS0059
FromVARIOUS HWYS IN FORT BEND COUNTY
ToVARIOUS HWYS IN FORT BEND COUNTY
CSJ6318-70-001
Proj IDRMC - 631870001
Work TypeCLEANING AND SWEEPING OF HIGHWAYS
 
0.001695757.92240184.2034.5
Work Order00-00-00
Work Began11-20-17
Work Completed
Time Computed11-20-17
Contract Working Days365
Addl Days Granted0
Working Days Charged133
Percent Time Used36
Contractor(s)
EXPERT MAINTENANCE & CONSTRUCTION SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08174205
Totals695757.9258866.20240184.2034.5

CountyBRAZORIA
HighwayFM1462
FromFM 521
ToSH 288
CSJ6319-72-001
Proj IDRMC - 631972001
Work TypeACP OVERLAY
 
2.150648550.230.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days24
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 6319-72-001
BATTERSON,LLP (5.50)
THIRD COAST SERVICES LLC (2.63)
INTERSTATE BARRICADES & MARKINGS, INC. (0.58)
ISI CONTRACTING, INC. (1.21)
COX PAVING OF TEXAS, INC. (16.00)
Contract #04184005
Totals648550.230.000.000.0

CountyGALVESTON
HighwaySH0146
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6319-75-001
Proj IDRMC - 631975001
Work TypeGUARDRAIL REPAIR
 
0.001322162.00105734.0632.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-02-18
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged145
Percent Time Used39
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10174013
Totals322162.0010999.08105734.0632.8

CountyFORT BEND
HighwayUS0059
FromVARIOUS HWYS IN FORT BEND COUNTY
ToVARIOUS HWYS IN FORT BEND COUNTY
CSJ6319-99-001
Proj IDRMC - 631999001
Work TypeREFLECTIVE PAVEMENT MARKINGS (LONG LINE)
 
0.001445906.0065235.9214.6
Work Order00-00-00
Work Began01-01-18
Work Completed
Time Computed01-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged116
Percent Time Used31
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6319-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09174004
Totals445906.0065235.9265235.9214.6

CountyGALVESTON
HighwayFM2004
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6320-04-001
Proj IDRMC - 632004001
Work TypeREFLECTIVE PAVEMENT MARKERS (LONG LINE)
 
0.001476730.28432557.1890.7
Work Order00-00-00
Work Began01-09-18
Work Completed
Time Computed01-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged145
Percent Time Used39
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6320-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10174209
Totals476730.2811.40432557.1890.7

CountyHARRIS
HighwaySL0008
FromVARIOUS HIGHWAYS IN SOUTHEAST HARRIS COU
ToVARIOUS HIGHWASY IN SOUTHEAST HARRIS COU
CSJ6320-08-001
Proj IDRMC - 632008001
Work TypeHIGH EDGE REMOVAL
 
0.001418860.00411485.8898.2
Work Order00-00-00
Work Began01-04-18
Work Completed
Time Computed01-02-18
Contract Working Days365
Addl Days Granted0
Working Days Charged142
Percent Time Used38
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6320-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10174004
Totals418860.0024195.00411485.8898.2

CountyBRAZORIA
HighwaySH0288
FromVARIOUS LOCATIONS IN BRAZORIA CTY
ToVARIOUS LOCATIONS IN BRAZORIA CTY
CSJ6320-15-001
Proj IDRMC - 632015001
Work TypeCLEANING BRIDGE JOINTS
 
0.001433000.00366959.0084.7
Work Order00-00-00
Work Began02-01-18
Work Completed
Time Computed02-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged82
Percent Time Used22
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6320-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10174207
Totals433000.00158200.00366959.0084.7

CountyGALVESTON
HighwayFM1764
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6320-96-001
Proj IDRMC - 632096001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.001524534.00269855.0051.4
Work Order00-00-00
Work Began12-04-17
Work Completed
Time Computed12-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged176
Percent Time Used48
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6320-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10174005
Totals524534.0040688.00269855.0051.4

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN HOUSTON DISTRICT
ToVARIOUS HWYS IN HOUSTON DISTRICT
CSJ6321-63-001
Proj IDRMC - 632163001
Work TypeLOOP DET REP AND/OR REPLCMNT
 
0.0011257495.00152175.5012.1
Work Order03-22-18
Work Began04-02-18
Work Completed
Time Computed04-02-18
Contract Working Days730
Addl Days Granted0
Working Days Charged53
Percent Time Used7
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6321-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184003
Totals1257495.00127682.50152175.5012.1

CountyGALVESTON
HighwaySH0146
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6321-84-001
Proj IDRMC - 632184001
Work TypeASHPHALT PAVEMENT REPAIR
 
0.001609900.00263166.7643.1
Work Order00-00-00
Work Began04-02-18
Work Completed
Time Computed02-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged114
Percent Time Used31
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6321-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11174204
Totals609900.000.00263166.7643.1

CountyHARRIS
HighwaySH0249
FromVARIOUS HIGHWAYS IN N. HARRIS COUNTY
ToVARIOUS HIGHWAYS IN N. HARRIS COUNTY
CSJ6322-47-001
Proj IDRMC - 632247001
Work TypeGUARDRAIL REPAIR
 
0.001340930.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-25-18
Work Began00-00-00
Work Completed
Time Computed06-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6322-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03184205
Totals340930.000.000.000.0

CountyGALVESTON
HighwaySH0275
FromFM 188
To0.2 MILES EAST OF 77TH STREET
CSJ6322-60-001
Proj IDRMC - 632260001
Work TypeMILLING,BASE RPR,SEAL COAT,1"TOMF&C STRI
 
0.821717548.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days55
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6322-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05184204
Totals717548.800.000.000.0

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN HOUSTON DISTRICT
ToVARIOUS HWYS IN HOUSTON DISTRICT
CSJ6323-09-001
Proj IDRMC - 632309001
Work TypeMNT OF TRAFFIC SGNLS
 
0.0011657565.20156414.309.4
Work Order03-30-18
Work Began04-03-18
Work Completed
Time Computed04-03-18
Contract Working Days730
Addl Days Granted0
Working Days Charged48
Percent Time Used6
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184205
Totals1657565.20144033.80156414.309.4

CountyHARRIS
HighwayIH0610
FromVARIOUS HWYS IN HOUSTON DISTRICT
ToVARIOUS HWYS IN HOUSTON DISTRICT
CSJ6323-37-001
Proj IDRMC - 632337001
Work TypeMNT OF VIVDS
 
0.0011364234.430.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-30-18
Work Began06-04-18
Work Completed
Time Computed06-04-18
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6323-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03184002
Totals1364234.430.000.000.0

CountyHARRIS
HighwaySH0249
FromVARIOUS HIGHWAYS IN NORTH HARRIS COUNTY
ToVARIOUS HIGHWAYS IN NORTH HARRIS COUNTY
CSJ6324-18-001
Proj IDRMC - 632418001
Work TypeFULL DEPTH CONC & ASPHALT REPAIR
 
0.001631700.00118160.3618.7
Work Order03-26-18
Work Began04-29-18
Work Completed
Time Computed04-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged50
Percent Time Used13
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6324-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184206
Totals631700.00118160.36118160.3618.7

CountyMONTGOMERY
HighwayIH0045
FromWALKER COUNTY LINE TO STOKES STREET
ToLOCATED IN HARRIS COUNTY
CSJ6325-74-001
Proj IDRMC - 632574001
Work TypeGENERAL MAINTENANCE OF IH 45
 
0.0013939621.95442064.3311.2
Work Order02-28-18
Work Began03-01-18
Work Completed
Time Computed03-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged89
Percent Time Used24
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6325-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184005
Totals3939621.95177439.82442064.3311.2

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11