Monthly State Let Maintenance Report For Houston District As Of Jul 12, 2019 Page 10 Of 10
Last Update: Friday, July 12, 2019
|
|
Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | HARRIS |
Highway | IH0610 |
From | IH 610 |
To | IH 610 |
CSJ | 6344-99-001 |
Proj ID | RMC - 634499001 |
Work Type | GENERAL MAINTENANCE HOU METRO AREA |
|
| 0.001 | 7890502.50 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
ISI CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6344-99-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 07194014 |
| Totals | 7890502.50 | 0.00 | 0.00 | 0.0 |
|
County | WALLER |
Highway | US0290 |
From | VARIOUS HWYS IN WALLER COUNTY |
To | VARIOUS HWYS IN WALLER COUNTY |
CSJ | 6345-54-001 |
Proj ID | RMC - 634554001 |
Work Type | ASPHALT PAVEMENT REPAIR |
|
| 0.001 | 561200.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
MAIN LANE INDUSTRIES LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6345-54-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 07194015 |
| Totals | 561200.00 | 0.00 | 0.00 | 0.0 |
|