Monthly State Let Maintenance Report For Fort Worth District As Of Jun 08, 2018 Page 4 Of 5

Last Update: Tuesday, June 12, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTARRANT
HighwayIH0030
FromVARIOUS LOCATIONS IN
ToTXDOT FORT WORTH DISTRICT
CSJ6315-38-001
Proj IDRMC - 631538001
Work TypeROADWAY SIGN MAINTENANCE
 
0.001457747.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SELECT STRIPING LLC
SUBCONTRACTOR(S) FOR CCSJ: 6315-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174017
Totals457747.000.000.000.0

CountyTARRANT
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToSOUTH TARRANT COUNTY
CSJ6315-39-001
Proj IDRMC - 631539001
Work TypeSWEEPING & DEBRIS REMOVAL
 
0.010830132.4691707.2011.0
Work Order00-00-00
Work Began04-03-18
Work Completed
Time Computed04-03-18
Contract Working Days365
Addl Days Granted0
Working Days Charged53
Percent Time Used14
Contractor(s)
ICA MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174010
Totals830132.4655089.0791707.2011.0

CountyTARRANT
HighwayIH0035W
FromVARIOUS LOCATIONS WITHIN
ToSOUTH & NORTH TARRANT COUNTIES
CSJ6315-63-001
Proj IDRMC - 631563001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010827500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6315-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04184016
Totals827500.000.000.000.0

CountyTARRANT
HighwayIH0020
FromVARIOUS LOCATIONS IN
ToTXDOT FORT WORTH DISTRICT
CSJ6315-96-001
Proj IDRMC - 631596001
Work TypeROADWAY ILLUMINATION MAINTENANCE
 
0.001493024.8049784.0710.0
Work Order03-27-18
Work Began04-02-18
Work Completed
Time Computed04-02-18
Contract Working Days365
Addl Days Granted0
Working Days Charged54
Percent Time Used14
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-96-001
TX DOWN UNDER CONSTRUCTION LLC (0.42)
ALTUS TRAFFIC MANAGEMENT LLC (0.73)
Contract #12174015
Totals493024.8032616.5249784.0710.0

CountyWISE
HighwayUS0081
FromWISE AND JACK COUNTIES
ToWISE AND JACK COUNTIES
CSJ6317-26-001
Proj IDRMC - 631726001
Work TypeROADSIDE MOWING
 
0.100393071.420.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6317-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174016
Totals393071.420.000.000.0

CountyWISE
HighwayUS0380
FromWISE AND JACK COUNTIES
ToPARKER AND PALO PINTO COUNTIES
CSJ6317-60-001
Proj IDRMC - 631760001
Work TypeGUARDRAIL INSTALLATION AND REPAIR
 
0.100793602.00200408.0025.2
Work Order01-31-18
Work Began02-01-18
Work Completed
Time Computed02-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged114
Percent Time Used31
Contractor(s)
T&L CLEANING SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6317-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174207
Totals793602.0048655.00200408.0025.2

CountyTARRANT
HighwaySH0183
FromVARIOUS
ToVARIOUS
CSJ6317-66-001
Proj IDRMC - 631766001
Work TypeTHERMOPLASTIC LONG LINE STRIPING
 
0.010576226.80128605.6022.3
Work Order04-27-18
Work Began04-29-18
Work Completed
Time Computed04-29-18
Contract Working Days90
Addl Days Granted0
Working Days Charged16
Percent Time Used17
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6317-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09174016
Totals576226.80128605.60128605.6022.3

CountyTARRANT
HighwaySH0114
FromVARIOUS ROADWAYS IN
ToNORTH TARRANT COUNTY
CSJ6318-03-001
Proj IDRMC - 631803001
Work TypeR.O.W.MOWING, LITTER REMOVAL, HERBICIDE
 
0.010898962.7017710.251.9
Work Order04-16-18
Work Began04-18-18
Work Completed
Time Computed04-18-18
Contract Working Days365
Addl Days Granted0
Working Days Charged40
Percent Time Used10
Contractor(s)
ICA MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174215
Totals898962.7016516.5017710.251.9

CountyWISE
HighwaySH0114
FromWISE,JACK,PARKER,PALO PINTO COUNTIES
ToWISE,JACK,PARKER,PALO PINTO COUNTIES
CSJ6318-55-001
Proj IDRMC - 631855001
Work TypeFLEXIBLE PAVEMENT REPAIR
 
0.1002781230.00621596.2022.3
Work Order04-11-18
Work Began04-11-18
Work Completed
Time Computed04-11-18
Contract Working Days259
Addl Days Granted0
Working Days Charged34
Percent Time Used13
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184215
Totals2781230.0060000.00621596.2022.3

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATIONS IN PARKER COUNTY
ToPALO PINTO COUNTY
CSJ6318-59-001
Proj IDRMC - 631859001
Work TypeREFLECTORIZED PVMT MRK AND MRKS
 
0.010935508.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-05-18
Work Began00-00-00
Work Completed
Time Computed06-05-18
Contract Working Days155
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6318-59-001
BRYDL CONTRACTING, INC. (4.70)
Contract #03184214
Totals935508.500.000.000.0

CountyWISE
HighwayUS0081
FromWISE AND JACK COUNTIES
ToWISE AND JACK COUNTIES
CSJ6319-24-001
Proj IDRMC - 631924001
Work TypeROUTINE SWEEPING
 
0.100294131.0077465.1026.3
Work Order03-09-18
Work Began03-22-18
Work Completed
Time Computed03-12-18
Contract Working Days365
Addl Days Granted0
Working Days Charged75
Percent Time Used20
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174216
Totals294131.0031065.0077465.1026.3

CountyTARRANT
HighwaySH0360
FromABRAMS STREET
ToMAYFIELD ROAD
CSJ6322-82-001
Proj IDRMC - 632282001
Work TypeASBESTOS ABATEMENT OF NB AND SB BRIDGES
 
0.140387265.00303290.0078.3
Work Order00-00-00
Work Began04-16-18
Work Completed
Time Computed04-16-18
Contract Working Days77
Addl Days Granted0
Working Days Charged30
Percent Time Used38
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6322-82-001
1 PRIORITY ENVIRONMENTAL SERVICES, INC. (71.41)
ACME BARRICADES, LLC (14.43)
Contract #01184201
Totals387265.00191465.00303290.0078.3

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATIONS IN
ToPARKER AND PALO PINTO
CSJ6323-27-001
Proj IDRMC - 632327001
Work TypeROADSIDE MOWING AND HERBICIDE
 
0.0101715509.00129914.407.5
Work Order04-11-18
Work Began04-16-18
Work Completed
Time Computed04-16-18
Contract Working Days365
Addl Days Granted0
Working Days Charged45
Percent Time Used12
Contractor(s)
LONESTAR HAWK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-27-001
JASCO (48.52)
Contract #01184216
Totals1715509.0086848.00129914.407.5

CountyTARRANT
HighwayFM1187
FromFM 731
ToEAST OF ROCK MEADOW DRIVE
CSJ6324-23-001
Proj IDRMC - 632423001
Work TypeADDING TURN LANE
 
1.584354604.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6324-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05184201
Totals354604.500.000.000.0

CountyTARRANT
HighwayIH0030
FromDISTRICTWIDE
ToVARIOUS LOCATIONS
CSJ6324-29-001
Proj IDRMC - 632429001
Work TypePREVENTIVE SIGNAL MAINTENANCE
 
0.100553358.5814383.552.5
Work Order04-27-18
Work Began04-30-18
Work Completed
Time Computed04-30-18
Contract Working Days365
Addl Days Granted0
Working Days Charged26
Percent Time Used7
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6324-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02184003
Totals553358.5814383.5514383.552.5

CountyJOHNSON
HighwayIH0035W
FromVARIOUS ROADWAYS WITHIN JOHNSON, HOOD,
ToERATH AND SOMERVELL COUNTIES
CSJ6324-61-001
Proj IDRMC - 632461001
Work TypeREFLECTORIZED PAVEMENT MRKINGS AND MRKS
 
0.010528709.440.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days125
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6324-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06184016
Totals528709.440.000.000.0

CountyTARRANT
HighwaySH0114
FromVARIOUS ROADWAYS IN
ToNORTH TARRANT COUNTY
CSJ6324-76-001
Proj IDRMC - 632476001
Work TypeROUTINE SWEEPING AND DEBRIS REMOVAL
 
0.010623817.650.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6324-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174219
Totals623817.650.000.000.0

CountyWISE
HighwayUS0081
FromWISE AND JACK COUNTIES
ToWISE AND JACK COUNTIES
CSJ6324-88-001
Proj IDRMC - 632488001
Work TypeTHERMOPLASTIC STRIPING AND HANDWORK
 
0.100309192.71299306.0196.8
Work Order04-15-18
Work Began04-16-18
Work Completed
Time Computed04-16-18
Contract Working Days44
Addl Days Granted0
Working Days Charged7
Percent Time Used15
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-88-001
RED SIXTEEN CONSTRUCTION, INC (29.97)
Contract #02184210
Totals309192.7111006.00299306.0196.8

CountyJOHNSON
HighwayIH0035W
FromVARIOUS ROADWAYS WITHIN
ToJOHNSON COUNTY
CSJ6324-95-001
Proj IDRMC - 632495001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.0101881428.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06184214
Totals1881428.000.000.000.0

CountyTARRANT
HighwayIH0020
FromIN ERATH,PALO PINTO,PARKER,TARRANT CNTYS
ToIN THE FORT WORTH DISTRICT
CSJ6325-01-001
Proj IDRMC - 632501001
Work TypeINTERSTATE SIGN MAINTENANCE
 
0.001532448.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days42
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 6325-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06184220
Totals532448.700.000.000.0