Monthly State Let Maintenance Report For Fort Worth District As Of Apr 10, 2018 Page 2 Of 4

Last Update: Friday, April 20, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyJOHNSON
HighwaySH0171
FromVARIOUS ROADWAYS IN
ToJOHNSON COUNTY
CSJ6281-09-001
Proj IDRMC - 628109001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010639283.203119697.3099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-25-15
Work Began00-00-00
Work Completed
Time Computed04-01-15
Contract Working Days25
Addl Days Granted25
Working Days Charged50
Percent Time Used100
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12144011
Totals639283.200.003119697.3099.9

CountyTARRANT
HighwayIH0820
FromVARIOUS ROADWAYS IN
ToNORTH TARRANT COUNTY
CSJ6281-24-001
Proj IDRMC - 628124001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010659900.001550104.14100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-03-15
Work Completed08-11-15
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged23
Percent Time Used92
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6281-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12144211
Totals659900.000.001550104.14100.0

CountyTARRANT
HighwayIH0035W
FromVARIOUS BRIDGES IN
ToTHE FORT WORTH DISTRICT
CSJ6283-26-001
Proj IDBPM - 628326001
Work TypeBRIDGE REPAIR
 
0.010689452.00865937.5999.9
Work Order01-17-17
Work Began01-17-17
Work Completed
Time Computed01-17-17
Contract Working Days184
Addl Days Granted20
Working Days Charged235
Percent Time Used115
Contractor(s)
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6283-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164003
Totals689452.000.00865937.5999.9

CountyTARRANT
HighwayUS0377
FromVARIOUS LOCATIONS IN TARRANT, JOHNSON,
ToAND PARKER COUNTIES
CSJ6284-11-001
Proj IDRMC - 628411001
Work TypeTARFFIC SIGNAL MAINTENANCE
 
0.020580600.0090961.2815.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-16
Work Began00-00-00
Work Completed
Time Computed07-25-16
Contract Working Days302
Addl Days Granted1
Working Days Charged70
Percent Time Used23
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6284-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08154007
Totals580600.000.0090961.2815.6

CountyTARRANT
HighwayIH0030
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6287-56-001
Proj IDRMC - 628756001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010738774.11632495.5190.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-08-16
Work Began02-08-16
Work Completed
Time Computed02-16-16
Contract Working Days365
Addl Days Granted46
Working Days Charged410
Percent Time Used99
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6287-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154002
Totals738774.110.00632495.5190.2

CountyTARRANT
HighwayIH0820
FromVARIOUS ROADWAYS IN
ToNORTH TARRANT COUNTY
CSJ6287-57-001
Proj IDRMC - 628757001
Work TypeSWEEPING & DEBRIS REMOVAL
 
0.010421504.75410388.9897.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-16
Work Began03-02-16
Work Completed
Time Computed03-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged350
Percent Time Used95
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6287-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154214
Totals421504.750.00410388.9897.3

CountyTARRANT
HighwayIH0030
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6288-08-001
Proj IDRMC - 628808001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010899300.00908187.3499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-28-15
Work Began09-30-15
Work Completed
Time Computed10-05-15
Contract Working Days60
Addl Days Granted0
Working Days Charged70
Percent Time Used116
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06154201
Totals899300.000.00908187.3499.9

CountyERATH
HighwayFM2156
FromVARIOUS ROADWAYS IN ERATH, HOOD, WISE,
ToSOMERVELL, PARKER, & PALO PINTO CONTIES
CSJ6288-80-001
Proj IDRMC - 628880001
Work TypeSEAL COAT
 
0.0101589066.921477632.27100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-15-16
Work Began06-15-16
Work Completed01-04-17
Time Computed06-22-16
Contract Working Days30
Addl Days Granted0
Working Days Charged29
Percent Time Used96
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-80-001
BARRICADES PLUS, LLC (1.88)
FLAT LINE, INC. (15.08)
BRYDL CONTRACTING, INC. (0.83)
Contract #10154216
Totals1589066.920.001477632.27100.0

CountyTARRANT
HighwayIH0035W
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6289-08-001
Proj IDRMC - 628908001
Work TypeGUARDRAIL INSTALLATION/REPAIR
 
0.0104024750.003843207.0095.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-16
Work Began01-07-16
Work Completed
Time Computed01-14-16
Contract Working Days365
Addl Days Granted81
Working Days Charged444
Percent Time Used99
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6289-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11154210
Totals4024750.000.003843207.0095.4

CountyJOHNSON
HighwayUS0067
FromVARIOUS ROADWAYS WITHIN
ToJOHNSON COUNTY
CSJ6293-58-001
Proj IDRMC - 629358001
Work TypeVEGETATION MGMT RURAL
 
0.0101029409.00683945.0066.4
Work Order04-07-16
Work Began05-04-16
Work Completed
Time Computed04-14-16
Contract Working Days214
Addl Days Granted0
Working Days Charged135
Percent Time Used63
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6293-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154213
Totals1029409.000.00683945.0066.4

CountyTARRANT
HighwayIH0020
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6296-04-001
Proj IDRMC - 629604001
Work TypeFULL-WIDTH MOWING
 
0.010690320.00669811.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-19-16
Work Began05-23-16
Work Completed12-19-17
Time Computed05-26-16
Contract Working Days120
Addl Days Granted0
Working Days Charged118
Percent Time Used98
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6296-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154014
Totals690320.000.00669811.00100.0

CountyTARRANT
HighwaySH0114
FromVARIOUS ROADWAYS IN
ToNORTH TARRANT COUNTY
CSJ6296-23-001
Proj IDRMC - 629623001
Work TypeROADSIDE MOWING
 
0.010857304.00433023.0050.5
Work Order05-12-17
Work Began05-17-16
Work Completed
Time Computed05-17-16
Contract Working Days184
Addl Days Granted0
Working Days Charged71
Percent Time Used38
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6296-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154015
Totals857304.000.00433023.0050.5

CountyPALO PINTO
HighwayUS0281
FromVARIOUS ROADWAYS IN PALO PINTO
ToAND ERATH COUNTIES
CSJ6296-64-001
Proj IDRMC - 629664001
Work TypeMOWING AND HERBICIDE
 
0.010604371.40571214.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-16-16
Work Began05-10-16
Work Completed12-12-17
Time Computed06-20-16
Contract Working Days140
Addl Days Granted0
Working Days Charged95
Percent Time Used67
Contractor(s)
LONESTAR HAWK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154201
Totals604371.400.00571214.50100.0

CountyPARKER
HighwayIH0020
FromVARIOUS ROADWAYS IN
ToPARKER COUNTY
CSJ6296-65-001
Proj IDRMC - 629665001
Work TypeMOWING AND HERBICIDE
 
0.010663779.480.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-05-16
Work Began00-00-00
Work Completed
Time Computed05-13-16
Contract Working Days144
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FMWB, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154202
Totals663779.480.000.000.0

CountyERATH
HighwayUS0067
FromVARIOUS ROADWAYS WITHIN HOOD, ERATH,
ToAND SOMERVELL COUNTIES
CSJ6296-90-001
Proj IDRMC - 629690001
Work TypeHES FLEX PVMT REPAIR
 
0.0101180000.003087940.21100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-06-16
Work Began09-06-16
Work Completed11-20-17
Time Computed09-12-16
Contract Working Days50
Addl Days Granted0
Working Days Charged48
Percent Time Used96
Contractor(s)
BICK'S CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06164201
Totals1180000.000.003087940.21100.0

CountyTARRANT
HighwayIH0820
FromVARIOUS ROADWAYS IN
ToNORTH TARRANT COUNTY
CSJ6297-13-001
Proj IDRMC - 629713001
Work TypeGUARDRAIL INSTALLATION/REPAIR
 
0.0103701550.003942608.8099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-10-16
Work Began02-10-16
Work Completed
Time Computed02-11-16
Contract Working Days365
Addl Days Granted90
Working Days Charged451
Percent Time Used99
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154017
Totals3701550.000.003942608.8099.9

CountyTARRANT
HighwayUS0081
FromVARIOUS ROADWAYS IN
ToNORTH TARRANT COUNTY
CSJ6297-15-001
Proj IDRMC - 629715001
Work TypeROADSIDE MOWING
 
0.010678737.00593716.0087.4
Work Order05-16-16
Work Began05-16-16
Work Completed
Time Computed05-16-16
Contract Working Days120
Addl Days Granted0
Working Days Charged114
Percent Time Used95
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154216
Totals678737.000.00593716.0087.4

CountyTARRANT
HighwaySH0114
FromVARIOUS ROADWAYS IN (TOLLROAD)
ToNORTH TARRANT COUNTY
CSJ6298-85-001
Proj IDRMC - 629885001
Work TypeROUTINE SWEEPING AND DEBRIS REMOVAL
 
0.010525027.00484178.0092.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-16-16
Work Began03-17-16
Work Completed
Time Computed03-16-16
Contract Working Days365
Addl Days Granted0
Working Days Charged338
Percent Time Used92
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6298-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02164214
Totals525027.000.00484178.0092.2

CountyERATH
HighwayUS0067
FromVARIOUS LOCATIONS IN
ToERATH, HOOD AND SOMERVELL
CSJ6299-80-001
Proj IDRMC - 629980001
Work TypeFULL WIDTH MOWING
 
0.010308378.620.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174008
Totals308378.620.000.000.0

CountyWISE
HighwayUS0380
FromVARIOUS ROADWAYS IN WISE AND JACK
ToCOUNTIES
CSJ6299-89-001
Proj IDRMC - 629989001
Work TypeTHERMOPLASTIC REFLECTORIZED PAVEMENT MRK
 
0.0101196127.191152485.28100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-20-16
Work Began06-20-16
Work Completed11-16-17
Time Computed06-23-16
Contract Working Days83
Addl Days Granted15
Working Days Charged94
Percent Time Used95
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164001
Totals1196127.190.001152485.28100.0